Stratford-on-Avon District Council
The Cabinet, Monday 7 February 2011

Capital Budget Monitoring

Approved Executive 2 papers

The Cabinet approved this item on Monday 7 February 2011. Below is the council's own wording, with the papers it was decided on.

Item700

Resolved

(1) That the position on capital expenditure and income for period 1-9 of 2010/11 be received; and (2) That the amendments detailed in the preamble to this Minute be approved. Note: This item is subject to call-in to the OSC.
Word for word from the decision Stratford-on-Avon published for this meeting. Source: democracy.stratford.gov.uk

Follow this further

Built from Stratford-on-Avon's papers

What the report saysPro

Report to The Cabinet

STRATFORD-ON-AVON DISTRICT COUNCIL CAPITAL BUDGET MONITORING PERIOD 1-9 2010/11

Slippage Forecast agreed at Amendments Committed Expenditure Original 21st June proposed 7th Amended April- Actual April - 1st January - Estimate 2010 Feb. 2011 Estimate December December to 31st March Budget 2010/11 Cabinet Cabinet 2010/11 2010/11 2010/11 2011 Remaining

£ £ £ £ £ £ £ £ GROSS EXPENDITURE

Head of Revenues & Housing 1,180,192 590,084 0 1,965,276 0 1,077,877 832,297 55,102

Head of Change & Performance 733,000 265,348 0 998,348 6,147 398,290 356,911 237,000

Head of Planning Services 350,000 324,668 0 674,668 110,000 -44 4,668 560,044

Head of Community Services 75,000 204,115 13,964 1,420,690 173,999 106,403 1,086,366 53,922

World Class Stratford 340,000 1,347,150 0 1,742,182 197,349 945,670 95,351 503,812

Head of Environment 50,000 669,123 0 736,123 172,271 361,483 45,160 157,209

Head of Member Services 0 0 0 0 0 0 0 0

Head of Customer Services 0 7,894 0 7,894 0 4,883 0 3,011

Head of Resources 455,220 235,790 0 1,353,712 31,828 31,693 763,375 526,816

TOTAL 3,183,412 3,644,172 13,964 8,898,893 691,594 2,926,256 3,184,128 2,096,915

FINANCED FROM:- Disabled facilities Grants 192,000 192,000 278,000 -86,000 Right to Buy Receipts : Clawback 0 0 0 0 Section 106 Contribution 273,370 552,568 13,964 1,752,580 0 0 0 1,752,580

Disposal of assets receipts 1,250,000 0 0

WCC Grant 0 198,489 95,489 103,000

Revenue Contribution 0 472,220 472,220

Regional Housing Pot 0 70,000 70,000

Lottery Grant 0 16,444 16,444

AWM Grant - WCS and others 0 631,567 23,909 710,508 951,409 -240,901

Loan Repayments 10,000 10,000 10,000 Total/Estimated Receipts 1,725,370 1,184,135 37,873 3,422,241 0 1,324,898 0 2,097,343

Use of SDC Receipts 1,458,042 2,460,037 -23,909 5,476,652 691,594 1,601,358 3,184,128 -428 Total Finance Required 3,183,412 3,644,172 13,964 8,898,893 691,594 2,926,256 3,184,128 2,096,915

Cap Bud Mon P1-9 1011.xls, Appendix A inc forecast 1/6 24/01/2011 STRATFORD-ON-AVON DISTRICT COUNCIL CAPITAL BUDGET MONITORING PERIOD 1-9 2010/11

Slippage Forecast agreed at Amendments Committed Expenditure Original 21st June proposed 7th Amended April- Actual April - 1st January - Estimate 2010 Feb. 2011 Estimate December December to 31st March Budget 2010/11 Cabinet Cabinet 2010/11 2010/11 2010/11 2011 Remaining

£ £ £ £ £ £ £ £

Use of Capital Receipts: Acc. Capital Receipts b/fwd 15,633,777 15,633,777 15,633,777 15,633,777 (Surplus) / Deficit on Year 1,458,042 5,476,652 1,601,358 3,184,128 Accumulated Capital Receipts 14,175,735 10,157,125 14,032,419 12,449,649 c/fwd

Head of Revenues & Housing

Affordable Housing Investment 596,822 290,739 887,561 0 571,088 316,473 0 Programme

Shipston S.106 - London Rd. 33,370 33,370 0 33,370 0 0

Earlswood S.106 0 230,000 230,000 0 0 230,000 0

Disabled Adaptations 80,000 -80,000 0 0 0 0 0

Disabled Adaptations - SWHA 0 0 0 0 0 (SWHA funded)

Disabled Facilities Grants - 320,000 27,339 80,000 497,339 0 343,517 112,612 41,210 Mandatory Rolling Programme

Minor Works Assistance & Home 150,000 5,660 155,660 0 81,247 74,413 0 Repair Grants (Discretionary) Rolling Programme

Choice Based Lettings 0 11,209 11,209 0 3,323 0 7,886

Empty Homes 0 19,131 144,131 0 36,792 107,339 0

Temporary Accommodation Unit - 0 6,006 6,006 0 8,540 -8,540 6,006 furnishings

Total Revenues & Housing 1,180,192 590,084 0 1,965,276 0 1,077,877 832,297 55,102

Head of Change Performance Total ICT and Business 733,000 265,348 0 998,348 6,147 398,290 356,911 237,000 Development Strategy

Cap Bud Mon P1-9 1011.xls, Appendix A inc forecast 2/6 24/01/2011 STRATFORD-ON-AVON DISTRICT COUNCIL CAPITAL BUDGET MONITORING PERIOD 1-9 2010/11

Slippage Forecast agreed at Amendments Committed Expenditure Original 21st June proposed 7th Amended April- Actual April - 1st January - Estimate 2010 Feb. 2011 Estimate December December to 31st March Budget 2010/11 Cabinet Cabinet 2010/11 2010/11 2010/11 2011 Remaining

£ £ £ £ £ £ £ £ Head of Planning Services Bridgetown Cyclepath (S.106) 0 2,100 2,100 0 0 2,100 0

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Cap Bud Mon P1-9 1011Report 26 KB DownloadRead as text
PDF
Capital Budget MonitoringReport 44 KB Download

At this meeting

Whole meeting

On this subject at Stratford-on-Avon

Search all
  1. Capital Budget MonitoringThis decision
  2. Capital Budget Monitoring Period 1 - 6 2026/27Decided
  3. Capital Budget Monitoring Period 1 - 4 2026/27Decided
  4. Capital Budget Monitoring Period 1 - 2 2026/27Decided
  5. Capital Budget Monitoring - Period 1 - 10 2025/26Decided
  6. Revenue and Capital Budget 2026/27Approved

More from Stratford-on-Avon The Cabinet

All decisions
MeetingDecisionOutcome
2 Nov 2026 Future of Southam United Football Club(1) That subject to the conditions identified in paragraph 1.4.3 of the agenda report, and subject to the above amend... Decided Open
2 Nov 2026 Strategic Risk RegisterThat the , attached as Appendix 1 to the agenda report, be endorsed. Note: In accordance with the Council’s Constitut... Decided Open
2 Nov 2026 Options for Boosting the Supply of Housing Land Update Report(1) That the progress in delivering the Housing Land Supply Action Plan, the September 2026 housing land supply calcu... Noted Open
2 Nov 2026 Youth Catalyst Project – Service Specification and Permission to Tender(1) That permission to procure a Youth Catalyst Project provision to meet the requirements of the specification, as d... Approved Open
2 Nov 2026 Revenue Budget Monitoring Period 1 - 6 2026/27(1) That the actual net variance as at Period 6, and the estimated revenue outturn for 2026/27, be received; and (2) ... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies