Agreement of the amendments to the Inter Authority Agreement (IAA) relating to the South London Waste Partnership (SLWP)
AgreedCommittee1 paper
Environment and Neighbourhood Committee agreed this item on Thursday 13 June 2013. Below is the council's own wording, with the papers it was decided on.
( i ) To agree the changes to the Inter Authority Agreement. (ii) To note the additional benefits being provided by the waste partnership. (iii) To refer this report to Strategy and Resources Committee for agreement to allocate £150,000 of capital funding as Sutton’s contribution towards additional benefits.
Word for word from the decision Sutton published for this meeting.Source: moderngov.sutton.gov.uk
As part of the South London Waste Partnership (SLWP) Sutton and its partners (Croydon, Merton & Kingston) are bound by an Inter Authority Agreement (IAA) which was originally agreed in 2009. This existing IAA focuses on the procurement of contracts but does not cover matters relating to contract management and service costs resulting from the contracts. This report summarises the proposed amendments to the existing IAA to address this.
Recommendations
I recommend the Environment & Neighbourhood¶V Committee to:
a) Agree the changes to the Inter Authority Agreement.
b) Note the additional benefits being provided by the waste partnership.
c) Refer this report to Strategy & Resources Committee for agreement to allocate £150,000 of capital funding as SXWWRQ¶VFRQWULEXWLRQWRZDUGVWKHDGGLWLRQDOEHQHILWV
Background Documents and Previous Decisions
Previous IAA documents - held by the Head of Waste Management & Fleet Services Agenda Item 17 Page 108
Mary Morrissey
Signed:
Strategic Director ± Environment & Neighbourhoods
Date: 31 May 2013 Page 109 Agenda Item 17
1. Background 1.1 The original Inter-Authority Agreement (IAA1) established the contractual arrangements between the four boroughs. It identified RB Kingston as the ³Lead Authority´ with respect to the procurement of the first set of joint waste management contracts together with approving the recruitment and commissioning of resources required to support the Partnership. It also set out the agreed method of apportioning costs between the boroughs.
1.2IAA1 also formalised the governance arrangements for the Partnership; establishing the Joint Waste Committee, setting out the powers delegated to the Committee and confirming the authority delegated to officers. 1.3 In 2011 a revised Inter-Authority Agreement (IAA2) was agreed to build upon the first agreement and address issues arising from the procurement of the residual waste treatment contract. This confirmed LB Croydon as the Lead Authority for the purposes of that procurement. 1.4 The original IAA established the principle that it should be reviewed at least annually. A review was carried out by officers in advance of the award of the residual waste treatment contract in November 2012 and it was agreed that in its current form the IAA2 was appropriate for the purpose of contract award. 1.5 Further amendments to the IAA2 agreement are now required in order to put in place mechanisms by which the Partnership can strengthen its contract management arrangements. 2. Issues
2.1The Management Group of the SLWP identified a number of matters that required resolution in order to satisfy all authorities that appropriate arrangements are in place to ensure the fair and effective management of the residual waste treatment contract. A summary of these issues and treatment is illustrated in the table below.
Issue Resolution
The method for calculating the These costs will continue to be management costs of the residual waste shared equally. treatment contract.
The principle for the apportionment of Each Authority shall bear its own service costs. transport and service costs for the Agenda Item 17 Page 110
tonnes it has treated, with the exception of RBK Haulage which is dealt with below.
+RZWKH³*XDUDQWHHG0LQLPXP There is a mechanism by which 7RQQDJH´HOHPHQWZRXOGEHPDQDJHG those partners which do not achieve their minimum tonnage compensate the other boroughs in the event that the Partnership does not achieve its contracted minimum tonnage
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.