That the report, as amended, be referred to the Cabinet. Grounds Maintenance The Chairman then invited Robert Weeks to answer questions from the Committee on his report regarding the Grounds Maintenance Contract Task and Finish Group. After discussion on who was responsible for unmown verges, the Chairman suggested that the Task and Finish Group reconvene to reconsider some of the issues raised. However Robert Weeks felt most of the issues will be addressed in the next quarterly service report so a meeting was not deemed necessary at this stage.
Word for word from the decision Stratford-on-Avon published for this meeting.Source: democracy.stratford.gov.uk
Report to Overview and Scrutiny Committee B, 6 pages
STRATFORD-ON-AVON_ DISTRICT COUNCIL
OVERVIEW _and SCRUTINY COMMITTEE 'B'
TASK and FINISH GROUP
BUSINESS ENTERPRISE REPORT
JUNE 2009 GROUP'S MANDATE
At its meeting on 14th January the OSC B Committee agreed a Task and Finish Group would undertake to examine the Authority's approach to businesses in regard to planning applications, i.e how these applications are initially addressed with the applicant, subsequent communications
and in particular the speed of determination.
MEMBERS OF THE BUSINESS ENTERPRISE TASK and FINISH GROUP
George Atkinson, Lynne Bowring and Sir William Lawrence.
CORPORATE OBJECTIVES -
COUNCIL'S PHILOSOPHY
* A district where business and enterprise can flourish.
( 2007/08 key events )
* Expanding local businesses are able to remain in the District.
( Corporate Strategy Priorities 2008 - 2012 ) ENCOURAGING BUSINESS AND EMPLOYMENT
x
* The encouragement of small business development.
* The development of local employment opportunities.
( An even better place to live and work report. )
* Planning process needs speeding up.
( Daily Telegraph 13th March 2009 )
* Locally we must find ways to support people and businesses....
( Clir Fradgley, First Feature January 2009 )
METHODOLOGY / FEEDBACK
The Group decided to survey all members and agreed a questionnaire as per the following page. The idea was to extract independent opinions based upon members’ involvement with individual cases. It was hoped a
broad level of opinion would be forthcoming.
The paucity of replies at only 4 was, to say the least, disappointing - in the circumstances the sample given does not provide sufficient reaction to come to a reasoned conclusion; however some sample case studies are
given in this report. Planning Questionnaire in relation to Business Enterprise
1) Have you given/commented on a business related planning
application in your Ward in the last 18 months? Yes/No
2) Please give the applicant's name and application reference if known.
3) Did you support the application? Yes/No
4) Was the application granted? Yes/No
5) Do you hold an opinion about the way the application was determined? If so, please give details.
6) Was the applicant asked to pay up front costs before it was granted?
( for example, for a bat survey, environmental assessment et cetera ) Yes/No
If yes, please give details.
7) How long did it take for the planning decision to be made after submission?
8) Do you have any comment about time span?
9) Of the applications that you have supported, did your opinion reflect in the department's attitude? ( please give specific details.)
10) In your opinion, was the officer's/committee’s decision in determining the application "business like"? Yes/No
Please feel free to elaborate, where you see fit, to substantiate your answer. 3 8 week turn round
CASE STUDIES
Given that the aim is to turn an application around ( decision time ) is 8 weeks and that the 'clock’ starts at the valid stage, the following
cases suggest that objective is not being achieved: -
07/03065/FUL - Valid October 2007
- Committee 2nd June 2009 08/00307/FUL - Member reported 8 month gestation term. 08/01462/FUL - Submitted circa April 2008 - disputes over up front
costs demands and technical re~submission arranged.
Eventually granted February 2009.
08/00928/FUL - Valid March 2008, refused @ P&R but re-submitted
with minor amendments and granted circa March 2009.
07/03591/FUL - A Green Belt site but holding business activity since circa 1924, The application was to consolidate, with the same volume, run down but usable units into a purpose built single unit for multi-occupancy. Up front costs for a bat survey were demanded, however continued, repeated queries frustrated the applicant who withdrew after some 12 months debate.
4 HABANERO BUSINESS CONSULTANCY
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Overview and Scrutiny Committee B at Stratford-on-Avon and we tell you when its next papers are published, before the meeting rather than after it.
Exception Reporting on Service Areas(1) That the report be noted. Planning Services Members felt that the Council needed to have a policy in place to dea...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.