Update Report for Noting Report to: Sutton Local Committee
Date : 24 November 2014
Sutton Station Gateway Scheme This report updates members on the progress of the scheme which is currently in the implementation stage
Ward Location: Author(s) and Contact Phone Number(s): Sutton Central Brian Bainbridge Project Manager – (020) 8870 5913
Area Served: Chair of the Committee: Sutton Central Councillor Marlene Heron Sutton North Sutton West
Works for Sutton Station Gateway Scheme
Scheme objectives
1. To improve the ‘arrival experience’ for visitors to Sutton arriving at the station. 2. To improve the ‘gateway to Sutton’ from the south on Brighton Road. 3. To improve station access and accessibility, thus supporting and encouraging rail use and inward/outward commuting. 4. Support the local economy through better access to Sutton town centre businesses, and an improved public realm and streetscape. 5. To make the gateway to Sutton town centre a more attractive place for inward investors, boosting jobs and growth, supporting regeneration and new development. 6. Encouraging greater use of sustainable transport, building on the Smarter Travel Sutton project. 7. To reduce risk of road closures. 8. To support wider and longer term Council policies and proposals for Sutton town centre, and the Business Improvement District and ‘Opportunity Sutton’ initiative. Economic benefits to the town centre, supporting jobs and growth. 9. Discourage crime and anti-social behaviour around the station.
Progress and Current Position:
EM Highways commenced work on site on 15.09.2014 having been appointed the contractor to deliver on behalf of LB Sutton. The existing footways have been taken-up on both sides of Brighton Road, south of the station working south to the junction with Cedar Road. Agenda Item 6 Page 12 On the west side of Brighton Road, new kerbs have been laid and construction of the new footway is substantially complete from the railway bridge south to Cedar Road. On the east side of Brighton Road, new kerbs and footways have been laid across the bridge on the west side of Brighton Road, and south to Cedar Road. The concrete base for the ‘cctv’ mast to be re-located in the Mulgrave Road junction traffic island has been constructed, and a new mast installed. Network Rail completed significant improvements to the station building during September 2014 and the second entrance is now open. Southern Railway have upgraded and increased cycle storage at the station from 80 cycles to 144 cycles. Planning consent has been received for the Civic Clock and this will be installed opposite the station in Mulgrave Road. Consultation is ongoing with shop keepers in the vicinity of the station to improve the appearance of shop fronts.
Planned Work, (Next Steps):
During November work on kerbs/footways between the railway bridge and Cedar Road junction is planned to be completed. During the ‘Moratorium Period’, (24.11.2014 – 17.12.2014), prior to Christmas no work is planned along High Street or Brighton Road. However work in Mulgrave Road, and ‘The Quadrant’ is planned to be progressed, but this should not cause significant disruption of traffic on High Street or Brighton Road. Work on the shop front improvements and Civic Clock is planned for early 2015. Legible London signage associated with the scheme is to be installed during early 2015. Legible London is an easy-to-use signage system that presents information in a range of ways, including maps and directional information and this will help people navigate their way around Sutton.
Key incidents:
A power failure at Sutton Station was reported on 14.10.2014 which affected electrical services and lighting within the station buildings. The faults which apparently occurred in the external substation were not attributed to the ongoing EM work outside the station.
Communications
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
20141119: Sutton Station Gateway, Sutton Local Committe Report v2 (1) (1)Report | 112 KB | DownloadRead as text |
Follow Sutton Local Committee at Sutton and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Jul 2026 | Minutes of the previous meetingthat the minutes of the meeting held on 12 February be agreed as an accurate record. | Agreed | Open |
| 12 Feb 2026 | Minutes of the previous meetingRESOLVED : that the minutes of the meeting held on 6 November 2025 be agreed as an accurate record. | Agreed | Open |
| 6 Nov 2025 | Minutes of the previous meetingRESOLVED : that the minutes of the meeting held on 19 June 2025 be agreed as an accurate record. | Agreed | Open |
| 6 Nov 2025 | Sutton Housing Partnership updateIt was agreed that this item would be deferred to a future meeting of the committee. | Agreed | Open |
| 19 Jun 2025 | Minutes of the previous meetingthat the minutes of the meeting held on 8 May 2025 be agreed as an accurate record. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.