AI summaryCabinet approves £10,386,479 capital slippage from 2025/26 into 2026/27 budget, funded by capital receipts. Slippage covers delayed housing acquisition, Elizabeth House window replacement, leisure centre solar panels and IT work.
Written from the decision and the officer reportPDF Pro
OutcomeDecided£10.39m added to 2026/27 capital budget
Money£10,386,479slippage from 2025/26 to 2026/27
What happens nextMonitored in 2026/27Reported in capital monitoring
Who it affectsCouncil capital projectsSchemes delayed from 2025/26
What was decided
Cabinet approved adding £10,386,479 to the 2026/27 Capital Budget for slippage, financed by capital receipts as budgeted in 2025/26. Report P5
Any issues identified for further consideration will be addressed by the relevant Portfolio Holder or, if required, by a further Cabinet report. Report P5
Why
The provisional 2025/26 capital outturn shows actual expenditure of £2,270,855 against an amended budget of £13,722,694, meaning unspent sums need to be carried forward. Report 1.2, 1.4
Table 3 lists projects with requested 2025/26 slippage added to existing 2026/27 budgets, including housing acquisition, Elizabeth House window replacement, leisure centre solar panels and IT workstreams. Report P10, P11
What happens next
Approved slippage will be monitored and reported as part of the 2026/27 capital budget monitoring report. Report P11
Work continues in the current financial year to ensure as many projects as possible are delivered within their intended timescales. Report P11
The money
£10,386,479 Total capital slippage from 2025/26 added to 2026/27 budget Report P5, P11
£2,619,000 Original 2025/26 capital expenditure budget agreed by Council Report 1.2
£13,722,694 2025/26 capital expenditure budget after amendments Report 1.2
£2,270,855 Actual capital expenditure to 31 March 2026 Report 1.4
£6,233,922 Accumulated capital receipts and grants at 1 April 2025 Report P6
£5,228,051 Remaining accumulated capital receipts and grants at 31 March 2026 Report P7
£2,500,000 Acquisition of housing to rent slippage Report P10
£1,858,270 Elizabeth House main window replacement 2026/27 total after slippage Report P10
Options considered
Chosen: Note the outturn and add slippage of £10,386,479 to 2026/27 Capital Budget. To continue projects not completed in 2025/26 Report P5
Rejected: Reject the draft 2025/26 outturn figure and requested slippage Report P5
Implications
Financial: This is a financial report dealing with capital receipts, grants, capital financing requirement and revenue contributions. Report P11
Legal: No direct legal implications arise from the report. Report P11
Equalities: Initial screening records no direct effects on equality across all strands. Report P11
Climate: Environmental and climate change implications are stated as not applicable. Report P11
Risk: Risk assessment is stated as not applicable. Report P11
Staffing: No human resources or staffing implications. Report P11
Other: No data protection or health and wellbeing implications; the report is restricted to financial implications of the Capital Budget. Report P11
Who and where
Residents waiting for council-purchased rental housing Report P10
Users of Elizabeth House council building Report P10
Users of Studley and Southam Leisure Centres Report P10
Council staff and service users of council IT systems Report P10
Visitors to Stratford-upon-Avon town centre affected by hostile vehicle mitigation works Report P11
Households placed in council temporary accommodation Report P10
Users of Recreation Ground paddling pool, play area and Stratford Leisure and Visitor Centre toilets Report P10
Residents served by the council's refuse and recycling collection Report P11
Timeline
February 2025: Council agreed the original 2025/26 capital expenditure budget of £2,619,000 Report 1.2
31 March 2026: End of 2025/26 financial year, with actual capital expenditure of £2,270,855 Report 1.4
6 July 2026: Cabinet approved £10,386,479 slippage from 2025/26 into 2026/27 capital budget Report P1
Plain English for the jargon
S.106: Section 106 planning obligations: payments or works from developers towards local infrastructure
CIL: Community Infrastructure Levy: a charge on certain new developments
Capital receipts: Money received by the council from the sale of capital assets
MRP: Minimum Revenue Provision: a charge to revenue to repay capital debt over time
Capital Financing Requirement: The council's underlying need to borrow to fund capital investment
HVM: Hostile Vehicle Mitigation: physical measures to protect against vehicle attacks
OSC: Overview and Scrutiny Committee
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item95
Resolved
That the Capital Budget for 2026/27 be increased by £10,386,479, for slippage, as listed in Appendix 3 to the agenda report, financed by the capital receipts as budgeted for in 2025/26. Note: This item is not subject to call-in to the OSC as it is not a key decision
Word for word from the decision Stratford-on-Avon published for this meeting.Source: democracy.stratford.gov.uk
Title: Capital Outturn 2025/26 and Capital Slippage
Lead Officer: Nicola Reynolds, Financial Accountant (01789 260608)
Portfolio Holder/ Lead Member: Councillor D Curtis
Summary This report provides The Cabinet with details of the provisional Capital Outturn 2025/26. Recommendation That the Capital Budget for 2026/27 be increased by £10,386,479, for slippage, as listed in Appendix 3, financed by the funding and capital receipts as budgeted for in 2025/26, and any issues identified for further consideration be addressed by: (1) The relevant Portfolio Holder for a point of clarification; and (2) If required, a further report to The Cabinet.
1 Background/Information 1.1 Table 1 Capital Budget Summary Position Table 1 summarises the Council’s estimated position with regard to accumulated capital receipts: Accumulated capital receipts and capital grants as at 1 April 2025 £6,233,922
Less expenditure for 2025/26 £(3,135,270) Plus new funds and financing in 2025/26 £3,111,139 Less Capital Financing Requirement Movement £(981,740) Remaining accumulated capital receipts and capital grants as at 31 March 2026 £5,228,051
1.2In February 2025 the Council agreed the capital expenditure budget for 2025/26 financial year totalling £2,619,000. With the amendments agreed by The Cabinet to date, the total Capital Expenditure Budget for the current year, including S.106, plus other additions, and slippage, as outlined in the 2024/25 Capital Budget Outturn Report, now totals £13,722,694. This is derived from the addition / removal of budget changes summarised in Table 2. 1.3 Table 2 – Capital expenditure –2025/26 2025/26 Gross Project/scheme expenditure budget £ Expenditure budget agreed as per The Cabinet, 10 2,619,000 February 2025 The Cabinet 7 July 2025 - Slippage of 2024/25 Items 4,905,530 9 Timothy’s Bridge Road headlease acquisition 777,000 Southam & Studley Leisure Centres - solar panels 400,000 EH main window replacement 361,000 Recreation Ground splash pad installation budget (150,000) transferred Recreation Ground paddling pool refurbishment and 150,000 additional water features Recreation Ground replacement play equipment and 100,000 sandpit accessibility improvements Acquisition of housing to rent 2,500,000 Uplift to Refuse Vehicles annual budget 45,000 S106 play area additions funded by commuted sums 113,389 S106 Gaydon/Lighthorne Community Hub design - 21,840 additional BREEAM costs S106 Wellesbourne CCTV Replacement 14,718 S106 Meon Vale CCTV & Wellesbourne & Meon Vale 9,010 CCTV Synetics CIL IFS 2025/26 agreed at The Cabinet 03/11/25 1,856,207 2025/26 expenditure budget 13,722,694
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Future of Southam United Football Club(1) That subject to the conditions identified in paragraph 1.4.3 of the agenda report, and subject to the above amend...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.