Resolved
(i) To note the latest position on capital expenditure and resources; (ii) To agree the revised level of invest-to-save funding required for corporate energy efficiency schemes of £92.3k, as detailed in paragraph 2.6 of the report.
The Executive noted this item on Tuesday 15 January 2008. Below is the council's own wording, with the papers it was decided on.
Resolved
(i) To note the latest position on capital expenditure and resources; (ii) To agree the revised level of invest-to-save funding required for corporate energy efficiency schemes of £92.3k, as detailed in paragraph 2.6 of the report.
Page 17 Agenda Item 5
London Borough of Sutton
The Executive – 15 January 2008
Report of the Executive Head of Financial Services
HIGH LEVEL MONITORING – CAPITAL PROGRAMME 2007/08
Ward Location: Not Applicable Author(s) and Contact Phone Number(s): Tony Cooke, 020 8770 5379 Area Served: Borough-Wide Lead Councillor: John Drage
Key Decision Report Summary This report reviews the latest position of 2007/08 capital expenditure and resources.
Recommendations I recommend the Committee to: a) consider and note the latest position on capital expenditure and resources. b) agree the revised level of invest-to-save funding required for corporate energy efficiency schemes of £92.3k as detailed in paragraph 2.6.
1. Background 1.1 This is the fifth report for the current financial year which sets out: (i) the latest estimate of capital expenditure for the year updated from the Capital Budget approved by Council on 5 March 2007. (ii) the revised resource position for 2007/08. (iii) the actual payments made up to 30 November 2007 against profiled estimates.
2. Issues 2.1 A surplus of £9.897m is forecast for General Fund Services for 2007/08, which is an increase of £1.003m from month 7 reported to The Executive on 3 December 2007. The deficit in the resource position over the three-year budget cycle to the end of 2009/10 has improved slightly to £2.1m, an improvement of £0.200m. Latest Estimates 2.2 The table overleaf shows the position for the current financial year. Estimated expenditure on capital schemes for the year has reduced by £1.003m since month 7. This is due to a number of areas of slippage of expenditure, which include Kimpton Road Re-Use & Recycling Centre of £0.158m, Cheam Leisure Centre Roof Repairs of £0.120m, Mandatory Disabled Facilities Grant payments of £0.200m and S106 funded highways schemes totalling £0.393m. Agenda Item 5 Page 18
PREVIOUS LATEST PROFILED PAYMENTS EXPENDITURE ESTIMATE ESTIMATE PAYMENTS T0 30/11/07 (Details in Appendix) T0 31/12/07 £000 £000 £000 £000 Adult Social Services and Housing 10,300 10,408 7,727 6,28 Children, Young People & Learning 24,125 24,195 9,161 7,908 Environment and Leisure 12,654 11,473 5,777 4,10 Resources and Chief Executive’s 3,738 3,738 2,041 8 1,71 TOTAL EXPENDITURE 50,817 49,814 24,706 2 20,015 RESOURCES Government Supported Borrowing 6,615 6,615 Sutton Approved Prudential Borrowing 2,380 2,380 Borrowing b/fwd from 2006/07 1,331 1,331 Usable Capital Receipts (in year) 17,473 17,555 Government grants 19,494 19,750 Other Public Sector Grants & contribtn. 3,275 3,284 Developer & Private Sector contribtns. 3,943 3,605 Major Repairs Allowance 4,468 4,468 Revenue financing 732 723 TOTAL RESOURCES 59,711 59,711 Estimated Surplus 31.3.2008 8,894 9,897
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Capital MOn reportReport | 66 KB | DownloadRead as text |
PDF |
Capital Mon ASSHReport | 55 KB | Download |
PDF |
Capital Mon Appx 2Report | 51 KB | Download |
PDF |
Capital Mon CYPLSReport | 55 KB | Download |
PDF |
Capital Mon E&LReport | 57 KB | Download |
PDF |
Capital Mon Res&CEReport | 55 KB | Download |
Follow The Executive at Sutton and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 8 May 2012 | Advocacy Commissioning(i) To note the contents of the report and progress made to date in reviewing and realigning advocacy services to mee... | Noted | Open |
| 8 May 2012 | Domestic Violence - Strategic Options(i) That the proposals set out in paragraphs 4 to 6 in the report be endorsed; (ii) To agree to forward the report to... | Agreed | Open |
| 8 May 2012 | Review of Housing Allocations Policy and Development of a Tenancy Strategy( i ) That the draft revised housing allocations policy, as set out in Appendix 1 to the report, be approved and adop... | Approved | Open |
| 8 May 2012 | Sutton Housing Partnership Delivery Plan 2012/13To approve the Sutton Housing Partnership Delivery Plan for 2012/13. | Approved | Open |
| 8 May 2012 | Epsom and Ewell Borough Council Insurance Arrangements(i) To agree to the principle of the provision of insurance services to Epsom and Ewell Borough Council and to author... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.