(i) That the following amended terms of reference be agreed for the Internal Audit review of the Sutton Town Centre redevelopment: To consider all aspects of the Sutton Town Centre Redevelopment project from its approval and planning through to its implementation and completion, including consideration of the following: · Delivery of the project vision that was approved by Members · Details of the areas of consultation that were undertaken · Assessment of the effectiveness of project coordination and oversight in managing operational and financial risks · Compliance with the Council’s own policies and procedures for procurement, project management, contracting and design · The mechanisms put in place for monitoring progress and signing off project deliverables by those involved with the project. (ii) That a progress report be submitted to the next meeting of this Committee.
Word for word from the decision Sutton published for this meeting.Source: moderngov.sutton.gov.uk
Audit Committee - 16th December 2010 Report of the Chief Internal Auditor INTERNAL AUDIT – TERMS OF REFERENCE: REVIEW OF SUTTON TOWN CENTRE REDEVELOPMENT Ward Location: Not Applicable Author(s) and Contact Phone Number(s): David Dobbs - Chief Internal Auditor (020 8770 5260) Area Served: Borough wide Executive Councillor: N/A
Report For Information only
Summary This report comprises the proposed terms of reference for the Internal Audit review of the Town Centre Redevelopment. Members of the Audit Committee are asked to consider and comment on the draft terms of reference. 1. Background 1.1 A number of concerns have been raised in relation to the Sutton Town Centre redevelopment project. These include, but are not necessarily limited to the following: x Injuries sustained by individuals when using the new town centre furniture and an attendant increase in claims against the Council x Health and safety issues concerning sighting of obstacles, access for emergency vehicles and electricity supply x Perceived failure of the project to deliver the initial vision that was promulgated by the Council x Concerns regarding project governance from consultation through design to implementation x Perceived quality issues resulting from the use of sub-contractors x Potential financial risks arising from an additional claim for payment made by the main contractor, totalling c£800k x Reputational risks resulting from adverse local press coverage.
1.2Members have asked that a review be undertaken that addresses the issues listed above and it has been agreed with the Strategic Director of Resources and the Strategic Director of Environment and Leisure that this review should be carried out by Internal Audit. Agenda Item 9 Page 56
2. Issues Objectives of the Review 2.1 The overall objective of the review is a full, independent evaluation of project governance which will also include the routine elements of a post project evaluation. 2.2 The review will consider all aspects of the project from its approval and planning through to its implementation and completion, including consideration of the following:
x Delivery of the project vision that was approved by Members
x Assessment of the effectiveness of project management in managing operational and financial risks
x Compliance with the Council’s own policies and procedures for project management, contracting and design
x The mechanisms put in place for monitoring progress and signing off project deliverables by the Council
Timescales and Deliverables 2.3 The review will commence immediately; a draft report will be produced and circulated to interested parties in the first half of 2011. Sources of Evidence 2.4 The majority of evidence is expected to be obtained from in-house records of scheme management including details of appointments, project initiation, feasibility, design and tender, contracts and completion paperwork. 2.5 Council officers who have knowledge or involvement with the project will be interviewed.
2.6Where relevant it may be also be necessary to request information or discuss pertinent issues with the external parties contracted by the Council. Resources 2.7 The majority of the fieldwork will be undertaken by Philip Evenden (Senior Auditor). He will be assisted by Linda Wood (Head of Programme and Project Management). 2.8 The Chief Internal Auditor will have overall responsibility for supervision and delivery. 3. Financial Implications 3.1 The officer time required for completing this review will be absorbed within current budgeted resources. 4. Influence of the Council’s Core Values 4.1 The work of Internal Audit provides a valuable contribution to the provision of high quality, cost effective services. 5. Equality Impact Assessment 5.1 There are no direct equality implications from this report. Page 57 Agenda Item 9
6. Background Papers 6.1 None. Page 58
This page is intentionally left blank
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Treasury Management Quarterly reportRESOLVED that : The treasury management activity undertaken during the first nine months of the year was noted It be ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.