Resolved

Agreed: That Councillors Bromwich, Curtis, Feilding, Rolfe and Whalley-Hoggins (with one further Conservative appointment to be confirmed) be appointed to the Stratford-on-Avon (SDC) & Warwick District Council (WDC) Merger: Lessons Learnt Review Task and Finish Group (T&FG).
Word for word from the decision Stratford-on-Avon published for this meeting. Source: democracy.stratford.gov.uk

Follow this further

Built from Stratford-on-Avon's papers

What the report saysPro

Report to Overview and Scrutiny Committee, 3 pages

Scoping Document Stratford & Warwickshire Merger: Lessons Learnt Task and Finish Group Title: Review

To be determined. Membership of the Group: (including any invitation to non- councillors)

Area for Investigation: This area of investigation covers the whole Council. (Directorate/Service Area)

Key Officer Contacts: Chief Executive: David Buckland Deputy Chief Executive: Tony Perks

Objectives

To identify why the proposed merger between Stratford- on-Avon District Council and Warwick District Council ended, what lessons can be learnt from this and identify any benefits that have been derived from the merger Summary of overall aims process. and intended outcomes:

That the Task and Finish Group identify what caused the end of the merger and lessons that can be identified from Indicators of success the end of the merger.

Furthermore, the Task and Finish Group can identify successful parts of the merger in hopes that further progress in these areas could be made in the future.

Scope

 To understand why the merger ended. In Scope:  To explain what factors contributed to the end of the merger. [Define what the scope of  To layout what lessons the Council can learn from review is i.e. to understand the ending of the merger. which issues)  To understand how the Councils can work constructively together going forward.

Excluded from Scope:  While budgetary pressures were part of the reasoning for the merger this task and finish group should not speculate on future budgets as a task and finish group will be set up to review the next [Define the exclusions from the budget. scope of the review]  The Task and Finish group should consciously avoid seeking to assign blame for the end of the merger and should focus on events as they occurred.

Council and Partner Involvement

Senior Officers and Councillors that were involved in the Who would need to be merger. Furthermore, if possible, Councillors from Warwick involved from the Council? District Council should be involved.

Which of our partners,  Warwick District Council to be asked. stakeholders and Members of the community should we discuss this with?

Review Resources

Evidence:  Reports that guided the merger from the LGA and Deloitte etc. [what evidence needs to be  The report from the Task and Finish Group on the gathered and how) end of working with Cherwell District Council/South Northants.  Any other information pertaining to merger which may be required by the Task and Finish Group.

Witnesses:  Officers and Cabinet Members involved in the merger. [Who to see and when]

Site visits: N/A

[Details of site visits and when they will be held if appropriate]

Consultation: N/A

[Is there any consultation which needs to be undertaken to feed into the review?]

[Do findings need to be published for consultation before making final recommendations?]

Expert Advice: N/A

[Does the Task & Finish Group require expert advice support due to the nature of the review?]

Dangers/ Barriers/Risks

 The Task and Finish Group assigns blame which could undermine the continued working with Warwick District Council. What are the risks to the  The review could further damage the relationship review? between the two councils.  Because the merger affected all parts of the Council there is a risk that the review expands well outside its initial scope.

Timescales

Anticipated Review Start To be determined. Date:

Frequency of Meetings (and To be determined. any agreed dates):

Anticipated Reporting Date To be determined. to OSC:

Date to evaluate impact: To be determined.

[A review in six to twelve months (dependent on outcomes) at this point deciding to either re scrutinise this matter, with a different task and finish group, or sign it off as the indicators of success have been achieved]

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Update on Task and Finish GroupsReport 3 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Stratford-on-Avon

Search all
  1. Update on Task and Finish GroupsThis decision
  2. Minute 618 - Task and Finish Group: Privately Managed Public Open Spaces, Flood Alleviation Schemes, and Estate RoadsApproved
  3. Minute 374 - Task and Finish Group: Privately Managed Public Open Spaces, Flood Alleviation Schemes, and Estate RoadsNoted
  4. Task and Finish Group: Budget 2025/26Decided
  5. Minute 36 - Task and Finish Group: Housing AssociationsAgreed
  6. Update on Task and Finish GroupsAgreed

More from Stratford-on-Avon Overview and Scrutiny Committee

All decisions
MeetingDecisionOutcome
28 Oct 2026 Urgent BusinessThat, pursuant to Section 100A (4) of the Local Government Act 1972 (as amended), the public be excluded from the rem... Noted Open
2 Sep 2026 Cost of LivingThat, in principle, a Task and Finish Group on the Cost of Living would be formed at the next meeting of the Overview... Decided Open
2 Sep 2026 Urgent Business - The Three TunsThat, pursuant to Section 100A (4) of the Local Government Act 1972 (as amended), the public be excluded from the rem... Noted Open
27 May 2026 Start time of meetingsThat the meetings of the Overview and Scrutiny Committee during 2026/27 commence at 10.00 a.m. Decided Open
27 May 2026 The Cabinet Meeting - 13 April 2026It was agreed that the Climate Change Project Officer would be asked to provide an assessment of the project. It was ... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies