That the position on Capital expenditure and income for the period 1-4 2016/17 be received and noted. NOTE: This item is not subject to call-in to the OSC
The Cabinet noted this item on Monday 5 September 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
That the position on Capital expenditure and income for the period 1-4 2016/17 be received and noted. NOTE: This item is not subject to call-in to the OSC
THE CABINET 5 SEPTEMBER 2016
Subject: Capital Budget Monitoring 2016/17 Lead Officer: Sarah Pittaway Contact on 01789 260416 Lead Member/ Portfolio Holder: Councillor L Organ
Summary This report provides The Cabinet with details of the Capital Budget Monitoring for the Period 1–4 (April 2016–31 July 2016).
Recommendation That the position on capital expenditure and income for period 1-4 of 2016/17 is received and that any issues are identified for further consideration by:- a further report to The Cabinet; the Portfolio Holder.
1 Background/Information
1.1Table 1: Capital Budget Summary Position 1.2 The following table summarises the Council’s estimated position with regard to Accumulated Capital Receipts:-
Accumulated Capital Receipt of 1 April 2016 – now £9,561,938 updated for 2015/16 actual outturn position Add Capital Grants excluding s.106 – not included £193,198 above Plus estimated additional income in 2016/17 – DFG £689,298 & New property sale receipts Less estimated Capital Expenditure excluding S.106 (£3,485,803) for 2016/17 Estimated accumulated capital receipts and grants at £6,958,631 31 March 2017
1.3In February 2016 the Council agreed the Capital Expenditure Budget for 2016/17 budget, totalling £2,611,027. With the amendments agreed by The Cabinet to date, the total Capital Expenditure Budget for the current year including S.106 now totals £5,254,634. This is derived from the addition/removal of budget changes summarised in the following table; 1.4 Table 2: Capital Expenditure - Summary of changes in 2016/17
2016/17 Gross Expenditure Project/Scheme Budget £
Expenditure Budget agreed as per the Council February 2016 2,611,027
The Cabinet 23 May 2016 – Parking Management System 191,590
The Cabinet 20 June 2016 – Slippage 2,450,043
S.106 – Adult/Youth Facilities Falstaff Hs. 1,974
S.106 Avenue Farm play equipment – accountancy adjustment 115
Amended 2016/17 Expenditure Budget 5,254,749
1.5Committed (£647,779) and actual (£648,603) expenditure for the period to 31 July 2016 totals £1,296,382 as detailed in Appendix 1.
1.6A summary of uncommitted S.106 money for capital projects currently being held by the Council is shown at Appendix 2. This total excludes any sums estimated to be received in 2016/17. Total uncommitted funds held amount to £514k.
2 Options available to The Cabinet 2.1 There are no proposed amendments. 3 Members’ Comments 3.1 Comments from the Portfolio Holder have been incorporated into this report.
4 Implications of the Proposal 4.1 Legal 4.1.1 There are no direct legal implications arising from this report. 4.2 Financial 4.2.1 This is a financial report. 4.3 Environmental 4.3.1 Not applicable. 4.4 Corporate Strategy 4.4.1 The Capital Programme supports various aims within the Corporate Strategy; however, this report is restricted to the financial implications of the Council’s Capital Budget. 4.5 Analysis of the effects on Equality 4.5.1 None directly.
5 Conclusion 5.1 Work continues in the current financial year to ensure that all the projects are delivered. David Buckland EXECUTIVE DIRECTOR
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Capital Budget MonitoringReport | 2 pages | DownloadRead as text |
PDF |
Copy of Appx 1 Cap Bud Mon P1-4 16-17Report | 5 pages | Download |
Follow The Cabinet at Stratford-on-Avon and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Nov 2026 | Future of Southam United Football Club(1) That subject to the conditions identified in paragraph 1.4.3 of the agenda report, and subject to the above amend... | Decided | Open |
| 2 Nov 2026 | Strategic Risk RegisterThat the , attached as Appendix 1 to the agenda report, be endorsed. Note: In accordance with the Council’s Constitut... | Decided | Open |
| 2 Nov 2026 | Options for Boosting the Supply of Housing Land Update Report(1) That the progress in delivering the Housing Land Supply Action Plan, the September 2026 housing land supply calcu... | Noted | Open |
| 2 Nov 2026 | Youth Catalyst Project – Service Specification and Permission to Tender(1) That permission to procure a Youth Catalyst Project provision to meet the requirements of the specification, as d... | Approved | Open |
| 2 Nov 2026 | Revenue Budget Monitoring Period 1 - 6 2026/27(1) That the actual net variance as at Period 6, and the estimated revenue outturn for 2026/27, be received; and (2) ... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.