CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Stratford-on-Avon District Council
Overview and Scrutiny Committee B, Wednesday 8 July 2009

Update from Task Groups

Decided Scrutiny 1 paper

Overview and Scrutiny Committee B decided this item on Wednesday 8 July 2009. Below is the council's own wording, with the papers it was decided on.

Item149

Resolved

That the report, as amended, be referred to the Cabinet. Grounds Maintenance The Chairman then invited Robert Weeks to answer questions from the Committee on his report regarding the Grounds Maintenance Contract Task and Finish Group. After discussion on who was responsible for unmown verges, the Chairman suggested that the Task and Finish Group reconvene to reconsider some of the issues raised. However Robert Weeks felt most of the issues will be addressed in the next quarterly service report so a meeting was not deemed necessary at this stage.
Word for word from the decision Stratford-on-Avon published for this meeting. Source: democracy.stratford.gov.uk

Follow this further

Built from Stratford-on-Avon's papers

What the report saysPro

Report to Overview and Scrutiny Committee B, 6 pages

STRATFORD-ON-AVON_ DISTRICT COUNCIL

OVERVIEW _and SCRUTINY COMMITTEE 'B'

TASK and FINISH GROUP

BUSINESS ENTERPRISE REPORT

JUNE 2009 GROUP'S MANDATE

At its meeting on 14th January the OSC B Committee agreed a Task and Finish Group would undertake to examine the Authority's approach to businesses in regard to planning applications, i.e how these applications are initially addressed with the applicant, subsequent communications

and in particular the speed of determination.

MEMBERS OF THE BUSINESS ENTERPRISE TASK and FINISH GROUP

George Atkinson, Lynne Bowring and Sir William Lawrence.

CORPORATE OBJECTIVES -

COUNCIL'S PHILOSOPHY

* A district where business and enterprise can flourish.

( 2007/08 key events )

* Expanding local businesses are able to remain in the District.

( Corporate Strategy Priorities 2008 - 2012 ) ENCOURAGING BUSINESS AND EMPLOYMENT

x

* The encouragement of small business development.

* The development of local employment opportunities.

( An even better place to live and work report. )

* Planning process needs speeding up.

( Daily Telegraph 13th March 2009 )

* Locally we must find ways to support people and businesses....

( Clir Fradgley, First Feature January 2009 )

METHODOLOGY / FEEDBACK

The Group decided to survey all members and agreed a questionnaire as per the following page. The idea was to extract independent opinions based upon members’ involvement with individual cases. It was hoped a

broad level of opinion would be forthcoming.

The paucity of replies at only 4 was, to say the least, disappointing - in the circumstances the sample given does not provide sufficient reaction to come to a reasoned conclusion; however some sample case studies are

given in this report. Planning Questionnaire in relation to Business Enterprise

1) Have you given/commented on a business related planning

application in your Ward in the last 18 months? Yes/No

2) Please give the applicant's name and application reference if known.

3) Did you support the application? Yes/No

4) Was the application granted? Yes/No

5) Do you hold an opinion about the way the application was determined? If so, please give details.

6) Was the applicant asked to pay up front costs before it was granted?

( for example, for a bat survey, environmental assessment et cetera ) Yes/No

If yes, please give details.

7) How long did it take for the planning decision to be made after submission?

8) Do you have any comment about time span?

9) Of the applications that you have supported, did your opinion reflect in the department's attitude? ( please give specific details.)

10) In your opinion, was the officer's/committee’s decision in determining the application "business like"? Yes/No

Please feel free to elaborate, where you see fit, to substantiate your answer. 3 8 week turn round

CASE STUDIES

Given that the aim is to turn an application around ( decision time ) is 8 weeks and that the 'clock’ starts at the valid stage, the following

cases suggest that objective is not being achieved: -

07/03065/FUL - Valid October 2007

- Committee 2nd June 2009 08/00307/FUL - Member reported 8 month gestation term. 08/01462/FUL - Submitted circa April 2008 - disputes over up front

costs demands and technical re~submission arranged.

Eventually granted February 2009.

08/00928/FUL - Valid March 2008, refused @ P&R but re-submitted

with minor amendments and granted circa March 2009.

07/03591/FUL - A Green Belt site but holding business activity since circa 1924, The application was to consolidate, with the same volume, run down but usable units into a purpose built single unit for multi-occupancy. Up front costs for a bat survey were demanded, however continued, repeated queries frustrated the applicant who withdrew after some 12 months debate.

4 HABANERO BUSINESS CONSULTANCY

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Update from Task GroupsReport 6 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 27 attended
JA
Councillor John AppletonCommittee Member, present
PB
Councillor Peter BarnesCommittee Member, apologies
JF
Councillor Jennifer FradgleyCommittee Member, present
VH
Councillor Valerie HobbsChairman, present
JH
Councillor John HornerCommittee Member, present
KJ
Councillor Kim JamesCommittee Member, apologies
SJ
Councillor Susan JunedCommittee Member, present
SW
Councillor Sir William Lawrence BtVice-Chairman, present as substitute
SM
Councillor Sue MainCommittee Member, present
CM
Councillor Christopher MillsCommittee Member, present
AP
Councillor Andrew PatrickCommittee Member, present
GR
Councillor Gillian RoacheCommittee Member, apologies

All 27 on the meeting page

On this subject at Stratford-on-Avon

Search all
  1. Update from Task GroupsThis decision
  2. Update on Task and Finish GroupsAgreed
  3. Update on Task and Finish GroupsAgreed
  4. Update on Task and Finish GroupsAgreed
  5. Update on Task and Finish GroupsAgreed
  6. Update on Task and Finish GroupsAgreed

More from Stratford-on-Avon Overview and Scrutiny Committee B

All decisions
MeetingDecisionOutcome
24 Mar 2010 Focus on - The Future Committee Structure and OSC MeetingsThat the presentation be noted and the Committee’s comments be referred to the Committee Structure Working Group for ... Noted Open
24 Mar 2010 Exception Reporting on Service Areas(1) That the report be noted. Planning Services Members felt that the Council needed to have a policy in place to dea... Noted Open
24 Mar 2010 State of the District Report(1) That the report be noted; (2) That Officers ensure that all previous comments made by the Committee given in Appe... Noted Open
24 Mar 2010 Planning Committee - Update(1) That minutes 336, 483 and 696 be noted. Noted Open
24 Mar 2010 Warwickshire Overview & Scrutiny BoardThat the Warwickshire Overview and Scrutiny Board report of 3 March 2010 be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies