Resolved
That the position on the Capital expenditure and income for the period April to September 2013 be noted; and NOTE: This item is not subject to call-in to the OSC
The Cabinet noted this item on Monday 4 November 2013. Below is the council's own wording, with the papers it was decided on.
Resolved
That the position on the Capital expenditure and income for the period April to September 2013 be noted; and NOTE: This item is not subject to call-in to the OSC
THE CABINET 4 NOVEMBER 2013
Subject: Capital Budget Monitoring 2013/14 Lead Officer: Sarah Pittaway Contact on 01789 260416 Lead Member/ Portfolio Holder: Councillor J Ellard
Summary This report provides The Cabinet with details of the Capital Budget Monitoring for the Period 1 – 6 (April 2013 – 30 September 2013).
Recommendation (1) That the position on capital expenditure and income for period 1- 6 of 2013/14 be noted; (2) That the Portfolio Holder for Finance & Business Administration be authorised to decide how the remaining balance of the Section 106 funding is spent; and, (3) That any issues be identified for further consideration: by a further report to The Cabinet; or by the Portfolio Holder.
1 Background/Information
1.1Table 1 Capital Budget Summary Position 1.2 The following table summarises the Council’s estimated position with regard to Accumulated Capital Receipts:- Accumulated Capital Receipt of 1 April 2013 – now £12,568,760 updated for 2012/13 actual outturn position Estimated income from Capital Receipts for 2013/14 £1,688,634 Estimated Capital Expenditure for 2013/14 £3,596,453 Estimated accumulated capital receipts at 31 March £10,760,941 2014
1.3In February 2013 the Council agreed the Capital Expenditure Budget for 2013/14 budget, totalling £2,044,647. With the amendments agreed by The Cabinet to date, the total Capital Expenditure Budget for the current year now totals £3,596,453. This is derived from the addition/removal of budget changes summarised in the following table: 1.4 Table 2 – Capital Expenditure - Summary of changes in 2013/14
2013/14 Gross Expenditure Project/Scheme Budget £ Expenditure Budget agreed as per The Cabinet 2,044,647 February 2013 The Cabinet 17 June 2013 – Slippage 923,727 The Cabinet 20 May 2013 – Open Space and CCTV 349,079 s.106 The Cabinet 15 July 2013 – Traveller Site Budget 179,000 Proposed The Cabinet 9 September – Stratford Leisure Centre 100,000
Amended 2013/14 Expenditure Budget 3,596,453
1.5Committed and actual expenditure for the period to 30 September 2013 totals £1,076,976 as detailed in Appendix 1. 1.6 A summary of S.106 money currently being held by the Council is shown at Appendix 2. Total funds held amount to £2.5m although £1.1m of this is already included in the Capital Programme to be spent in 2013/14.
1.7In February 2013 the Council agreed the Capital Income Budget for 2013/14 budget, totalling £1,106,299. With the amendments agreed by The Cabinet to date, the total Capital Income Budget for the current year now totals £1,688,634. This is derived from the addition/removal of budget changes summarised in the following table: 1.8 Table 3 – Capital Income - Summary of changes 2013/14
2013/14 Gross Project/Scheme Income Budget £ Income Budget agreed as per The Cabinet 1,106,299 February 2013 The Cabinet 17 June 2013 – slippage to 2013/14 52,071 The Cabinet 20 May 2013 – Open Space and CCTV s.106 349,079
The Cabinet 15 July 2013 – Traveller Site Budget Proposed 179,000
The Cabinet 15 July 2013 – Skaters’ contribution towards skate park 2,185
Amended 2013/14 Income Budget 1,688,634 2. Options available to The Cabinet 2.1 With regard to the Southam Re-development Project, Members are requested to grant authorisation to the Portfolio Holder for Finance & Business Administration to decide how the remaining balance of the Section 106 funding is spent. 3 Members’ Comments 3.1 Comments from the Portfolio Holder have been incorporated into this report.
4 Implications of the Proposal 4.1 Legal 4.1.1 There are no direct legal implications arising from this report. 4.2 Financial 4.2.1 This is a financial report. 4.3 Environmental 4.3.1 Not applicable. 4.4 Corporate Strategy 4.4.1 The Capital Programme supports various aims within the Corporate Strategy, however, this report is restricted to the financial implications of the Council’s Capital Budget. 4.5 Analysis of the effects on Equality 4.5.1 None directly.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Capital: Appendix 1Appendix | 8 pages | Download |
PDF |
Capital: S 106 Appendix 2Appendix | 2 pages | Download |
PDF |
Capital Budget MonitoringReport | 3 pages | DownloadRead as text |
Follow The Cabinet at Stratford-on-Avon and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Nov 2026 | Future of Southam United Football Club(1) That subject to the conditions identified in paragraph 1.4.3 of the agenda report, and subject to the above amend... | Decided | Open |
| 2 Nov 2026 | Strategic Risk RegisterThat the , attached as Appendix 1 to the agenda report, be endorsed. Note: In accordance with the Council’s Constitut... | Decided | Open |
| 2 Nov 2026 | Options for Boosting the Supply of Housing Land Update Report(1) That the progress in delivering the Housing Land Supply Action Plan, the September 2026 housing land supply calcu... | Noted | Open |
| 2 Nov 2026 | Youth Catalyst Project – Service Specification and Permission to Tender(1) That permission to procure a Youth Catalyst Project provision to meet the requirements of the specification, as d... | Approved | Open |
| 2 Nov 2026 | Revenue Budget Monitoring Period 1 - 6 2026/27(1) That the actual net variance as at Period 6, and the estimated revenue outturn for 2026/27, be received; and (2) ... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.