Resolved 1. That progress against priorities be noted. 2. That the outturn o f a net underspend of £1.577m against an agreed revenue budget of £155.181m be noted. 3. That the proposed revenue budget carry forwards and reserve transfers set out in Appendices E and F of the report be approved 4. That the capital budget carry forward of £9.7m in to the 2014/15 Capital Programme and other capital programme adjustments totalling £0.3m ( para 2.8 and Appendix G of the report) be approved. 5. That authority to approve the addition of a new scheme to the capital programme to assist with the purchase of a property to facilitate adoption proceedings be delegated to the Strategic Director – Resources, subject to him being satisfied that the financial evaluation of the proposal is robust and that any necessary contractual or other arrangements to protect the Council’s position are in place ( para 6.5) be delegated to the Strategic Director – Resources 6. That the release of £419k from the Business Change reserve to fund Smarter Council projects in 2014/15 ( para 4.4 and Appendix I of the report) be agreed
Word for word from the decision Sutton published for this meeting.Source: moderngov.sutton.gov.uk
Report of: Strategic Director - Resources and Interim Executive Head of Policy and Customer Services
Ward Location: Not applicable Author(s) and Contact Phone Number(s): Rebecca Escott-New, Customer Insight and Performance Manager (020) 8770 6880
Phil Butlin, Executive Head of Finance and Procurement (020) 8770 4949
Area Served: Borough wide Chair of the Committee: Cllr Ruth Dombey
Lead Member for Resources: Cllr Simon Wales
Lead Member for Smarter Council: Cllr Colin Hall
Report title: Outturn performance and finance report 2013/14
Summary This report summarises the performance of the Council in the last quarter (January - March 2014) and over the last year against the key council-wide priorities and the Directorate commissioning intentions set out in the 2013/14 commissioning and financial plans. In the context of ongoing austerity, the Council’s overall performance is good, with performance against key targets being maintained or improved since the last year.
The report also provides details on financial performance and actions taken, or planned, to address areas of underperformance and significant budget variations.
Key achievements over the past year include the Department for Education (DfE) lifting its Notice to Improve from the Council’s Children’s Services, maintaining the level of resident satisfaction with the local area, reducing crime and the fear of crime in the borough, promoting economic development in the borough, reducing youth unemployment, supporting residents affected by the welfare reforms, ensuring vulnerable adults and children are safe and increasing resident satisfaction with key universal services such as street cleansing.
Appendix A provides a high level balanced score card summary of council-wide performance, including progress against our key corporate plan performance indicators.
The provisional revenue outturn for the year is for a net underspend of £1.6m (1% of the net budget) after taking account transfers to reserves. If the recommended carry forwards (as shown in Appendix E) of £1.6m are agreed this will result in an underspend of £10k. Agenda Item 4 Page 10
Appendix A is the overview of performance using our our balanced scorecard approach, Appendix B is the he corporate risk register and Appendix Appendix C is the residents’ performance perfor report. Appendix D sets out the major revenue budget variations. Appendix E shows recommended budget carry forwards into 2014/15. Appendix F summarises the recommended ended transfers to reserves, Appendix G recommends capital budget budg adjustments between 2013/14 and 2014/15, 2014/15 Appendix H is the latest pan-London London benchmarking performance data and Appendix I details the Smarter Council activity in 2014/15 recommended to be funded from the Business Change Reserve. Reserve
Recommendations The Strategy and Resources Committee is recommended to:
1. Note progress against priorities. 2. Note the outturn of a net underspend of £1.577m against an agreed revenue budget of £155.181m.
3. Approve the proposed revenue budget carry forwards and d reserve transfers set out in Appendices E and F.
4. Approve the capitall budget carry forward of £9.7m £9.7m in to the 2014/15 2 Capital Programme and other capital programme adjustments totalling £0.3m £ (para 2.8 and Appendix G).
5. Agree to delegate to the Strategic Director – Resources authority to approve the addition of a new scheme to the capital programme to assist with the purchase of a property to facilitate adoption proceedings, proceedings, subject to him being satisfied satisfi that the financial evaluation of the proposal is robust and that any necessary contractual or other arrangements to protect the Council’s position are in place (para 6.5).
6. Agree the release of £419k from the Business Change reserve to fund Smarter Council projects in 2014/15 (para 4.4 and Appendix I). I
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.