Resolved
To note the current spending position against the original estimates, and the issues arising and impacting on the 2007/08 budget.
The Executive noted this item on Tuesday 15 January 2008. Below is the council's own wording, with the papers it was decided on.
Resolved
To note the current spending position against the original estimates, and the issues arising and impacting on the 2007/08 budget.
Page 1 Agenda Item 4
London Borough of Sutton
The Executive – 15 January 2008
Report of the Executive Head of Financial Services
REVENUE BUDGET 2007/08 - REVIEW AS AT 30 NOVEMBER 2007
Ward Location: Not Applicable Author(s) and Contact Phone Number(s): David Dominey, Head of Accountancy Services (020) 8770 5375 Area Served: Borough-Wide Executive Member: Cllr John Drage
Key Decision Report
Summary This report indicates the financial position at month eight for the Council’s Service Groups and estimates the full year effects in 2007/08 of current levels of spending and income. The projected year end position is an overspend of £151k compared with an underspend of £196k when last reported. Recommendations I recommend The Executive to note the current spending position against the original estimates, and review issues arising and impacting on the 2007/08 budget
1. Background 1.1 The month eight figures form the basis for revised estimates 2007/08 which will be considered by The Executive on 19 February 2008. The current projections build on trends and variations previously reported.
2. Issues 2.1 The latest overall position on the General Fund shows an overspending of £9k at 30 November 2007, and a projected overspending of £151k for the full year. 2.2 Since the October figures were reported, the projected full year budget variance on the General Fund has increased by £347k and is now showing a £151k overspending. The main change has occurred in the Environment and Leisure Group projection as detailed below (paragraph 2.6). In terms of the overall position the currently projected overspending is more than covered by the unallocated balance on the central contingency provision (see para 2.13). 2.3 A summary of latest estimates reflecting Service Groups’ anticipated expenditure for 2007/08, compared to the original estimates, is attached as Appendix A. A summary of the major variances at month eight for the General Fund is attached as Appendix B.
1 Agenda Item 4 Page 2
2.4A summary of the latest position for trading services is attached as Appendix C.
Adult Social Services and Housing 2.5 The projected underspending on Adult Social Services has increased by a further £108k since month seven to £669k, and reflects the ongoing trend of lower than predicted demand for residential and nursing care and greater emphasis on provision of homecare. 2.6 Community living is predicted to overspend by £89k, due in the main to the level of bad and doubtful debts from the provision of temporary and/or emergency accommodation.
Environment and Leisure 2.7 The projected overspend has increased by £487k since month seven to £668k. The increase in projected overspend is mainly due to:- a. Projected overspendings on property repairs and maintenance - £344k. Whilst repairs have been carried out during the year by the Council’s contractor, Inspace, and accounts settled for work done, technical problems with linking the “Orderline” system to Agresso has meant that no costs were posted to the ledger until November. This has now been resolved and the overspending has come to light. The servicing contract has identified a higher level of repairs needed to catch up to acceptable standards. Managers have been instructed to carry out only health and safety work for the rest of this financial year. The impact of this instruction will be reflected in the next cycle of budget monitoring reporting. Investigations in to this are ongoing and findings will be reflected in future reports. b. Transportation costs that can no longer be funded from the Parking Reserve Account - £130k.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
High Level Monitoring Report: revisedReport | 64 KB | DownloadRead as text |
PDF |
High Level Monitoring Report appendix B revisedAppendix | 52 KB | Download |
PDF |
High Level Monitoring report appendix revisedAppendix | 48 KB | Download |
Follow The Executive at Sutton and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 8 May 2012 | Advocacy Commissioning(i) To note the contents of the report and progress made to date in reviewing and realigning advocacy services to mee... | Noted | Open |
| 8 May 2012 | Domestic Violence - Strategic Options(i) That the proposals set out in paragraphs 4 to 6 in the report be endorsed; (ii) To agree to forward the report to... | Agreed | Open |
| 8 May 2012 | Review of Housing Allocations Policy and Development of a Tenancy Strategy( i ) That the draft revised housing allocations policy, as set out in Appendix 1 to the report, be approved and adop... | Approved | Open |
| 8 May 2012 | Sutton Housing Partnership Delivery Plan 2012/13To approve the Sutton Housing Partnership Delivery Plan for 2012/13. | Approved | Open |
| 8 May 2012 | Epsom and Ewell Borough Council Insurance Arrangements(i) To agree to the principle of the provision of insurance services to Epsom and Ewell Borough Council and to author... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.