The Cabinet, Monday 9 March 2026

The procurement of contractors for works at Elizabeth House

Noted Executive 1 paper

AI summaryStratford-on-Avon District Council Cabinet noted progress on procuring contractors for safety works at Elizabeth House, with electrical work due to start in early April and fire safety work within two months.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCabinet asked to note the report on progress.
Money566 and 244Capital costs listed for electrical and fire works, both fully budgeted.
What happens nextWorks to start soonElectrical work in early April, fire work within two months.
Who it affectsStaff and visitors at Elizabeth HouseBuilding compliance and safety works in progress.

What was decided

The Cabinet noted the contents of the progress report on procurement of contractors for works at Elizabeth House. Report P5

The item was not subject to call-in to the Overview and Scrutiny Committee as it was not a key decision.

Why

Building checks over the last 18 months identified works needed to meet regulatory requirements and keep staff and visitors safe. Report P6

Two main areas were identified: replacement of emergency lights and associated electrical works, and repairs to fire doors and fire compartmentalisation. Report P6

A Leader's decision on 29 September 2025 had already approved procurement of the contractors, and this report provided the requested update. Report 1.4, P10

What happens next

A contractor for emergency lights and electrical works has been appointed and contracts are being finalised, with works hoped to start in early April, some carried out out of hours to reduce disruption. Report 1.5

A contractor for fire compartmentalisation and fire safety work has been appointed; contracts are being finalised with a view to starting within the next two months, with work programming aimed at minimising disruption.

Pulse Ltd was used as external consultants to agree the specification and tender the works because the council had no Construction Manager in post. Report P7

The money

  • 566 Capital cost of electrical works proposal, 2025/26 to 2028/29 Report P10
  • 566 Currently budgeted for electrical works, 2025/26 to 2028/29 Report P10
  • 0 Cost or saving of electrical works proposal Report P10
  • 244 Capital cost of fire works proposal, 2025/26 to 2028/29 Report P11
  • 244 Currently budgeted for fire works, 2025/26 to 2028/29 Report P11
  • 0 Cost or saving of fire works proposal Report P11

Options considered

  • Chosen: Note the report. Only option presented; allows Cabinet to receive the update requested as part of the Leader's decision. Report P10

Implications

  • Legal: Work is required to ensure compliance with relevant Health and Safety legislation and staff and visitor safety.
  • Financial: Capital costs of 566 (electrical) and 244 (fire works) are already fully budgeted across 2025/26 to 2028/29, with no cost or saving against the proposal. Report P10, P11
  • Equalities: Initial screening identified low or no relevance across all equality strands; no effects on equality were identified. Report P29
  • Climate: Climate change implications have been included in the specification, with sensor lighting to reduce electricity use. Report 5.4
  • Staffing: No staffing implications; works are being carried out as part of the everyday duties of the Construction Team.
  • Risk: Works are needed to address risks identified by Fire Risk Assessments and Fixed Wire Testing and to meet regulatory compliance. Report P10

Who and where

  • Staff working at Elizabeth House Report P6
  • Visitors and members of the public using the building Report P6
  • Council service delivery based at Elizabeth House Report 5.3

Timeline

  • 29 September 2025: Leader's decision approved procurement of contractors to carry out various works at Elizabeth House. Report 1.4
  • Last 18 months to 9 March 2026: Building checks carried out on Elizabeth House to check regulatory requirements. Report P6
  • 9 March 2026: Cabinet received and noted the update report on progress of works. Report P1
  • Within two months of 9 March 2026: Fire compartmentalisation and fire safety work planned to start, subject to contract finalisation.
  • Early April 2026: Electrical works hoped to commence, with some done out of hours to minimise disruption. Report 1.5

Plain English for the jargon

  • Fire compartmentalisation: Dividing a building into sections using fire-resistant walls and doors to slow the spread of fire and smoke.
  • Fire Risk Assessment: An inspection and review to identify fire hazards and the people at risk in a building.
  • Fixed Wire Testing: Periodic inspection and testing of the fixed electrical installations in a building.
  • Leader's decision: A decision taken by the leader of the council under delegated authority, used here to approve the procurement ahead of this update report.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item560

Resolved

That the contents of the report be noted. Note: This item is not subject to call-in to the OSC as it is not a key decision.
Word for word from the decision Stratford-on-Avon published for this meeting. Source: democracy.stratford.gov.uk

Follow this further

Built from Stratford-on-Avon's papers

What the report saysPro

Report to The Cabinet, 6 pages

The Cabinet 9 March 2026

Title: The procurement of contractors for works at Elizabeth House

Lead Officer: Julie Lewis, Head of Environmental and Neighbourhood Services (01789 267575)

Portfolio Holder/ Lead Member: Councillor L Grocott

Summary To update The Cabinet on the progress of works at Elizabeth House. Recommendation That the contents of the report be noted.

1 Background/Information 1.1 Elizabeth House is a very large and ageing building. A number of building checks have been carried out over the last 18 months to ensure that the building meets regulatory requirements. 1.2 These have identified some areas where work has been needed to ensure the building meets the relevant regulatory requirements and is safe for staff and visitors. 1.3 Two main areas of work were identified, outlined as follows: 1.3.1 Replacement of emergency lights and various associated distribution boards and electrical works. Several of the lights are unable to be repaired due to parts no longer being available. As they are part of an integrated lighting system this has meant complete exploration of design options and use of specialist companies to determine the extent of work needed to ensure compliance and at the same time maximising opportunities to reduce CO2 by installing smart scan options. Due to this being a recommendation to ensure compliance with regulations and concerns about staff and public safety in the building the work needs to be completed as soon as possible. 1.3.2 Repairs and alterations to fire doors and fire compartmentalisation to meet requirements of Fire Risk Assessments relative to the current and proposed future use of Elizabeth House. Comprehensive surveys have been undertaken by specialist companies to determine the exact scope of the works needed, given the age of the building, it’s use by staff and members of the public and to ensure that relevant legislation is complied with.

1.3.3 The work was outsourced to consultants, Pulse Ltd, to agree the specification and tender the works due to the absence of a Construction Manager.

1.4Leader’s Decision 1.4.1 A Leader’s decision was made on 29 September 2025 to ‘approve the procurement of contractors to carry out various works at Elizabeth House to comply with recommendations from statutory regulatory inspections for health and safety and building maintenance.’

1.5Emergency Lights and Electrical Works 1.5.1 A scope of works has been agreed and a contractor appointed. Details of the specification, price and contracts are being finalised and it is hoped works will commence in early April. Due to the need to switch off power, some of the work will be done out of hours to minimise disruption. 1.6 Fire compartmentalisation and Fire Safety Work 1.6.1 The need for this was identified in Fire Risk Assessments. It has taken a considerable time to finalise the exact specification of works due to the changing uses of rooms and changes to the use of rooms in the building. A final specification has now been agreed and a contractor appointed. Contracts are being finalised with a view to starting the work in the next two months. A considerable amount of work programming is underway to minimise staff and customer disruption and to try to combine different contractors all working at the same time. 2 Options available to The Cabinet 2.1 To note the report.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
The procurement of contractors for works at Elizabeth HouseReport 6 pages DownloadRead as text

More from Stratford-on-Avon The Cabinet

All decisions
MeetingDecisionOutcome
2 Nov 2026 Future of Southam United Football Club(1) That subject to the conditions identified in paragraph 1.4.3 of the agenda report, and subject to the above amend... Decided Open
2 Nov 2026 Strategic Risk RegisterThat the , attached as Appendix 1 to the agenda report, be endorsed. Note: In accordance with the Council’s Constitut... Decided Open
2 Nov 2026 Options for Boosting the Supply of Housing Land Update Report(1) That the progress in delivering the Housing Land Supply Action Plan, the September 2026 housing land supply calcu... Noted Open
2 Nov 2026 Youth Catalyst Project – Service Specification and Permission to Tender(1) That permission to procure a Youth Catalyst Project provision to meet the requirements of the specification, as d... Approved Open
2 Nov 2026 Revenue Budget Monitoring Period 1 - 6 2026/27(1) That the actual net variance as at Period 6, and the estimated revenue outturn for 2026/27, be received; and (2) ... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies