SUTTON STATION GATEWAY SCHEME - Project Governance Arrangements

Approved Committee 1 paper

Environment and Neighbourhood Committee approved this item on Thursday 3 October 2013. Below is the council's own wording, with the papers it was decided on.

Item930

Resolved

( i ) To approve the proposed programme and governance arrangements now submitted and outlined above. (ii) To approve the following membership of the Sutton Station Gateway Project Board:- Project Board Chair - Councillor Simon Wales: Sutton West ward Committee Chairs - Councillor Jill Whitehead: Chair, Environment and Neighbourhood Committee Councillor Marlene Heron: Chair, Sutton Local Committee Councillor Tony Shields: Chair of Sutton South, Cheam and Belmont Local Committee Ward Councillors - Councillor Graham Tope: Sutton Central Councillor Richard Clifton: Sutton South Project Sponsor - Eleanor Purser Executive Head of Economic Development, Planning and Sustainability Programme Manager - Mandy Cherrington: Head of Economic Renewal and Regeneration Project Manager - Peter Boddy Partner Agencies - Transport for London: Peter Blaine Network Rail - Paul Donald Southern Railway - Mark Epsom London Assembly - Steve O’Connell AM (iii) That authority be delegated to the Strategic Director – Environment and Neighbourhoods, in consultation with the Sutton Station Gateway Programme Board, the Chairs of this Committee and relevant local committees, and ward councillors, to progress the development and delivery of the Sutton Station Gateway scheme. (iv) That authority ... view the full minutes text for item 930.
Word for word from the decision Sutton published for this meeting. Source: moderngov.sutton.gov.uk

Follow this further

Built from Sutton's papers

What the report saysPro

Report to Environment and Neighbourhood Committee

Background

1.1Sutton station is the main gateway into Sutton town centre for people arriving by train and it also sits at the entrance to the town centre by road from the south. It is therefore an important focal point for the town centre and the first impression that many visitors get of Sutton. The Council has identified a need to undertake a package of improvements to create a gateway to the town centre, enhance accessibility to the station and the town centre, improve public realm and transport mode interchange and address crime and anti- social behaviour issues.

1.2Sutton station attracts almost six million passenger movements per year. It was recently identified by TfL as one of the 18 stations in London suffering from significant congestion problems. This is largely due to the limited capacity of the ticket barriers at the entrance hall at the front of the station. 1.3 7KH&RXQFLOVXEPLWWHGDµPDMRUVFKHPHELG¶IRUD*DWHZD\,PSURYHPHQW Scheme at Sutton station to Transport for London (TfL) in September 2012. TfL announced in December 2012 that the bid was successful and the Council has been awarded an indicative allocation of £740,000. This was reported to Environment and Neighbourhoods Committee on the 17th January 2013 as part of the annual Local Implementation Plan settlement report, and subsequently to Sutton and Sutton South, Cheam and Belmont Local Committees in March 2013.

2. Programme Management and Governance

2.1The London Borough of Sutton has established formal project management processes to help deliver projects on time, to budget and to a high quality.

2.2All projects and programmes require a governance structure that clearly defines the roles and responsibilities of all involved and ensure clarity about where decisions will be taken.

2.3The key roles in the Sutton Station Gateway Scheme are as follows;

(i) The Project Sponsor is accountable to the Strategic Director of Environment and Neighbourhoods and to the Programme Board for providing direction and leadership to the project.

(ii) The Project Manager provides oversight to the project ensuring its work streams, funders and stakeholders are coordinated and ensuring the duties of the officer working group are delivered on time and to budget.

(iii) The Project Board is accountable for the overall success of the project and to provide direction, input and challenge..

(iv) The Chair of the Project Board acts as a champion, giving direction and drives the project forward. Agenda Item 6 Page 12

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Sutton Station EN committee 130905 FINALReport 303 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 18 attended
JW
Councillor Jill WhiteheadChair, present
GT
Councillor Graham TopeVice-Chair, present
EA
Councillor Eric AllenCommittee Member, present
SF
Councillor Stephen FenwickCommittee Member, present
CH
Councillor Colin HallCommittee Member, present
LH
Councillor Lester HollowayCommittee Member, present
MJ
Councillor Miguel JavelotCommittee Member, present
JM
Councillor Joyce MelicanCommittee Member, present
HP
Councillor Hamish PollockCommittee Member, present
TS
Councillor Tony ShieldsCommittee Member, present
RD
Councillor Ruth DombeyEx Officio, absent
MM
Mary MorrisseyOfficer, expected

All 18 on the meeting page

On this subject at Sutton

Search all
  1. SUTTON STATION GATEWAY SCHEME - Project Governance ArrangementsThis decision
  2. APPLICATION NO.DM2019/00434 -12 Station Road Belmont Sutton SM2 6BHAgreed
  3. Sutton station gateway - updateNoted
  4. Units 2 and 3 sutton station and 3 railway bridge, high street, sutton - application no. b2014/70755/advDecided
  5. Sutton station gateway - updateNoted
  6. Bus shelter outside entrance to sutton station, high street, sutton - application no. b2014/70396/advDecided

More from Sutton Environment and Neighbourhood Committee

All decisions
MeetingDecisionOutcome
1 Oct 2020 Minutes of the previous meetingthat the minutes of the meeting held on 11 March 2020 be agreed as an accurate record. Agreed Open
1 Oct 2020 Any urgent businessthat 1. the petitions received regarding street cleansing and refuse collection in Wandle Valley ward, specifically t... Refused Open
1 Oct 2020 Petitions Regarding the Safer, Active, Greener Streets Schemethat 1. The petitions received regarding the streetspace schemes be noted 2. The following be noted: · the rationale ... Noted Open
1 Oct 2020 Authority to Consult on the Draft Sustainable Transport Strategy Supplementary Planning DocumentRESOLVED : 1. that the Draft Sustainable Transport Strategy 2020-2025 (STS) for public consultation be agreed. Agreed Open
1 Oct 2020 Environment Strategy 2020 Refresh and Climate Emergency Response PlanRESOLVED : that 1. the updated Environment Strategy be agreed 2. the Climate Emergency Response Plan be agreed 3. It ... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies