( i) To commit the use of the £150k allocated to Collingwood Recreational grounds to allow work to commence. (ii)To note other public realm updates (iii)That Councillor Cliff Carter would become the Tree Trail representatives for Sutton Local committee.
Word for word from the decision Sutton published for this meeting.Source: moderngov.sutton.gov.uk
London Borough of Sutton Report to Sutton Local Committee 16th October 2008
Report of the Lead officer for Sutton Local Committee
Public Realm Projects
Ward Location: Sutton North, West & Author(s) and Contact Phone Number(s): Central Matt Clubb – Lead Officer (020 8770 6128) Area Served: Sutton Lead Councillor: Ruth Dombey
Report for Decision
Summary This report will provide details of the proposed scheme for Collingwood Rec identified for the use of the public realm funding and the timescales for the completion of the project. Recommendation 1 – That committee note the proposed improvements to the park 2 – Agreement that the funds allocated (£150k) to Collingwood Rec in April 2008 are formally released to allow work to commence.
1. Background 1.1 Sutton Local Committee has been allocated £330k of Public Realm funding to invest in the public realm over the next two financial years (2008/09 & 2009/10) 1.2 This funding has been identified from the London Borough of Suttons Capital Programme and there for is only available for use on capital projects. A report was received by this committee in April 2008 which allocated the £330k to various schemes and authorised the release of £180k for six of the seven schemes. The remaining £150k was allocated to Collingwood Rec. At the point of receiving the report in April the final designs for the improvements to Collingwood Rec had not been agreed by stakeholders. It was therefore requested that a report be brought to the committee on completion of the designs. 2. Issues 2.1 Work has been carried out by officers of the LBS with the friends of Collingwood Rec and other stakeholders including the Safer Neighbourhood Team to agree on the improvements to the park. 2.2 A presentation was received by this committee in July from those involved in the project to inform the committee of the plans for the park. As a result of that meeting
1 Agenda Item 12 Page 8
plans have been finanlised with further consultation planned prior to commencement of the scheme. 2.3 The agreed proposal for the improvements of the park include the following o Install new sunken, concrete skatebowl, create new path linking skatebowl to ballcourt area (£60k) o Install new side panels to existing ballcourt, refurbish goal ends, block paint whole surface of court, and paint on new sports pitch markings (£20k) o Install new playground with dog-free fencing (£70k) 2.4 The timescales for the remaining work are Consutation – November to January Review of consultation – February Agreement of scheme – March Commencement of work – April 2009 Completion – October 2009. 2.5 The committee are requested to agree to the use of the £150k allocated to Collingwood Rec in April 2008 as detailed in 2.3 of this report. 3. Financial Implications 3.1 The 2008/9 and 2009/10 Capital Estimates contain £2m for the Public Realm Scheme which has been allocated to the six local committees on the basis of population. The Sutton Local Committee has been allocated £330k. 3.2 The estimated cost of the works detailed in this report at Collingwood Rec are £150k and can be funded from the balance of the Public Realm funding which has been allocated to this committee. 3.3 The Parks Service has confirmed that it will fund the normal, ongoing maintenance costs associated with these projects from within existing revenue budgets, however it will not be able to fund costs associated with vandalism to, and/or replacement of, items of equipment.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.