Capital Outturn 2025/26 and Capital Slippage

Decided Executive 4 papers

AI summaryCabinet approves £10,386,479 capital slippage from 2025/26 into 2026/27 budget, funded by capital receipts. Slippage covers delayed housing acquisition, Elizabeth House window replacement, leisure centre solar panels and IT work.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecided£10.39m added to 2026/27 capital budget
Money£10,386,479slippage from 2025/26 to 2026/27
What happens nextMonitored in 2026/27Reported in capital monitoring
Who it affectsCouncil capital projectsSchemes delayed from 2025/26

What was decided

Cabinet approved adding £10,386,479 to the 2026/27 Capital Budget for slippage, financed by capital receipts as budgeted in 2025/26. Report P5

Any issues identified for further consideration will be addressed by the relevant Portfolio Holder or, if required, by a further Cabinet report. Report P5

Why

The provisional 2025/26 capital outturn shows actual expenditure of £2,270,855 against an amended budget of £13,722,694, meaning unspent sums need to be carried forward. Report 1.2, 1.4

Table 3 lists projects with requested 2025/26 slippage added to existing 2026/27 budgets, including housing acquisition, Elizabeth House window replacement, leisure centre solar panels and IT workstreams. Report P10, P11

What happens next

Approved slippage will be monitored and reported as part of the 2026/27 capital budget monitoring report. Report P11

Work continues in the current financial year to ensure as many projects as possible are delivered within their intended timescales. Report P11

The money

  • £10,386,479 Total capital slippage from 2025/26 added to 2026/27 budget Report P5, P11
  • £2,619,000 Original 2025/26 capital expenditure budget agreed by Council Report 1.2
  • £13,722,694 2025/26 capital expenditure budget after amendments Report 1.2
  • £2,270,855 Actual capital expenditure to 31 March 2026 Report 1.4
  • £6,233,922 Accumulated capital receipts and grants at 1 April 2025 Report P6
  • £5,228,051 Remaining accumulated capital receipts and grants at 31 March 2026 Report P7
  • £2,500,000 Acquisition of housing to rent slippage Report P10
  • £1,858,270 Elizabeth House main window replacement 2026/27 total after slippage Report P10

Options considered

  • Chosen: Note the outturn and add slippage of £10,386,479 to 2026/27 Capital Budget. To continue projects not completed in 2025/26 Report P5
  • Rejected: Reject the draft 2025/26 outturn figure and requested slippage Report P5

Implications

  • Financial: This is a financial report dealing with capital receipts, grants, capital financing requirement and revenue contributions. Report P11
  • Legal: No direct legal implications arise from the report. Report P11
  • Equalities: Initial screening records no direct effects on equality across all strands. Report P11
  • Climate: Environmental and climate change implications are stated as not applicable. Report P11
  • Risk: Risk assessment is stated as not applicable. Report P11
  • Staffing: No human resources or staffing implications. Report P11
  • Other: No data protection or health and wellbeing implications; the report is restricted to financial implications of the Capital Budget. Report P11

Who and where

  • Residents waiting for council-purchased rental housing Report P10
  • Users of Elizabeth House council building Report P10
  • Users of Studley and Southam Leisure Centres Report P10
  • Council staff and service users of council IT systems Report P10
  • Visitors to Stratford-upon-Avon town centre affected by hostile vehicle mitigation works Report P11
  • Households placed in council temporary accommodation Report P10
  • Users of Recreation Ground paddling pool, play area and Stratford Leisure and Visitor Centre toilets Report P10
  • Residents served by the council's refuse and recycling collection Report P11

Timeline

  • February 2025: Council agreed the original 2025/26 capital expenditure budget of £2,619,000 Report 1.2
  • 31 March 2026: End of 2025/26 financial year, with actual capital expenditure of £2,270,855 Report 1.4
  • 6 July 2026: Cabinet approved £10,386,479 slippage from 2025/26 into 2026/27 capital budget Report P1

Plain English for the jargon

  • S.106: Section 106 planning obligations: payments or works from developers towards local infrastructure
  • CIL: Community Infrastructure Levy: a charge on certain new developments
  • Capital receipts: Money received by the council from the sale of capital assets
  • MRP: Minimum Revenue Provision: a charge to revenue to repay capital debt over time
  • Capital Financing Requirement: The council's underlying need to borrow to fund capital investment
  • HVM: Hostile Vehicle Mitigation: physical measures to protect against vehicle attacks
  • OSC: Overview and Scrutiny Committee
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item95

Resolved

That the Capital Budget for 2026/27 be increased by £10,386,479, for slippage, as listed in Appendix 3 to the agenda report, financed by the capital receipts as budgeted for in 2025/26. Note: This item is not subject to call-in to the OSC as it is not a key decision
Word for word from the decision Stratford-on-Avon published for this meeting. Source: democracy.stratford.gov.uk

Follow this further

Built from Stratford-on-Avon's papers

What the report saysPro

Report to The Cabinet, 8 pages

The Cabinet 6 July 2026

Title: Capital Outturn 2025/26 and Capital Slippage

Lead Officer: Nicola Reynolds, Financial Accountant (01789 260608)

Portfolio Holder/ Lead Member: Councillor D Curtis

Summary This report provides The Cabinet with details of the provisional Capital Outturn 2025/26. Recommendation That the Capital Budget for 2026/27 be increased by £10,386,479, for slippage, as listed in Appendix 3, financed by the funding and capital receipts as budgeted for in 2025/26, and any issues identified for further consideration be addressed by: (1) The relevant Portfolio Holder for a point of clarification; and (2) If required, a further report to The Cabinet.

1 Background/Information 1.1 Table 1 Capital Budget Summary Position Table 1 summarises the Council’s estimated position with regard to accumulated capital receipts: Accumulated capital receipts and capital grants as at 1 April 2025 £6,233,922

Less expenditure for 2025/26 £(3,135,270) Plus new funds and financing in 2025/26 £3,111,139 Less Capital Financing Requirement Movement £(981,740) Remaining accumulated capital receipts and capital grants as at 31 March 2026 £5,228,051

1.2In February 2025 the Council agreed the capital expenditure budget for 2025/26 financial year totalling £2,619,000. With the amendments agreed by The Cabinet to date, the total Capital Expenditure Budget for the current year, including S.106, plus other additions, and slippage, as outlined in the 2024/25 Capital Budget Outturn Report, now totals £13,722,694. This is derived from the addition / removal of budget changes summarised in Table 2. 1.3 Table 2 – Capital expenditure –2025/26 2025/26 Gross Project/scheme expenditure budget £ Expenditure budget agreed as per The Cabinet, 10 2,619,000 February 2025 The Cabinet 7 July 2025 - Slippage of 2024/25 Items 4,905,530 9 Timothy’s Bridge Road headlease acquisition 777,000 Southam & Studley Leisure Centres - solar panels 400,000 EH main window replacement 361,000 Recreation Ground splash pad installation budget (150,000) transferred Recreation Ground paddling pool refurbishment and 150,000 additional water features Recreation Ground replacement play equipment and 100,000 sandpit accessibility improvements Acquisition of housing to rent 2,500,000 Uplift to Refuse Vehicles annual budget 45,000 S106 play area additions funded by commuted sums 113,389 S106 Gaydon/Lighthorne Community Hub design - 21,840 additional BREEAM costs S106 Wellesbourne CCTV Replacement 14,718 S106 Meon Vale CCTV & Wellesbourne & Meon Vale 9,010 CCTV Synetics CIL IFS 2025/26 agreed at The Cabinet 03/11/25 1,856,207 2025/26 expenditure budget 13,722,694

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Outturn P1-12 25-26Appendix 1 6 pages Download
PDF
Committed & Uncommitted S106 & CIL 310326Appendix 2 5 pages Download
PDF
Capital Slippage 310326Appendix 3 1 pages Download
PDF
Capital Outturn 2025/26 and Capital SlippageReport 8 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Stratford-on-Avon

Search all
  1. Capital Outturn 2025/26 and Capital SlippageThis decision
  2. Capital Outturn 2024/25 and Capital SlippageDecided
  3. Capital Outturn 2023/24 and Capital SlippageDecided
  4. Capital Outturn 2022/23 and Capital SlippageAgreed
  5. Capital Outturn 2021/22 and Capital SlippageDecided
  6. Capital Outturn 2020/21 and Capital SlippageDecided

More from Stratford-on-Avon The Cabinet

All decisions
MeetingDecisionOutcome
2 Nov 2026 Future of Southam United Football Club(1) That subject to the conditions identified in paragraph 1.4.3 of the agenda report, and subject to the above amend... Decided Open
2 Nov 2026 Strategic Risk RegisterThat the , attached as Appendix 1 to the agenda report, be endorsed. Note: In accordance with the Council’s Constitut... Decided Open
2 Nov 2026 Options for Boosting the Supply of Housing Land Update Report(1) That the progress in delivering the Housing Land Supply Action Plan, the September 2026 housing land supply calcu... Noted Open
2 Nov 2026 Youth Catalyst Project – Service Specification and Permission to Tender(1) That permission to procure a Youth Catalyst Project provision to meet the requirements of the specification, as d... Approved Open
2 Nov 2026 Revenue Budget Monitoring Period 1 - 6 2026/27(1) That the actual net variance as at Period 6, and the estimated revenue outturn for 2026/27, be received; and (2) ... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies