Capital Outturn 2020/21 and Capital Slippage

Decided Executive 4 papers

The Cabinet decided this item on Monday 5 July 2021. Below is the council's own wording, with the papers it was decided on.

Item101

Resolved

That the Capital Budget for 2021/22 be increased by £8,537,675, as detailed in Appendix 1 to the agenda report, for slippage, as detailed in Appendix 3 to the agenda report, financed by the capital receipts as budgeted for in 2020/21. NOTE: This item is not subject to call-in to the OSC as it is not a key decision
Word for word from the decision Stratford-on-Avon published for this meeting. Source: democracy.stratford.gov.uk

Follow this further

Built from Stratford-on-Avon's papers

What the report saysPro

Report to The Cabinet, 6 pages

Recommendation

That the Capital Budget be increased by £8,537,675, as detailed in Appendix 1, in 2021/22 for slippage, listed in Appendix 3, financed by the capital receipts as budgeted for in 2020/21.

1 Background/Information 1.1 Table 1 Capital Budget Summary Position 1.2 Table 1 summarises the Council’s estimated position with regard to Accumulated Capital Receipts:-

Accumulated Capital Receipt and Capital Grants of £6,399,085 1 April 2020

Plus new funds and financing in 2020/21 £1,598,036

Less Expenditure for 2020/21 (£2,313,328)

Remaining accumulated capital receipts and capital £5,683,794 grants at 31 March 2021

1.3In February 2020 the Council agreed the Capital Expenditure Budget for 2020/21 budget, totalling £5,822,000. With the amendments agreed by The Cabinet to date, the total Capital Expenditure Budget for the current year, including S.106, now totals £10,756,044. This is derived from the addition/removal of budget changes summarised in Table 2: 1.4 Table 2 – Capital Expenditure - Summary of changes in 2020/21

2020/21 Gross Project/Scheme Expenditure Budget £ Expenditure Budget agreed as per The Cabinet, February 2020 5,822,000

Approved S.106 projects carried forward from 19/20 512,229

The Cabinet 6 July 2020 - slippage 3,908,482

The Cabinet 7 September 2020 Fred Winter S.106 Project 400,000

The Cabinet 7 September 2020 Public Arts S.106 Project 31,626 The Cabinet 7 September 2020 Shottery Fields Play Area S.106 7,710 Project Shipston Flood Risk CIL Infrastructure Project 80,000

471,821 WHG Affordable Housing Scheme Southam S.106 Project

CCTV Wellesbourne S.106 Project 16,254

CCTV Southam Play area S.106 Project 23,937

Alcester Flood Risk CIL Infrastructure Project 200,000 1 Evesham Place High Support Capacity Building Scheme, CIL 750,000 Infrastructure Project Project budget releases outlined by George Hill, February 2021 (1,467,944)

Amended 2020/21 Expenditure Budget 10,756,115

1.5Actual expenditure for the period to 31 March 2021 totals £2,313,328 as detailed in Appendix 1. 1.6 A summary of S.106 money for capital projects currently being held by the Council is shown at Appendix 2. Total S.106 funds held amount to £4.90m. Committed CIL funds amount to £1.03m

2. Options available to The Cabinet 2.1 Explanations of notable variances and progress on schemes are included within Appendix 1. Details of some of the more significant variances are shown below: Deputy Chief Executive 2.1.1 Strategic Review of IT & WoW Transformation Budget £736,580, Spending £260,230, Underspend £476,350 Continued support is required. Slippage of £476,350 is requested into 2021/22 Head of Regulatory Services 2.1.2 Environmental/Streetscene Improvements Budget £178,314, Spending £0, Underspend £178,314 Continued support is required. Slippage of £178,314 is requested into 2021/22

Interim Head of Resources and Transformation (S.151 Officer) 2.1.3 Planned Maintenance Budget £459,257, Spending £159,025, Underspend £300,232 Continued support is required. Slippage of £300,232 is requested into 2021/22 2.1.4 Housing Initiatives Budget £382,247, Spending £0, Underspend £382,247 Continued support is required. Slippage of £382,247 is requested into 2021/22 2.1.5 Next Steps Accommodation Programme Budget £300,000, Spending £154,000, Underspend £146,000 Continued support is required as the remaining 3 properties have already been purchased in 2021/22. Slippage of £146,000 is requested into 2021/22

Head of Community & Operational Services 2.1.6 Materials Recycling Centre Budget £5,000,000, Spending £0, Underspend £5,000,000 Continued support is required as first tranche of funding has been paid in 2020/21. Slippage of £5,000,000 is requested into 2021/22

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Outturn P1-12 20-21 v2Appendix 1 5 pages Download
PDF
Capital Outturn P1-12 20-21 to 31.03.21Appendix 2 5 pages Download
PDF
Capital Slippage 5 July 2021Appendix 3 1 pages Download
PDF
Capital Outturn 2020/21 and Capital SlippageReport 6 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Stratford-on-Avon

Search all
  1. Capital Outturn 2020/21 and Capital SlippageThis decision
  2. Capital Outturn 2025/26 and Capital SlippageDecided
  3. Capital Outturn 2024/25 and Capital SlippageDecided
  4. Capital Outturn 2023/24 and Capital SlippageDecided
  5. Capital Outturn 2022/23 and Capital SlippageAgreed
  6. Capital Outturn 2021/22 and Capital SlippageDecided

More from Stratford-on-Avon The Cabinet

All decisions
MeetingDecisionOutcome
2 Nov 2026 Future of Southam United Football Club(1) That subject to the conditions identified in paragraph 1.4.3 of the agenda report, and subject to the above amend... Decided Open
2 Nov 2026 Strategic Risk RegisterThat the , attached as Appendix 1 to the agenda report, be endorsed. Note: In accordance with the Council’s Constitut... Decided Open
2 Nov 2026 Options for Boosting the Supply of Housing Land Update Report(1) That the progress in delivering the Housing Land Supply Action Plan, the September 2026 housing land supply calcu... Noted Open
2 Nov 2026 Youth Catalyst Project – Service Specification and Permission to Tender(1) That permission to procure a Youth Catalyst Project provision to meet the requirements of the specification, as d... Approved Open
2 Nov 2026 Revenue Budget Monitoring Period 1 - 6 2026/27(1) That the actual net variance as at Period 6, and the estimated revenue outturn for 2026/27, be received; and (2) ... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies