Capital Budget Monitoring

Noted Executive 2 papers

The Cabinet noted this item on Monday 13 February 2012. Below is the council's own wording, with the papers it was decided on.

Item580

Resolved

That the position on the Capital expenditure and income for the period April to December 2011 be noted. NOTE: This item is not subject to call-in to the OSC
Word for word from the decision Stratford-on-Avon published for this meeting. Source: democracy.stratford.gov.uk

Follow this further

Built from Stratford-on-Avon's papers

What the report saysPro

Report to The Cabinet

THE CABINET 13 FEBRUARY 2012

Subject: Capital Budget Monitoring 2011/12 Lead Officer: Sarah Pittaway Contact on 01789 260416 Lead Member/ Portfolio Holder: Councillor J Ellard

Summary This report provides The Cabinet with details of the Capital Budget Monitoring for the Period 1 – 9 (April 2011 – 31 December 2011).

Recommendation (1) That the position on capital expenditure and income for period 1- 9 of 2011/12 is noted; (2) That any issues be identified for further consideration:  by a further report to The Cabinet; or  by the Portfolio Holder.

1 Background/Information

Accumulated Capital Receipt of 1 April 2011 – now £14,104,892 updated for 2010/11 actual outturn position Estimated usage of Capital Receipts for 2011/12 £995,697 Estimated Capital Expenditure for 2011/12 £ 4,069,321 Estimated accumulated capital receipts at 31 March 2012 £11,031,268

1.1In February 2011 the Council agreed the Capital Expenditure Budget for 2011/12 budget, totalling £2,076,303. With the amendments agreed by the Cabinet to date, the total Capital Expenditure Budget for the current year now totals £4,069,321. This is derived from the addition/removal of budget changes summarised in the table below: Summary of changes 2011/12 Gross Project/Scheme Expenditure Budget £ Expenditure Budget agreed as per The Cabinet February 2011 2,076,303

The Cabinet 20 June 2011 – Slippage 3,144,062

The Cabinet 18 July 2011 – Skate park 18,000

The Cabinet 18 July 2011 – Bridgetown – re-profile to 2015/16 -160,863

The Cabinet 18 July 2011 – Warwick Road Land – re-profile to -207,482 2015/16 The Cabinet 18 July 2011 – community Woodland – re-profile to -9,900 2015/16 The Cabinet 18 July 2011 – s106 Masons Road – re-profile to -560,000 2015/16 The Cabinet 18 July 2011 – s106 Southam re-generation – re-profile -686,299 to 2013/14 The Cabinet 18 July 2011 – Landlord Accreditation Scheme 24,000

The Cabinet 10 October 2011 – s106 Earlswood -57,500

The Cabinet 10 October 2011 – s106 Canal Quarter Master Plan 15,000

The Cabinet 10 October 2011 – refuse bins purchase 10,000

The Cabinet 10 October 2011 – LPSA2 – affordable housing 464,000

Amended 2011/12 Expenditure Budget 4,069,321

1.2Committed and actual expenditure for the period to 31 December 2011 totals £1,529,290, as detailed in Appendix 1.

1.3In February 2011 the Council agreed the Capital Income Budget for 2011/12 budget, totalling £202,000. With the amendments agreed by the Cabinet to date, the total Capital Income Budget for the current year now totals £995,697. This is derived from the addition/removal of budget changes summarised in the following table: Summary of changes 2011/12 Gross Project/Scheme Income Budget £

Income Budget agreed as per The Cabinet February 2011 202,000

The Cabinet 20 June 2011 – slippage to 2011/12 1,490,496

The Cabinet 18 July 2011 – Skate park grant contribution 18,000 The Cabinet 18 July 2011 – s106 Masons Road – re-profile to -560,000 2015/16 The Cabinet 18 July 2011 – s106 Southam re-generation – re- -686,299 profile to 2013/14 The Cabinet 18 July 2011 – Landlords Accreditation Scheme 24,000 funded from Regional Housing Pot The Cabinet 10 October 2011 – s106 Earlswood -57,500

The Cabinet 10 October 2011 – s106 Canal Quarter Master Plan 15,000

The Cabinet 10 October 2011 – LPSA2 – affordable housing 464,000

The Cabinet 5 December 2011 - Disabled Facilities Grant – 86,000 additional income Amended 2011/12 Income Budget 995,697

2 Options available to The Cabinet There are no amendments proposed to the current year’s Capital Programme.

3 Members’ Comments 3.1 Comments for the Portfolio holder have been incorporated into the report.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Cap Bud Appendix 1Appendix 29 KB Download
PDF
Capital Budget MonitoringReport 55 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Stratford-on-Avon

Search all
  1. Capital Budget MonitoringThis decision
  2. Capital Budget Monitoring Period 1 - 6 2026/27Decided
  3. Capital Budget Monitoring Period 1 - 4 2026/27Decided
  4. Capital Budget Monitoring Period 1 - 2 2026/27Decided
  5. Capital Budget Monitoring - Period 1 - 10 2025/26Decided
  6. Revenue and Capital Budget 2026/27Approved

More from Stratford-on-Avon The Cabinet

All decisions
MeetingDecisionOutcome
2 Nov 2026 Future of Southam United Football Club(1) That subject to the conditions identified in paragraph 1.4.3 of the agenda report, and subject to the above amend... Decided Open
2 Nov 2026 Strategic Risk RegisterThat the , attached as Appendix 1 to the agenda report, be endorsed. Note: In accordance with the Council’s Constitut... Decided Open
2 Nov 2026 Options for Boosting the Supply of Housing Land Update Report(1) That the progress in delivering the Housing Land Supply Action Plan, the September 2026 housing land supply calcu... Noted Open
2 Nov 2026 Youth Catalyst Project – Service Specification and Permission to Tender(1) That permission to procure a Youth Catalyst Project provision to meet the requirements of the specification, as d... Approved Open
2 Nov 2026 Revenue Budget Monitoring Period 1 - 6 2026/27(1) That the actual net variance as at Period 6, and the estimated revenue outturn for 2026/27, be received; and (2) ... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies