The Cabinet, Monday 27 November 2017

Options for Alcester Greig Centre

Agreed Executive 2 papers

The Cabinet agreed this item on Monday 27 November 2017. Below is the council's own wording, with the papers it was decided on.

Item537

Resolved

That six months’ notice to terminate the Leisure Agreement is issued to the Greig Trustees. Note: This item is subject to call-in to the OSC
Word for word from the decision Stratford-on-Avon published for this meeting. Source: democracy.stratford.gov.uk

Follow this further

Built from Stratford-on-Avon's papers

What the report saysPro

Report to The Cabinet, 3 pages

THE CABINET 27 NOVEMBER 2017

Subject: Options for Alcester Greig Centre Lead Officer: Tony Perks Contact on 01789 260620 Lead Member/ Portfolio Holder: Councillor C Saint/Councillor M Brain/ Councillor L Organ

Summary The Council’s Corporate Strategy identifies refurbishment of the Lifestyles Sports Hall at the Greig Centre as a priority. This report sets out a legal option that could be used to allow the District Council to gain control of the Greig Centre in Alcester so that these aims could be achieved. Recommendation That six months’ notice to terminate the Leisure Agreement is issued to the Greig Trustees.

1 Background/Information 1.1 In March 2014, The Cabinet approved a scheme which would have led to the managed transfer of the Greig site to the District Council. This transfer would have led to investment in the leisure facilities on the site, and the opportunity for Alcester Town Council to take a long term lease on the Greig Hall. 1.2 The Council provided grant funding to the Greig Trustees to ensure that the facility remained open during the efforts to achieve a managed transfer of the facility. Negotiations for the transfer broke down in May 2015 due to a fundamental difference between the Council and the trustees in relation to the valuation of the site. 1.3 Investment in the leisure facilities of Alcester remains a Corporate Strategy 2015-19 priority, the Council has earmarked £250,000 within the approved capital programme. Such investment cannot proceed under the current management arrangements. It is evident that the financial position of the trust is precarious and that the facilities on the site are deteriorating. It was therefore necessary to investigate other mechanisms which could result in the transfer of the asset to the Council. 1.4 To this end Legal advice has been obtained to establish how the District Council could gain control of the Greig complex in Alcester. 1.5 Selborne Chambers was commissioned to give an opinion on the best way for the District Council to achieve this aim. Their advice is summarised in section 2 below. 1.6 To provide further context to this advice a brief history of the District Council’s involvement with the Greig site is set out in Appendix 1. 2 Legal opinion 2.1 Selborne Chambers has advised the agreement that was attached to the £800,000 contains a number of ‘Events of Default’ under which the £800,000 becomes repayable. One of these relates to the termination of the ‘Leisure Agreement by either party (District Council or the Greig Trustees) in any manner’. 2.2 The Leisure Agreement can be cancelled by either party giving six months’ notice in writing to the other party. It therefore follows that the District Council can give six months’ notice to terminate the Leisure Agreement at the end of which a default of the funding agreement would be triggered and the £800,000 would be repayable. 2.3 It is unlikely that the Trustees will be able to repay the £800,000 in which case, as the holder of the Principal Charge, it should be possible for the District Council to gain control of the site.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Greig Centre CJS editAppendix 1 5 pages Download
PDF
Options for Alcester Greig CentreReport 3 pages DownloadRead as text

More from Stratford-on-Avon The Cabinet

All decisions
MeetingDecisionOutcome
2 Nov 2026 Future of Southam United Football Club(1) That subject to the conditions identified in paragraph 1.4.3 of the agenda report, and subject to the above amend... Decided Open
2 Nov 2026 Strategic Risk RegisterThat the , attached as Appendix 1 to the agenda report, be endorsed. Note: In accordance with the Council’s Constitut... Decided Open
2 Nov 2026 Options for Boosting the Supply of Housing Land Update Report(1) That the progress in delivering the Housing Land Supply Action Plan, the September 2026 housing land supply calcu... Noted Open
2 Nov 2026 Youth Catalyst Project – Service Specification and Permission to Tender(1) That permission to procure a Youth Catalyst Project provision to meet the requirements of the specification, as d... Approved Open
2 Nov 2026 Revenue Budget Monitoring Period 1 - 6 2026/27(1) That the actual net variance as at Period 6, and the estimated revenue outturn for 2026/27, be received; and (2) ... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies