St. Helier, The Wrythe and Wandle Valley Local Committee noted this item on Tuesday 30 June 2009. Below is the council's own wording, with the papers it was decided on.
( i ) To note the completion of 8 projects totalling £42,500. These range from security fencing works at The Quad youth centre to increase access times, to planting of additional trees along Green Lane and improvements to the tennis courts in Royston Park. (ii) To note the progress with a further 6 projects currently underway or with orders placed at a total cost of £110,100. These include re-laying and re-surfacing footpaths at St Helier open space and ... view the full minutes text for item 564.
Word for word from the decision Sutton published for this meeting.Source: moderngov.sutton.gov.uk
Report to St. Helier, The Wrythe and Wandle Valley Local Committee
Background
1.1Progress on this programme was last detailed in a report to the Local Committee on 7 April 2009 following a period of consultation with key stakeholders including local councillors, special advisers, local residents and other interested groups in the Locality. The purpose of the programme is to:
“Develop our town, district and local centres, including parks, open spaces and playgrounds to enable them to thrive, and better meet the needs of residents and businesses, making them more attractive places to work, shop and live”
1.2The St Helier, Wrythe & Wandle Valley Local Committee has been allocated £354k of Public Realm funding to invest in area improvements over two financial years (2008/09 & 2009/10). With a further £88,000 earmarked for 2010/11.
1.3Public Realm is defined to include shared, open civic spaces not including highway improvements. It does not include any areas inside buildings that would be considered to be public space.
2. Issues
Progress to date 2.1 The attached schedule at Appendix A details the current position for each of the projects previously agreed by the local committee. These total £275k.
2.2As indicated in Appendix A sections 1, 2 and 3 most of the projects have been completed or works ordered and contractors appointed. It has also been necessary to coordinate projects on a Borough wide basis with public realm projects for the five other Local Committees.
2.3The Committee is asked to consider the proposals in section 4 of Appendix A for a further 4 new projects. If agreed and in order for the projects to proceed, the Committee will also need to approve the release of funds totalling £50,000 from the remaining public realm budget for 2009/10 which is currently £79,000.
2.4Details of schemes yet to be agreed are provided in section 5 of Appendix A. The budgeted costs for these have yet to be confirmed.
2.5A further verbal update on progress will be presented at the meeting
Financial implications
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow St. Helier, The Wrythe and Wandle Valley Local Committee at Sutton and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.