Cheam North and Worcester Park Local Committee noted this item on Thursday 20 January 2011. Below is the council's own wording, with the papers it was decided on.
( i ) To request that consultation on the zebra crossing for Kingston Avenue be done first before the committee commits funds as there may be some reason why it could not go ahead. (ii) That two benches and two litter bins be purchased from public realm funds, for Fairlands Park, at a cost of up to £2,200. (iii) To note the possible request for a very large sum of money towards a flood alleviation scheme and to request all relevant information be submitted to a future meeting of this committee for consideration. (iv) That members would reconsider the previously considered schemes put on hold and resubmit any further information on them. (v) To thank Simon Densey for his report and all the work he is doing in the local area.
Word for word from the decision Sutton published for this meeting.Source: moderngov.sutton.gov.uk
Report to Cheam North and Worcester Park Local Committee
APPENDIX A No Location Description Page 5 Service/Organisatio n delivering project Budget released Final cost Eligible for Cost code/ Comments Agenda Item 5 £0=N/K Public project Realm referenc e Completed Schemes 1 Fairlands Park - Nonsuch Relocate and install new Parks 60,000 65,531 Y M200 Original estimate £60,000, overspend due to amount of wet playground pour that had to be removed from old playground. 2 Cuddington Rec - Nonsuch New fencing at all three main Parks Service 28,000 28,000 Y M201 Committee agreed 18.12.08 to spend an additional £8k to entrances complete this scheme. Work completed August 2009 3 Carlton Crescent - Nonsuch Upgrade lighting to the Environmental 3,000 3,000 Y M217 Complete, cost to be finalised Sept 10 bridleway Improvement/Commu nity Safety 4 Sutton Common Park - Stonecot Improved signage at entrances Parks 2,000 1,402 Y M202 New sign installed.
5 Sutton Common Park - Stonecot Flower tree and shrub planting Parks 5,000 5,464 Y M203 Tree planting cost of £1370; bulbs £2000; shrubs £1794; labour £300. 9 Ridge Road Library - Stonecot Provision of plants for FORR Environmental 1,000 703 Y M207 Complete Library planting day Improvement 10 Kimpton - Stonecot SNT Signage (Neighbourhood Environmental 300 279 Y M208 Complete Watch Signs) Improvement/Commu nity Safety 12 Central Road - Worcester Park New Xmas Lights Central Environmental 18,000 18,153 Y M209 Complete Road, Worcester Park Improvement
13 Dorchester Rec - Worcester Park Replace junior climbing frame Parks 25000 19,521 Y M210 Completed under budget. and under-surface 19 Longfellow Road - Worcester Park Rosa Smith playground, Parks 28,000 26,000 Y M212 Complete. Final account to be checked 12.2.10 resurface, 2 no. ball court ends, fencing repair, 2 no. seats, bump stop on gate to prevent noise 23 Hamilton Ave - Stonecot Repaint Railings Highways 0 0 Y N/A Completed by Community Pay Back
37 Stonecot - Hamilton Ave Provision of Flood Defences Estates and 0 0 N N/A New scheme agreed with EA to increase flood storage valuation/Parks capacity within the park. Scheme constructed autumn 2009. Final channel works to be completed late 2010 for hand over Feb 2011.
33 Cuddington Rec - Nonsuch Replace tennis court fencing Parks 0 0 Y N/A Completed by Parks Service from Revenue budget.
6 Sutton Common Park - Stonecot Contribution towards Parks 25,000 25,000 Y M204 Complete apart from minor finishing 12.2.10. Agreed to playground / climbing frame complete at same time as playground refurbishment being funded by Playbuilder scheme. Public Realm contribution funded new fence, installation costs and infant swings as these items could not be funded from Playbuilder. 11 Stonecot - All Ward Improved alleyway lighting Environmental 20,000 20,000 Y M216 Complete. Final cost to be confirmed 12.2.10 appearance and planting Improvement/Commu nity Safety 42 Stonecot - Sutton Common Park Provision of new park fence Parks 19,000 19,000 M215 Complete. Final cost to be confirmed 12.2.10. Cost expected to be £42,500. Safer Sutton Partnership has agreed to fund new gates at the Sutton Common Road at a cost of £4,500 and half the cost of the park fences. Their total contribution will be £23,500. Committee agreed on 18.12.08 to fund £25,000 half the original estimated costs of the fences, but will now only need to fund £19,000.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Cheam North and Worcester Park Local Committee at Sutton and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.