Resolved
That the position on the revenue expenditure for the period 1 April to 31 December 2007, together with the reasons for the variances between expenditure and budgets, be noted. NOTE: This item is subject to call-in to OSC B
Executive noted this item on Monday 11 February 2008. Below is the council's own wording, with the papers it was decided on.
Resolved
That the position on the revenue expenditure for the period 1 April to 31 December 2007, together with the reasons for the variances between expenditure and budgets, be noted. NOTE: This item is subject to call-in to OSC B
EXECUTIVE 11 FEBRUARY 2008 SUBJECT: REVENUE BUDGET MONITORING P1 – P9 2007/08 LEAD OFFICER: RICHARD BURRELL CONTACT ON 01789 260404 LEAD MEMBER/ PORTFOLIO HOLDER: COUNCILLOR ORGAN
SUMMARY To update members of the Executive on the overall financial position of the authority. This report provides members with the Revenue Monitoring position for the period 1 - 9 of 2007/08 and reasons for variances between spend to date and period budget. RECOMMENDATION (1) That the position on the revenue expenditure for period 1-9 of 2007/08 is received and the Executive identifies any issues that it wishes to be considered further:
by a further report to the Executive; by the Portfolio-holder; by a report to the relevant Overview & Scrutiny Committee by the relevant Head of Service or Strategic Director.
1 BACKGROUND/INFORMATION 1.1 This report is a high level summary, which is split into two main areas. The budgets for those services provided directly (Direct Services) to the public and those to internal customers (Support Services). 1.2 Items specifically listed in this report up to period 9 are where there is a budget variance of either +/- £40,000, or greater than 20%. Additional items may be included at the discretion of the Head of Resources. 2 LEGAL/FINANCIAL/ENVIRONMENTAL/CORPORATE STRATEGY 2.1.1 BUDGET MONITORING PERIOD 9 2.1.2 The global position for the Council at the end of period 9 is an overall unfavourable variance of £170,644. Summary Table Description Variance Other Variations Real Variance £ £ £ Direct Services 281,540 -65,930 215,610 Support Services -120,423 75,457 -44,966 TOTAL 161,117 9,527 170,644 The following table shows how this Real Variance reported to Executive has changed through the year.
Period Reported to Executive Real Variance Period 1 to 3 £62,015 Period 1 to 5 £230,883 Period 1 to 7 £261,206 Period 1 to 9 (above) £170,644
Appendix 1 shows the Summary position as at period 9. A detailed analysis of the significant variances follows:
2.2Budget Monitoring (Direct Services) Period 1-9 2007/08, Appendix 2, shows an unfavourable variance of £281,540 against a profiled budget of £7,876,312. 2.2.1 Appendices 3 & 4 gives reasons for the main variances in Direct Services. Some of the more significant real variances are detailed below:- 2.2.2 Head of Revenues & Housing • Council Tax This unfavourable variance of £50,397 relates mainly to income not received but expected from cases taken to court. • Housing Benefits The unfavourable variance of £108,960 relates to more Housing Benefit paid out than subsidy income received to date. The Council is required to forecast benefit payments to DWP. Given that these payments are c£18m per annum this variance represents 0.6% of total payments. 2.2.3 Head of Resources • Corporate Estates shows a favourable variance of £117,322 being the income expected for the current and previous years in respect of a new lease agreement. 2.2.4 Head of Community Services • Off Street Parking shows a unfavourable variance of £146,979 is mainly attributable to the floods which disrupted parking. Price increases were implemented on the 1st of October, 2007. 2.2.5 Head of Environment • Environmental Health shows a favourable variance of £74,252 which is the result of additional income from pest control work and money from the Food Standards Agency. • Domestic Refuse Collection shows an unfavourable variance of £74,252 which has resulted from an unbudgeted performance clause which pays a bonus when recycling rates have been achieved and through using a lower RPI increase than the industry rate. • Street Cleansing shows an expected unfavourable variance of £67,351 the result of additional roads and inflationary increases being more than budgeted.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Rev budget monitoring AppendixAppendix | 247 KB | Download |
PDF |
Revenue Budget Monitoring Report for Periods 1: 9 2007/08Report | 59 KB | DownloadRead as text |
Follow Executive at Stratford-on-Avon and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 28 Jul 2008 | Service Excellence StatementsRESOLVED : 1) That the progress made in 2007/08 be noted; and, 2) That the updated Statements of Service Excellence a... | Noted | Open |
| 28 Jul 2008 | State of the DistrictThat the foregoing actions in response to the comments made by Council on the report be endorsed. NOTE: This item is ... | Decided | Open |
| 28 Jul 2008 | Request from Audit Committee - Change of NameThat the Executive be renamed as ‘Cabinet’. NOTE: This item is not subject to call-in. | Decided | Open |
| 28 Jul 2008 | Fundamental Budget ReviewRESOLVED : 1) That the proposal to create a Budget Working Group to oversee the Budget Review, as summarised in the p... | Approved | Open |
| 28 Jul 2008 | Interim Procurement Strategy1) That the interim Procurement Strategy 2008 - 2012, as presented, be received and adopted; and, 2) That progress on... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.