Resolved
To incur capital expenditure for the planned highway and pavement maintenance works identified in the 2012-16 Capital Programme which was to be undertaken during 2013/14.
Environment and Neighbourhood Committee decided this item on Thursday 13 June 2013. Below is the council's own wording, with the papers it was decided on.
Resolved
To incur capital expenditure for the planned highway and pavement maintenance works identified in the 2012-16 Capital Programme which was to be undertaken during 2013/14.
Page 35 Agenda Item 9
Report to: Environment & Neighbourhoods Committee
Date: 13 June 2013
Report of: Interim Executive Head of Planning and Transportation
Ward Location: Not Applicable Author(s) and Contact Phone Number(s): Gerry McLaughlin, Deputy Head of Highways. (020) 8770 6391 Area Served: Borough Wide Chair of the Committee: Councillor Jill Whitehead
Report title: Release of Capital Funding for Planned Highways Maintenance in 2013/14
Summary The Council has a statutory duty under S41 of the Highways Act 1980 to maintain the highway in a safe condition for all users. The Planned Highway Maintenance Works Programme is drawn up to address the more important maintenance requirements of roads in the Borough. By undertaking this work we are meeting our statutory responsibility for road maintenance and investing wisely for the future by minimising ongoing maintenance costs and the potential liability for insurance claims.
Recommendations That the Environment & Neighbourhoods Committee agrees to incur capital expenditure for the planned Highway and Pavement Maintenance Works identified in the 2012-16 Capital Programme which is to be undertaken during 2013/14.
Background Documents and Previous Decisions Approved Capital Programme for 2012-16 (Council Minute 210/12). Agenda Item 9 Page 36
Signed:
Strategic Director Page 37 Agenda Item 9
Date: 31st May 201
1. Background 1.1 A provisional planned highway maintenance programme is drawn up each year EDVHGRQ+LJKZD\V,QVSHFWRUV¶ILQGLQJVDQGWKHVXUYH\ZRUNFDUULHGRXWE\ Planned Maintenance engineers. All roads on the provisional list are prioritised using an agreed weighting assessment, which takes account of the overall condition, usage, location and level of interest from Councillors and members of the public. Within this criterion, principal roads, bus routes and cycleways receive a higher priority, as do footways in shopping areas and those close to hospitals, schools and care homes.
1.2,QUHFHQW\HDUVVXIILFLHQWFDSLWDOIXQGLQJWRFRPSOHWHHDFK\HDU¶VVFKHPHVKDV not been available and this has led to a backlog of roads requiring attention. 1.3 The provisional list of roads is sent to all Public Utilities for consultation as required under the New Roads and Street Works Act (NRSWA) 1991. This allows the Utilities to give notice of their future planned works and gives us the opportunity to delay any schemes until after their work has been completed. 1.4 The works programme is then finalised for approval and schemes progress, subject to the required capital and revenue funding being available.
1.5Resident's are informed on pending works through an advance letter drop in the weeks leading up to the planned maintenance taking place, and the term contractor also affixes notices to lamp columns in the days preceding the works taking place.
1.6The Council is now required to prepare a valuation of the highways assets and report this annually to comply with Whole of Government Accounts. The 'HSUHFLDWHG5HSODFHPHQW&RVW '5& RI6XWWRQ¶VKLJKZD\DVVHWVZDVYDOXHGDW PLOOLRQLQWKHERURXJK¶VVXEPLVVLRQIRU,WLVLPSRUWDQWWKHUHIRUH that the service has a robust revenue funded reactive maintenance programme in partnership with the capital funded planned maintenance programme.
2. Issues 2.1 The Mori Survey 2011 shows that progress has been made in addressing FXVWRPHUV¶FRQFHUQV Pavement maintenance satisfaction is up 12% to 62%. Road maintenance satisfaction is also up 2% to 56% However these satisfaction rates are relatively low compared with other Council services and dissatisfaction levels are significant: 22% of customers are dissatisfied with pavements Agenda Item 9 Page 38
26% of customers are dissatisfied with roads There is also variation in satisfaction across the borough 3. Options Considered Glossary of Planned Maintenance Methods:-
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
EN Planned Highways Maintenance Report 2013-14 (2)Report | 65 KB | DownloadRead as text |
PDF |
EN Planned Highways Maintenance Report 2013-14 (2) APPENDICES A and BReport | 23 KB | Download |
Follow Environment and Neighbourhood Committee at Sutton and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 1 Oct 2020 | Minutes of the previous meetingthat the minutes of the meeting held on 11 March 2020 be agreed as an accurate record. | Agreed | Open |
| 1 Oct 2020 | Any urgent businessthat 1. the petitions received regarding street cleansing and refuse collection in Wandle Valley ward, specifically t... | Refused | Open |
| 1 Oct 2020 | Petitions Regarding the Safer, Active, Greener Streets Schemethat 1. The petitions received regarding the streetspace schemes be noted 2. The following be noted: · the rationale ... | Noted | Open |
| 1 Oct 2020 | Authority to Consult on the Draft Sustainable Transport Strategy Supplementary Planning DocumentRESOLVED : 1. that the Draft Sustainable Transport Strategy 2020-2025 (STS) for public consultation be agreed. | Agreed | Open |
| 1 Oct 2020 | Environment Strategy 2020 Refresh and Climate Emergency Response PlanRESOLVED : that 1. the updated Environment Strategy be agreed 2. the Climate Emergency Response Plan be agreed 3. It ... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.