Stratford-on-Avon District Council
The Cabinet, Monday 4 June 2018

Capital Outturn 2017/18 and Capital Slippage

Decided Executive 4 papers

The Cabinet decided this item on Monday 4 June 2018. Below is the council's own wording, with the papers it was decided on.

Item61

Resolved

That the Capital Budget for 2018/19 be increased by £2,696,860 for slippage to be financed from the capital receipts as budgeted for in 2017/18. NOTE: This item is subject to Call-in to the OSC.
Word for word from the decision Stratford-on-Avon published for this meeting. Source: democracy.stratford.gov.uk

Follow this further

Built from Stratford-on-Avon's papers

What the report saysPro

Report to The Cabinet

THE CABINET 4 JUNE 2018

Subject: Capital Outturn 2017/18 and Capital Slippage Lead Officer: Sarah Pittaway Contact on 01789 260416 Lead Member/ Portfolio Holder: Councillor L Organ

Summary This report provides The Cabinet with details of the Capital Outturn 2017/18.

Recommendation That the Capital Budget be increased by £2,696,860 as detailed in Appendix 2 in 2018/19 for slippage financed by the capital receipts as budgeted for in 2017/18.

1 Background/Information 1.1 Table 1 Capital Budget Summary Position 1.2 The following table summarises the Council’s estimated position with regard to Accumulated Capital Receipts:-

Accumulated Capital Receipt and Capital Grants of 1 £6,202,781 April 2017 Plus new funds and financing in 2017/18 £700,000 Less Expenditure excluding S.106 for 2017/18 (£2,695,041) Remaining accumulated capital receipts and capital £4,207,740 grants at 31 March 2018

1.3In February 2017 the Council agreed the Capital Expenditure Budget for 2017/18 budget, totalling £1,135,000. With the amendments agreed by The Cabinet to date, the total Capital Expenditure Budget for the current year including S.106 now totals £4,339,428. This is derived from the addition/removal of budget changes summarised in the following table: 1.4 Table 2 – Capital Expenditure - Summary of changes in 2017/18

2017/18 Gross Expenditure Project/Scheme Budget £ Expenditure Budget agreed as per The Cabinet 1,135,000 February 2017 The Cabinet 10 April 2017 162,000

The Cabinet 5 June 2017 – Slippage 3,009,998

Portfolio Holder approval – Shottery Hall S.106 32,430

Amended 2017/18 Expenditure Budget 4,339,428

1.5Actual expenditure for the period to 31 March 2018 totals £1,428,802 as detailed in Appendix 1. 1.6 A summary of S.106 money for capital projects currently being held by the Council is shown at Appendix 2. Total funds held amount to £2.4m.

2. Options available to The Cabinet 2.1 Explanations of notable variances and progress on schemes are included within Appendix 1. Details of some of the more significant variances are shown below:- Head of Revenue & ICT 2.1.1 ICT Budget

Budget £1,091,820, Spending £121,865, Underspend £969,955. Main slippage requested is for the BDUK project (£535k) where the Council is working in conjunction with Warwickshire County Council and £360k for Microsoft Licensing. Slippage of £969,955 is requested into 2018/19. Head of Planning & Housing 2.1.2 Minor Works Assistance & Home Repair Grants Budget £166,407, Spending £41,900, Underspend £124,507. Outstanding commitments in relation to approved grants awarded in 2017/18 at 31 March 2018 amount to £10,900. Slippage is therefore requested in order to fund these commitments. Slippage of £10,900 is requested to be approved into 2018/19.

2.1.3 Empty Homes Loan Scheme Budget £100,000, Spending £0, Underspend £100,000. Please slip this budget for the following reason: On the 12 March 2018 The Cabinet agreed to amend the empty homes assistance grant criteria in order to make the scheme more attractive to private property owners. Consequently a budget with which to deliver this amended scheme is necessary. The use of private sector properties, which this scheme will facilitate, is a vital element of the plan to reduce reliance on B&B for accommodating the homeless. Slippage of £100,000 is requested to be approved into 2018/19.

Head of Community & Technical Services 2.1.4 Planned Maintenance

Budget £450,000, Spending £263,829 Underspend £186,171. A commitment exists in relation the ANPR system for Parking Services (£70k). Members are therefore requested to approve slippage of £100k into 2017/18. Slippage of £186,171 is requested into 2018/19. 2.1.5 Greig Centre

Budget £250,000, Spending £0 Underspend £250,000. Following the transfer of the asset to the Council it is requested that this budget be slipped into 2018/19.

Slippage of £250,000 is requested into 2018/19. 2.1.6 Stratford Leisure Centre

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital income and expenditure: revisedAppendix 1 133 KB Download
PDF
Slippage 4th June 18 Captial OutturnAppendix 3 33 KB Download
PDF
Capital Outturn 2017/18 and Capital SlippageReport 73 KB DownloadRead as text
PDF
S.106 Appendix 2 Capital ExpenditureAppendix 87 KB Download

At this meeting

Whole meeting

On this subject at Stratford-on-Avon

Search all
  1. Capital Outturn 2017/18 and Capital SlippageThis decision
  2. Capital Outturn 2025/26 and Capital SlippageDecided
  3. Capital Outturn 2024/25 and Capital SlippageDecided
  4. Capital Outturn 2023/24 and Capital SlippageDecided
  5. Capital Outturn 2022/23 and Capital SlippageAgreed
  6. Capital Outturn 2021/22 and Capital SlippageDecided

More from Stratford-on-Avon The Cabinet

All decisions
MeetingDecisionOutcome
2 Nov 2026 Future of Southam United Football Club(1) That subject to the conditions identified in paragraph 1.4.3 of the agenda report, and subject to the above amend... Decided Open
2 Nov 2026 Strategic Risk RegisterThat the , attached as Appendix 1 to the agenda report, be endorsed. Note: In accordance with the Council’s Constitut... Decided Open
2 Nov 2026 Options for Boosting the Supply of Housing Land Update Report(1) That the progress in delivering the Housing Land Supply Action Plan, the September 2026 housing land supply calcu... Noted Open
2 Nov 2026 Youth Catalyst Project – Service Specification and Permission to Tender(1) That permission to procure a Youth Catalyst Project provision to meet the requirements of the specification, as d... Approved Open
2 Nov 2026 Revenue Budget Monitoring Period 1 - 6 2026/27(1) That the actual net variance as at Period 6, and the estimated revenue outturn for 2026/27, be received; and (2) ... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies