Page 29 Agenda Item 8
ST HELIER, THE WRYTHE AND WANDLE VALLEY LOCAL COMMITTEE – 30 JUNE 2009
Brief Report for Information only This briefing is to report on the progress on the replacement of the London Road Bridge at Hackbridge.
Network Rail HV Cables Two HV cables in concrete troughs pass over the area in which the South Abutment of the new bridge is to be built. It was established that these cables would have to be temporarily diverted to allow the abutment to be constructed. They would then be moved back into their permanent position when the existing bridge had been demolished. The initial condition imposed by Network Rail (NR) was that they could only remain in their temporary position for 6 months. A site meeting was held with NR representatives in early June 2008 at which it was stated that it would be impossible to construct the new bridge and demolish the old within the 6 month time frame. A longer period would be required. After discussion, the NR representatives agreed that they were looking for certainty of period rather than a specific duration. After preparing a draft constriction programme, NR was advised that the temporary diversion would need to be in place for 15 months. Some progress has been achieved to remove the impasse with NR and it now possible that the HV cable diversion will be in place by the end of July. This progress must be treated with a great deal of caution, as such previous agreements have fallen, but the involvement of senior Network Rail staff gives some measure of optimism.
Network Rail Signal and Telecom Cables Several signal and telecom cables in concrete troughing also pass over the area on which the South Abutment of the new bridge is to be built. It was that these cables could remain in place and be protected while the abutment is constructed around them. It has been established that they were aware of and accepted the plan to put the signal cables through the South Abutment of the new bridge, subject to strict conditions on cable protection during the construction period. It is understood that NR are currently detailing the exact arrangements for these cables. However, there are also a number of telecom cables in the same vicinity, which are the responsibility of a different team and a recent meeting with them has led to some measure of confidence.
Network Rail Form B There are a set of procedures that have to be followed to gain approval from NR to build over or near to their railway. The first is the Form A, which is an ‘in principal’ agreement to the design. This then has to be followed by an independent Check of the Design and submission for a Form B approval. The design check has now been completed and has been submitted to NR for their approval. NR advises that it would take 6 weeks to complete the approval process.
Land Issues The Land Agreement has had to be revised for the following reasons: The revised bridge is slightly wider so the abutments require a small area of additional land. The wider bridge means that a wider flying easement is required The working space licence agreement was time limited. The agreement needs to be revised to relate to the new contract period. Agenda Item 8 Page 30
A new easement agreement is to be negotiated for the possible use of a footbridge over the line adjacent to the station. A meeting was held with NR property surveyors who were very constructive and it is envisaged that all these issues can be resolved by agreement.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
hackbridge bridge3Report | 58 KB | DownloadRead as text |
Follow St. Helier, The Wrythe and Wandle Valley Local Committee at Sutton and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Mar 2022 | Minutes of the previous meetingRESOLVED : that the minutes of the meeting held on 13 January 2022 be agreed as an accurate record. | Agreed | Open |
| 13 Jan 2022 | Minutes of the previous meetingRESOLVED : that the minutes of the meeting held on 21 October 2021 be agreed as an accurate record. | Agreed | Open |
| 13 Jan 2022 | Petition Regarding Measures to Reduce Antisocial Behaviour in the Rose Hill AreaTo note the petition. 2. To agree that Sutton Council’s Community Safety Team will review CCTV coverage in the area a... | Noted | Open |
| 21 Oct 2021 | Minutes of the previous meetingRESOLVED : that the minutes of the meeting held on 17 June 2021 be agreed as an accurate record. | Agreed | Open |
| 21 Oct 2021 | Community Investment ProgrammeIt was agreed that an update on outcomes would be provided at a future meeting of the committee. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.