Building Cleaning Contract

Approved Executive 1 paper

Executive approved this item on Monday 29 October 2007. Below is the council's own wording, with the papers it was decided on.

Item564

Resolved

(1) That the Head of Environment be given delegated authority to extend the Building Cleaning Services Contract until 31 March 2008. (2) That the tender evaluation criteria for the Office and Toilet Cleaning Contract, as presented, be received and adopted. NOTE: This item is subject to call-in to OSC B.
Word for word from the decision Stratford-on-Avon published for this meeting. Source: democracy.stratford.gov.uk

Follow this further

Built from Stratford-on-Avon's papers

What the report saysPro

Report to Executive, 2 pages

Recommendation

(1) That the Executive give delegated authority to the Head of Environmental Services to extend the Building Cleaning Services Contract until 31 March 2008. (2) That the Executive agrees the tender evaluation criteria described in this report for use in the tendering process for the renewal of the Office and Toilet Cleaning Contract.

1 BACKGROUND/INFORMATION 1.1 On 31 October 2005 (minutes 55) the Executive resolved to approve the extension of the existing Building Cleaning contract. 1.2 Under the OJEU procedure used to originally source the existing contractor in 2003, the existing contract can legally be extended by a further 6 months. Extending the Building Cleaning contract for a further 6 months will benefit the Council by giving it certainty of affordable costs for the entire 2007/2008 financial year at current rates. In addition, it is operationally beneficial to retain the existing satisfactory service provided by the current contractor, Regent Cleaning Services. The Contract will go out to tender and a new Contract will be in place by 1st April 2008. 1.3 The tendering process for the renewal of this contract is to start in November 2007. It is proposed that the evaluation criteria to be used in this process will be: - Ability to deliver service required as determined through: Management arrangements 10% Health and Safety arrangements 10% Environmental procedures 10% Staffing – resources to be used 10% Operating procedures 10% And Price 50%

2 OPTIONS AVAILABLE TO THE COMMITTEE 2.1 Adopt the Recommendation as detailed. 2.2 Decline to adopt the Recommendation as detailed and re-tender the contract with the inherent uncertainty of costs and the likely adverse affect on budgets. 2.3 Agree the tender evaluation criteria as proposed or ask for alternative criteria to be developed.

3 MEMBERS’ COMMENTS 3.1 Include any comments from Members in response to the consultation on the report.

4 IMPLICATIONS OF THE PROPOSAL 4.1 Legal 4.1.1 Legal will complete the necessary Deed of Variation. 4.2 Financial 4.2.1. The extension of this contract will ensure building cleaning costs will be contained within the budget provision made to the end of the financial year. 4.3 Environmental 4.3.1 Head of Service comments have been included in the Report. 4.4 Corporate Strategy 4.4.1 This will help deliver efficient Council services. 4.5 Equality Impact Assessment 4.5.1 The Contractors have a responsibility to ensure they have an equality and diversity policy in place.

5 RISK ASSESSMENT

6 CONCLUSION It is considered to be in the Council’s best financial interests to extend the current Cleaning Services Contract pending the re-tendering exercise. ROBERT WEEKS Head of Environment

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Building Cleaning ContractReport 2 pages DownloadRead as text

More from Stratford-on-Avon Executive

All decisions
MeetingDecisionOutcome
28 Jul 2008 Service Excellence StatementsRESOLVED : 1) That the progress made in 2007/08 be noted; and, 2) That the updated Statements of Service Excellence a... Noted Open
28 Jul 2008 State of the DistrictThat the foregoing actions in response to the comments made by Council on the report be endorsed. NOTE: This item is ... Decided Open
28 Jul 2008 Request from Audit Committee - Change of NameThat the Executive be renamed as ‘Cabinet’. NOTE: This item is not subject to call-in. Decided Open
28 Jul 2008 Fundamental Budget ReviewRESOLVED : 1) That the proposal to create a Budget Working Group to oversee the Budget Review, as summarised in the p... Approved Open
28 Jul 2008 Interim Procurement Strategy1) That the interim Procurement Strategy 2008 - 2012, as presented, be received and adopted; and, 2) That progress on... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies