Stratford-on-Avon District Council
The Cabinet, Monday 1 July 2024

Capital Budget Monitoring - Period 1 - 2 2024/25

Decided Executive 3 papers

The Cabinet decided this item on Monday 1 July 2024. Below is the council's own wording, with the papers it was decided on.

Item99

Resolved

That the position on capital expenditure and income for Period 1 - 2 (1 April – 31 May 2024) be received. Note: This item is not subject to call-in to the OSC as it is not a key decision
Word for word from the decision Stratford-on-Avon published for this meeting. Source: democracy.stratford.gov.uk

Follow this further

Built from Stratford-on-Avon's papers

What the report saysPro

Report to The Cabinet, 5 pages

The Cabinet 1 July 2024

Title: Capital Budget Monitoring Period 1 – 2 2024/25

Lead Officer: Nicola Reynolds, Financial Accountant (01789 260608)

Portfolio Holder/ Lead Member: Councillor D Curtis

Summary This report provides The Cabinet with details of the Capital Budget Monitoring for the period 1 – 2 (1 April 2024 to 31 May 2024).

Recommendation That the position on capital expenditure and income for the period 1 – 2 of 2024/25 is received, and any issues identified for further consideration be addressed by: (1) A further report to The Cabinet; (2) The Portfolio Holder.

1 Background/Information 1.1 Table 1 Capital Budget Summary Position Table 1 summarises the Council’s estimated position with regard to accumulated capital receipts: Accumulated capital receipts and capital grants as £6,226,768 at 1 April 2024 Less budgeted expenditure for 2024/25 (1,735,000) Plus new funds and financing in 2024/25 £1,530,000 Plus budgeted Capital Financing Movement £205,000 Accumulated estimated capital receipts and £6,226,768 capital grants as at 31 March 2025

1.2In February 2024 the Council agreed the capital expenditure budget for 2024/25 financial year totalling £1,735,000, as summarized in Table 2. 1.3 Table 2 – Capital expenditure –2024/25 2024/25 Gross Project/scheme expenditure budget £ Expenditure budget agreed as per The Cabinet, 12 1,735,000 February 2024 2024/25 expenditure budget 1,735,000

1.4Actual (£9,567) and committed (£305,784) expenditure for the period to 31 May 2024 totals £315,351 as detailed in Appendix 1. 1.5 A summary of S.106 money for capital projects being held by the Council is shown in Appendix 2. Total S.106 funds held amount to £12.4m (including committed/spent funds of £631k). Committed & spent CIL funds amount to £3.01m. Both S.106 & the CIL committed and spent form part of the proposed 2023/24 slippage (see 2023/24 Outturn). 2 Options available to The Cabinet. 2.1 To receive the report on capital expenditure for Periods 1 – 2 of 2024/25.

3 Evidence Base 3.1 The draft outturn position has been prepared by comparing the actual and accrued capital expenditure against the current budget for 2024/25. 4 Consultation and Members’ comments 4.1 Comments from the Portfolio Holder have been incorporated into this report. 5 Implications of the proposal 5.1 Legal Implications 5.1.1 There are no direct legal implications arising from this report. 5.2 Financial 5.2.1 This is a financial report. 5.3 Council Plan 5.3.1 The Capital Programme supports various aims within the Council Plan. This report is restricted, however, to the financial implications of the Council’s Capital Budget.

5.4Environmental/Climate Change Implications 5.4.1 Not applicable. 5.5 Analysis of the effects on Equality 5.5.1 None directly. 5.6 Data Protection 5.6.1 There are no data protection implications to this report. 5.7 Health and Wellbeing 5.7.1 There are no health and wellbeing implications to this report. 5.8 Human Resources/Staffing 5.8.1 There are no human resource implications to this report. 6 Risk Assessment 6.1 Not applicable. 7 Conclusion/Reasons for the Recommendation 7.1 Work continues in the current financial year to ensure that as many projects as possible are delivered within their intended timescales.

Richard Burrell

HEAD OF FINANCE (S.151 OFFICER)

Background papers: None. Form A1 INITIAL SCREENING FOR STRATEGIES/POLICIES/FUNCTIONS FOR EQUALITIES RELEVANCE TO ELIMINATE DISCRIMINATION, PROMOTE EQUALITY AND FOSTER GOOD RELATIONS

1. Please provide a summary of the proposal (including any legislation/guidance if relevant)

This report provides The Cabinet with details of the Capital Budget Monitoring 2024/25.

2. Tick all of the coloured boxes appropriately depending on degree of relevance/priority to each of the equality strands set out below following an assessment of the OVERALL IMPACT DESCRIPTORS.

High Medium Low or no relevance/priority relevance/priority relevance/ priority

Business Relevance/Risk to Equalities Unit/ Services: State the

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Bud Mon P1-2 24-25 DRAFTAppendix 1 5 pages Download
PDF
S106 & CIL Actual & Committed Spend P1: 2 24-25 DRAFTAppendix 2 5 pages Download
PDF
Capital Budget Monitoring: Period 1: 2 2024/25Report 5 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Stratford-on-Avon

Search all
  1. Capital Budget Monitoring - Period 1 - 2 2024/25This decision
  2. Capital Budget Monitoring Period 1 - 6 2026/27Decided
  3. Capital Budget Monitoring Period 1 - 4 2026/27Decided
  4. Capital Budget Monitoring Period 1 - 2 2026/27Decided
  5. Capital Budget Monitoring - Period 1 - 10 2025/26Decided
  6. Revenue and Capital Budget 2026/27Approved

More from Stratford-on-Avon The Cabinet

All decisions
MeetingDecisionOutcome
2 Nov 2026 Future of Southam United Football Club(1) That subject to the conditions identified in paragraph 1.4.3 of the agenda report, and subject to the above amend... Decided Open
2 Nov 2026 Strategic Risk RegisterThat the , attached as Appendix 1 to the agenda report, be endorsed. Note: In accordance with the Council’s Constitut... Decided Open
2 Nov 2026 Options for Boosting the Supply of Housing Land Update Report(1) That the progress in delivering the Housing Land Supply Action Plan, the September 2026 housing land supply calcu... Noted Open
2 Nov 2026 Youth Catalyst Project – Service Specification and Permission to Tender(1) That permission to procure a Youth Catalyst Project provision to meet the requirements of the specification, as d... Approved Open
2 Nov 2026 Revenue Budget Monitoring Period 1 - 6 2026/27(1) That the actual net variance as at Period 6, and the estimated revenue outturn for 2026/27, be received; and (2) ... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies