The Cabinet, Monday 9 March 2026

Capital Budget Monitoring - Period 1 - 10 2025/26

Decided Executive 3 papers

AI summaryStratford-on-Avon District Council Cabinet noted the capital budget position for April 2025 to January 2026, with £2,560,294 spent or committed against a £9,312,788 budget. No further action required unless issues arise.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedNo further action unless issues identified
Money£9,312,788 capital budget for 2025/26£2,560,294 spent or committed by 31 January 2026
What happens nextMonitor delivery of capital projectsFurther Cabinet report only if issues require it
Who it affectsCapital projects across the districtLeisure centres, recreation grounds, CCTV, play areas

What was decided

The Cabinet received the position on capital expenditure and income for Period 1 to 10 of 2025/26, covering 1 April 2025 to 31 January 2026. Report P5

Any issues identified are to be addressed by the relevant Portfolio Holder for clarification, with a further report to The Cabinet if required. Report P5

Why

The report sets out details of capital budget monitoring for the first ten months of 2025/26, comparing actual and accrued expenditure against the current budget. Report P5

Work continues to ensure that as many projects as possible are delivered within their intended timescales.

What happens next

The relevant Portfolio Holder will respond to any points of clarification identified from the report.

A further report to The Cabinet will be considered if required.

Project delivery continues through the remainder of 2025/26 towards the 31 March 2026 year end.

The money

  • £9,312,788 2025/26 capital expenditure budget after in-year amendments Report 1.2
  • £2,560,294 Actual and committed capital expenditure to 31 January 2026 Report 1.4
  • £1,454,706 Actual capital expenditure to 31 January 2026 Report 1.4
  • £1,105,588 Committed capital expenditure to 31 January 2026 Report 1.4
  • £6,233,922 Accumulated capital receipts and grants at 1 April 2025 (provisional)
  • £6,233,922 Estimated remaining capital receipts and grants at 31 March 2026
  • £4,905,530 Slippage of 2024/25 items added by Cabinet on 7 July 2025
  • £777,000 9 Timothy's Bridge Road headlease acquisition budget

Options considered

  • Chosen: Receive the report and address any issues via the relevant Portfolio Holder, with a further Cabinet report if required. Standard approach for budget monitoring with no issues requiring decision Report P5

Implications

  • Legal: No direct legal implications arising from the report.
  • Financial: This is a financial report; the Capital Programme supports various aims within the Council Plan.
  • Equalities: No direct equalities effects identified.
  • Climate: Environmental and climate change implications not applicable to this report.
  • Risk: Risk assessment marked not applicable.
  • Staffing: No human resources or staffing implications.
  • Other: No data protection or health and wellbeing implications.

Who and where

  • Users of Southam and Studley Leisure Centres (solar panel investment)
  • Visitors to Recreation Ground (paddling pool refurbishment, play equipment, sandpit accessibility)
  • Occupiers of 9 Timothy's Bridge Road (headlease acquisition)
  • Residents of Wellesbourne and Meon Vale (CCTV replacement and upgrade)
  • Residents of Gaydon and Lighthorne (Community Hub design, BREEAM additional costs)
  • Council tenants and users of EH building (main window replacement)

Timeline

  • February 2025: Council agreed the original 2025/26 capital expenditure budget of £2,619,000 Report 1.2
  • 1 April 2025 to 31 January 2026: Capital budget monitoring period covered by the report Report P5, P2
  • 7 July 2025: Cabinet agreed slippage of 2024/25 items and other budget changes
  • 9 March 2026: Cabinet meeting at which the report was received Report P1
  • 31 March 2026: End of 2025/26 financial year, target for remaining capital delivery

Plain English for the jargon

  • Section 106 (S.106): Developer contributions secured through planning obligations to fund local infrastructure
  • CIL: Community Infrastructure Levy, a charge developers pay to fund local infrastructure
  • BREEAM: Building Research Establishment Environmental Assessment Method, a sustainability rating for buildings
  • OSC: Overview and Scrutiny Committee, the council's scrutiny body
  • Period 1 to 10: First ten months of the financial year, 1 April to 31 January
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item562

Resolved

That the position on capital expenditure and income for the Period 1 - 10 of 2025/26 be received. Note: This item is not subject to call-in to the OSC as it is not a key decision.
Word for word from the decision Stratford-on-Avon published for this meeting. Source: democracy.stratford.gov.uk

Follow this further

Built from Stratford-on-Avon's papers

What the report saysPro

Report to The Cabinet, 5 pages

The Cabinet 9 March 2026

Title: Capital Budget Monitoring Period 1 – 10 2025/26

Lead Officer: Nicola Reynolds, Financial Accountant (01789 260608)

Portfolio Holder/ Lead Member: Councillor D Curtis

Summary This report provides The Cabinet with details of the Capital Budget Monitoring for the period 1 – 10 (1 April 2025 to 31 January 2026). Recommendations That the position on capital expenditure and income for the period 1 – 10 of 2025/26 be received, and any issues identified for further consideration be addressed by: (1) The relevant Portfolio Holder for a point of clarification; and (2) If required, a further report to The Cabinet.

1 Background/Information 1.1 Table 1 Capital Budget Summary Position Table 1 summarises the Council’s estimated position with regard to accumulated capital receipts: Accumulated capital receipts and capital grants as £6,233,922 at 1 April 2025 (provisional) Less budgeted expenditure for 2025/26 (9,312,788) Plus new funds and financing in 2025/26 £9,108,043 Plus budgeted Capital Financing Movement £204,745 Remaining estimated capital receipts and capital £6,233,922 grants as at 31 March 2026

1.2In February 2025 the Council agreed the capital expenditure budget for 2025/26 financial year totalling £2,619,000. With the amendments agreed by The Cabinet to date, the total Capital Expenditure Budget for the current year, including S.106, plus other additions, and slippage, as outlined in the 2024/25 Capital Budget Outturn Report, now totals £9,312,788. This is derived from the addition/removal of budget changes summarised in Table 2. 1.3 Table 2 – Capital expenditure –2025/26 2025/26 Gross Project/scheme expenditure budget £ Expenditure budget agreed as per The Cabinet, 10 2,619,000 February 2025 The Cabinet 7 July 2025 - Slippage of 2024/25 Items 4,905,530 9 Timothy’s Bridge Road headlease acquisition 777,000 Southam & Studley Leisure Centres - solar panels 400,000 EH main window replacement 361,000 Recreation Ground splash pad installation budget (150,000) transferred Recreation Ground paddling pool refurbishment & 150,000 additional water features Recreation Ground replacement play equipment & 100,000 sandpit accessibility improvements S106 play area additions funded by commuted sums 104,069 S106 Gaydon/Lighthorne Community Hub design - 21,471 additional BREEAM costs S106 Wellesbourne CCTV Replacement 14,718 S106 Wellesbourne & Meon Vale CCTV Synetics 10,000 2025/26 expenditure budget 9,312,788

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Budget Monitoring P1-10 2025-26Appendix 1 6 pages Download
PDF
S106 & CIL P1-10 2025-26Appendix 2 5 pages Download
PDF
Capital Budget Monitoring: Period 1: 10 2025/26Report 5 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Stratford-on-Avon

Search all
  1. Capital Budget Monitoring - Period 1 - 10 2025/26This decision
  2. Capital Budget Monitoring Period 1 - 6 2026/27Decided
  3. Capital Budget Monitoring Period 1 - 4 2026/27Decided
  4. Capital Budget Monitoring Period 1 - 2 2026/27Decided
  5. Revenue and Capital Budget 2026/27Approved
  6. Capital Budget Monitoring - Period 1 - 8 2025/26Decided

More from Stratford-on-Avon The Cabinet

All decisions
MeetingDecisionOutcome
2 Nov 2026 Future of Southam United Football Club(1) That subject to the conditions identified in paragraph 1.4.3 of the agenda report, and subject to the above amend... Decided Open
2 Nov 2026 Strategic Risk RegisterThat the , attached as Appendix 1 to the agenda report, be endorsed. Note: In accordance with the Council’s Constitut... Decided Open
2 Nov 2026 Options for Boosting the Supply of Housing Land Update Report(1) That the progress in delivering the Housing Land Supply Action Plan, the September 2026 housing land supply calcu... Noted Open
2 Nov 2026 Youth Catalyst Project – Service Specification and Permission to Tender(1) That permission to procure a Youth Catalyst Project provision to meet the requirements of the specification, as d... Approved Open