The Cabinet, Monday 7 March 2011

Capital Budget Monitoring

Approved Executive 2 papers

The Cabinet approved this item on Monday 7 March 2011. Below is the council's own wording, with the papers it was decided on.

Item757

Resolved

(1) That the position on capital expenditure and income for period 1-10 of 2010/11 be received and the amendments detailed in the preamble to this Minute be approved; and (2) That a further report be submitted on the Capital budget position. Note: This item is subject to call-in to the OSC.
Word for word from the decision Stratford-on-Avon published for this meeting. Source: democracy.stratford.gov.uk

Follow this further

Built from Stratford-on-Avon's papers

What the report saysPro

Report to The Cabinet

THE CABINET 7 MARCH 2011

Subject: Capital Budget Monitoring 2010/11 Lead Officer: Sarah Pittaway Contact on 01789 260416 Lead Member/ Portfolio Holder: Councillor J Appleton

Summary This report provides the Cabinet with details of the Capital Budget Monitoring for the Period 1 – 10 (April 2010 – 31 January 2011). Also included is a forecast of expenditure for the period between February 2011 and March 2011.

Recommendation (1) That the position on capital expenditure and income for period 1- 10 of 2010/11 is received; (2) Approves amendments detailed in 2.1; (3) That the position on capital expenditure and income for period 1- 10 of 2010/11 is received and the Cabinet identifies any issues that it wishes to be considered further:  by a further report to the Cabinet;  by the Portfolio-holder; or  by a report to the relevant Overview and Scrutiny Committee by the relevant Head of Service or Strategic Director.

1 Background/Information

Accumulated Capital Receipt of 1/4/10 £15,633,777 Estimated Capital Receipts for 2010/11 £ 3,519,832 Estimated Capital Expenditure for 2010/11 £ 8,996,484 Estimated accumulated capital receipts at £10,157,125 31/3/11

1.1In February 2010 the Council agreed the Capital Expenditure Budget for 2010/11 budget, totalling £3,508,232. With the amendments agreed by the Cabinet to date and those proposed below, the total Capital Expenditure Budget for the current year now totals £8,996,484. This is derived from the addition/removal of budget changes summarised in the table below: Summary of changes

2010/11 Gross Expenditure Project/Scheme Budget £ Expenditure Budget agreed as per Cabinet 3,183,412 8/2/10 Cabinet (8 March 2010) – Slippage approval – 125,000 Empty Homes Cabinet (8 March 2010) – Slippage approval – 207,482 Warwick Road Lands Cabinet (21 June 2010) – Slippage approval 3,644,172 detailed at Appendix B Cabinet (4 October 2010) – Playbuilder project 95,489 funded by WCC grant Cabinet (4 October 2010) – Purchase of refuse 17,000 bins

Cabinet (29 November 2010) – Playbuilder project 103,000

Cabinet (29 November 2010) – Planned 455,220 maintenance of council owned assets

Cabinet (29 November 2010) - Skatepark 16,444

Cabinet (29 November 2010) – Southam re- 855,944 development Cabinet (29 November 2010) – World Class 55,032 Stratford Cabinet (29 November 2010) – S.106 Wattons 56,734 Lane, Southam Cabinet (29 November 2010) – Disabled Facilities 70,000 Grants funded by Regional Housing Pot Cabinet (proposed 7 February 2011) – S.106 6,111 Bidford - Trees Cabinet (proposed 7 February 2011) – S.106 Bidford – Kitchen refurbishment at Community 7,853 Hall Cabinet (proposed 7 March 2011) – contribution 50,000 from WCC for DFGs Cabinet (proposed 7 March 2011) – S.106 Bidford 35,991 –Public Open Space

Cabinet (proposed 7 March 2011) – WCC income 11,600 Amended 2010/11 Expenditure Budget 8,996,484

1.2Committed, actual and forecast expenditure for the year to 31 March 2011 totals £6,377,021, as detailed in Appendix 1.

1.3In February 2010 the Council agreed the Capital Income Budget for 2010/11 budget, totalling £1,725,370. With the amendments agreed by the Cabinet to date and changes proposed below, the total Capital Income Budget for the current year now totals £3,519,832. This is derived from the addition/removal of budget changes summarised in the table below: Summary of changes 2009/10 Gross Project/Scheme Income Budget £ Income Budget agreed as per Cabinet 8/2/10 1,725,370

Cabinet (21 June 2010) – slippage from 09/10 1,184,135

Cabinet (4 October 2010) – sale of land -1,250,000

Cabinet (4 October 2010) – Playbuilder project 95,489 funded by WCC grant Cabinet (4 October 2010) – Revenue contribution 17,000 for purchase of refuse bins

Cabinet (29 November 2010) – Playbuilder project 103,000

Cabinet (29 November 2010) – Planned 455,220 maintenance of council owned assets

Cabinet (29 November 2010) - Skatepark 16,444

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Budget Monitoring Appendix 1Appendix 22 KB Download
PDF
Capital Budget MonitoringReport 45 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Stratford-on-Avon

Search all
  1. Capital Budget MonitoringThis decision
  2. Capital Budget Monitoring Period 1 - 6 2026/27Decided
  3. Capital Budget Monitoring Period 1 - 4 2026/27Decided
  4. Capital Budget Monitoring Period 1 - 2 2026/27Decided
  5. Capital Budget Monitoring - Period 1 - 10 2025/26Decided
  6. Revenue and Capital Budget 2026/27Approved

More from Stratford-on-Avon The Cabinet

All decisions
MeetingDecisionOutcome
2 Nov 2026 Future of Southam United Football Club(1) That subject to the conditions identified in paragraph 1.4.3 of the agenda report, and subject to the above amend... Decided Open
2 Nov 2026 Strategic Risk RegisterThat the , attached as Appendix 1 to the agenda report, be endorsed. Note: In accordance with the Council’s Constitut... Decided Open
2 Nov 2026 Options for Boosting the Supply of Housing Land Update Report(1) That the progress in delivering the Housing Land Supply Action Plan, the September 2026 housing land supply calcu... Noted Open
2 Nov 2026 Youth Catalyst Project – Service Specification and Permission to Tender(1) That permission to procure a Youth Catalyst Project provision to meet the requirements of the specification, as d... Approved Open
2 Nov 2026 Revenue Budget Monitoring Period 1 - 6 2026/27(1) That the actual net variance as at Period 6, and the estimated revenue outturn for 2026/27, be received; and (2) ... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies