Capital Budget Monitoring

Noted Executive 3 papers

The Cabinet noted this item on Monday 8 October 2018. Below is the council's own wording, with the papers it was decided on.

Item369

Resolved

That the position on Capital expenditure and income for the period 1-5 , 2018 /19 be noted. NOTE: This item is not subject to call-in to the OSC
Word for word from the decision Stratford-on-Avon published for this meeting. Source: democracy.stratford.gov.uk

Follow this further

Built from Stratford-on-Avon's papers

What the report saysPro

Report to The Cabinet, 5 pages

STRATFORD-ON-AVON DISTRICT COUNCIL CAPITAL BUDGET MONITORING P1-5 2018/19

Amended Narrative 2018/19 Estimate agreed by Amendments Latest Amended Committed Actual April - Cabinet 4 already Estimate Estimate April-August August Budget June inc. agreed 2018/19 2018/19 2018/19 2018/19 Remaining slippage £ £ £ £ £ £

GROSS EXPENDITURE

Executive Director, Head of Paid Service 43,500 0 43,500 43,500 0 -8,000 51,500

Head of Governance & Democracy 216,345 465,000 681,345 681,345 40,875 24,198 616,272

Head of Head of Revenues & ICT 1,184,955 0 1,184,955 1,184,955 121,176 184,977 878,802

Head of Planning & Housing 1,666,600 0 1,666,600 1,666,600 32,361 13,574 1,620,665

Head of Community & Technical Services 903,171 625,000 1,528,171 1,528,171 70,382 513,813 1,276,353

Total Capital Expenditure Exc. S106 4,014,571 1,090,000 5,104,571 5,104,571 264,794 728,562 4,443,592

S.106 Projects funded by S.106 and LPSA2 contributions 1,088,334 0 1,088,334 1,088,334 29,753 190,279 868,302

Total S.106 Project Expenditure 1,088,334 0 1,088,334 1,088,334 29,753 190,279 868,302

TOTAL 5,102,905 1,090,000 6,192,905 6,192,905 294,547 918,841 5,311,894

FINANCED FROM:- Section 106 Contributions & LPSA2 Grant 1,088,334 0 1,088,334 1,088,334 0 0 1,088,334 To fund S.106 schemes included below in the capital programme.

Venture House Grant 1,164 1,164 1,164 0 1,164 Balance of grant carried forward to cover retention.

Right to Buy Receipts : Clawback Houses 200,000 200,000 200,000 253,406 -53,406 Income expected from the sale of houses transferred as part of the LSVT to Orbit/HoE.

Revenue Contribution 0 1,090,000 1,090,000 1,090,000 1,090,000 A revenue contribution funded from the income generated from CIL to cover the costs of the new system. New Capital Receipts 500,000 500,000 500,000 0 500,000 the Pit - 16/17 The Grange Southam 17/18 Canal Quarter (from old football ground)19/20 & 20/21??? TOTAL 1,789,498 1,090,000 2,879,498 2,879,498 0 253,406

Use of Capital Receipts and Captal Grants:

Capital Receipts b/fwd 7,237,379 7,237,379 7,237,379 Add Capital Grants (exc. S.106 & LPSA2) 1,164 1,164 1,164

Add new funds in this year and financing of projects 700,000 1,090,000 1,790,000 1,790,000 0

Total SDC Receipts available to spend 7,938,543 1,090,000 9,028,543 9,028,543

Less net expenditure in this year (exc. S.106) 4,014,571 1,090,000 5,104,571 5,104,571

Remaining Capital Receipts & Capital Grants estimated 3,923,972 0 3,923,972 3,923,972 at 31 March 2019

1 STRATFORD-ON-AVON DISTRICT COUNCIL CAPITAL BUDGET MONITORING P1-5 2018/19

Amended Narrative 2018/19 Estimate agreed by Amendments Latest Amended Committed Actual April - Cabinet 4 already Estimate Estimate April-August August Budget June inc. agreed 2018/19 2018/19 2018/19 2018/19 Remaining slippage £ £ £ £ £ £

Executive Director and Head of Paid Service Business Support 38,500 38,500 38,500 0 0 38,500 This budget provides a package of support for businesses by way of a loan or grant.

Landlords Accreditation Scheme 0 0 0 0 0 0 An earmarked reserve balance of £22,497 is remaining from the original £24k approved at Cabinet 17/6/13. This reserve will be used to fund any expenditure relating to the Landlords Accreditiation Scheme.

Market Town Regeneration 0 0 0 0 -8,000 8,000 Manual provisional creditor b/f from 17/18 to be spent in 18/19 on shop front grants.

Affordable Housing Investment Programme 5,000 5,000 5,000 0 0 5,000 The balance of £5k committed via an agreement for a site at Stockton.

Total Executive Director and Head of Paid Service 43,500 0 43,500 43,500 0 -8,000 51,500

Head of Governance & Democracy

CCTV Equipment - Birmingham Road 0 0 0 0 -24,577 24,577 Installation of CCTV cameras on the Birmingham Road, using wifi cameras is to be installed and 3 cameras on the Birmingham Road (including the new one). Site survey has been carried out and the Planning Application submitted, awaiting approval. KS 8/8/18

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Appx 1 P1-5 18-19Report 5 pages DownloadRead as text
PDF
Capital Appx 2 S.106Report 4 pages Download
PDF
Capital Budget MonitoringReport 2 pages Download

At this meeting

Whole meeting

On this subject at Stratford-on-Avon

Search all
  1. Capital Budget MonitoringThis decision
  2. Capital Budget Monitoring Period 1 - 6 2026/27Decided
  3. Capital Budget Monitoring Period 1 - 4 2026/27Decided
  4. Capital Budget Monitoring Period 1 - 2 2026/27Decided
  5. Capital Budget Monitoring - Period 1 - 10 2025/26Decided
  6. Revenue and Capital Budget 2026/27Approved

More from Stratford-on-Avon The Cabinet

All decisions
MeetingDecisionOutcome
2 Nov 2026 Future of Southam United Football Club(1) That subject to the conditions identified in paragraph 1.4.3 of the agenda report, and subject to the above amend... Decided Open
2 Nov 2026 Strategic Risk RegisterThat the , attached as Appendix 1 to the agenda report, be endorsed. Note: In accordance with the Council’s Constitut... Decided Open
2 Nov 2026 Options for Boosting the Supply of Housing Land Update Report(1) That the progress in delivering the Housing Land Supply Action Plan, the September 2026 housing land supply calcu... Noted Open
2 Nov 2026 Youth Catalyst Project – Service Specification and Permission to Tender(1) That permission to procure a Youth Catalyst Project provision to meet the requirements of the specification, as d... Approved Open
2 Nov 2026 Revenue Budget Monitoring Period 1 - 6 2026/27(1) That the actual net variance as at Period 6, and the estimated revenue outturn for 2026/27, be received; and (2) ... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies