Electric Vehicle Charging Point (EVCP) Procurement
DecidedCommittee1 paper
AI summarySutton's Strategy and Resources Committee has delegated the award of a 15 year electric vehicle charging point concession contract, estimated at £40 million over its term, to the Strategic Director of Resources.
Written from the decision and the officer reportPDF Pro
OutcomeDecidedTo Strategic Director of Resources after procurement
Money£40 millionEstimated 15 year contract value, inclusive of VAT
What happens nextProcurement processOfficers to report award recommendation to Strategic Director
Who it affectsEV charging infrastructureAround 180 chargers on circa 40 council sites
What was decided
The committee delegated the award of the EVCP contract to the Strategic Director of Resources, in consultation with the Lead Member for Resources and the Chair of the Environment and Sustainable Transport Committee.
The contract will be a 15 year concession for installation and maintenance of around 180 new fast, rapid and ultra rapid EV chargers, awarded in return for a revenue share. Report P14
The procurement will follow a Competitive Flexible procedure under the Procurement Act 2023. Report P14
Why
The project is expected to generate a long term revenue stream to help fund the council's statutory services, while expanding EV charging options for residents and visitors. Report P6
The market engagement strategy is designed to maximise competition and secure the best commercial outcome, and all bidders must pass the council's financial vetting procedures. Report P7
The contract is structured as a services concession, with the supplier exposed to real operating risk from shifts in user patterns, electricity price spikes, and unanticipated ground conditions. Report P16
What happens next
Officers will report to the Strategic Director of Resources to recommend award of the concession contract once the procurement process is complete. Report P18
After award, a contract award notice will be published to start an 8 working day standstill period, followed by a contract detail notice within 30 days of entering the contract. Report P21
The £150k MTFP saving for 2026/27 is unlikely to be fully realised this year and full achievement is now expected in 2027/28. Report P8, P11
The money
£150k MTFP saving for 2026/27 from EV charging revenue, expected to shift to 2027/28 Report P8, P11
£40 million (inclusive of VAT) Estimated maximum contract value for the 15 year term Report P15
Options considered
Chosen: Delegate contract award to the Strategic Director of Resources. Allows prompt approval upon completion of procurement, enabling immediate commencement of the phased rollout and expediting revenue generation. Report P12
Implications
Financial: Financial risk is allocated to the supplier to reflect the contract's concessionary nature. Report P17
Financial: Full realisation of the £150k MTFP saving is expected to shift from 2026/27 to 2027/28. Report P11
Climate: Overall climate impact is anticipated to be positive, as electric cars are more sustainable and reduce CO2 emissions. Report P3
Equalities: An Equalities Impact Assessment has been drafted and will be finalised during procurement, with bidders required to factor in accessibility. Report P1, P2
Legal: Full implications of the Procurement Act 2023 apply, as the contract value is above the relevant threshold. Report P15
Legal: A bespoke contract is required covering electricity supply legislation, access to council assets, data protection, and service standards. Report P17
Risk: Around 40 off highway sites may have current leaseholders, so licences or lease variations may be needed before signing. Report P22
Who and where
Residents and visitors who will have access to expanded EV charging options Report P6
Current leaseholders of council off highway sites that may host chargers Report P22
Local businesses able to use the EV charge points Report P16
Timeline
20/05/2026: Equalities and Climate Impact Assessments consulted by Director for Assets and Capital Delivery Report P31, P32
29/05/2026: Commercial and Procurement consulted by Head of Commercial and Procurement Report P30
01/06/2026: Legal consulted by Head of Law, South London Legal Partnership Report P29
02/06/2026: Finance consulted by Director of Finance Report P28
2026/27: Original MTFP target year for the £150k saving Report P8
2027/28: Expected year for full realisation of the £150k saving Report P11
8 working days: Standstill period following publication of the contract award notice Report P21
Within 30 days of entering the contract: Contract detail notice to be published Report P21
Plain English for the jargon
EVCP: Electric Vehicle Charging Point
EQIA: Equalities Impact Assessment
CIA: Climate Impact Assessment
MTFP: Medium Term Financial Plan
PA 23: Procurement Act 2023
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item9
Resolved
That the award of the contract for an electric vehicle charging supplier following the procurement process, be delegated to the Strategic Director of Resources in consultation with the Lead Member for Resources and Chair of the Environment & Sustainable Transport Committee.
Word for word from the decision Sutton published for this meeting.Source: moderngov.sutton.gov.uk
Page 61 Agenda Item 9 Electric Vehicle Charging Point (EVCP) Procurement
Report Title Electric Vehicle Charging Point (EVCP) Procurement
Committee Strategy and Resources Committee
Meeting Date 22 June 2026
Chair Councillor Barry Lewis - Leader of the Council
Lead Member Councillor Sunita Gordon - Lead Member for Resources
Report From Richard Simpson - Strategic Director of Resources and s151 Officer
Report Author Thuso Selelo - Director of Assets & Capital Delivery
Wards Affected Council Business All Wards
Ambitious for Sutton An efficient and well run Council priorities Action on climate change
Open/Exempt Open
Signed Date 9 June 2026
1 Summary
1.1 The purpose of this report is to update the Committee on plans to use council assets to increase the supply of Electric Vehicle Charging Points (EVCPs) in the borough. The aim is to create infrastructure which supports the uptake of more sustainable transport options for Sutton residents, whilst also generating income which can be reinvested into local services.
1.2 The proposal is to use around 40 council-owned sites to provide around 180 new fast, rapid and ultra-rapid EV chargers. The mechanism to deliver this would be a concessionary contract with an EVCP operator, who would own and be responsible for the chargers, while the council would retain a share of the income generated.
1.3 This report updates the Committee on the procurement process that is being undertaken in order to select a preferred operator, and seeks approval for the Strategic Director of Resources to award the contract.
1.4 Whilst this opportunity is specifically about use of council assets (as opposed to EV chargers on the public highway), there will be collaborative working across the council and with partners to ensure the EV charging infrastructure across the borough meets the needs of Sutton residents.
Report page 1 Agenda Item 9 Page 62 Electric Vehicle Charging Point (EVCP) Procurement
2 Recommendation
2.1 To delegate the award of the contract for an electric vehicle charging supplier following the procurement process, to the Strategic Director of Resources in consultation with the Lead Member for Resources and Chair of the Environment &Sustainable Transport Committee.
3 Background and Key Information
3.1 In 2025, the Council worked with a digital partner (Triple Value Impact) to identify areas where digital technology could be used to support the delivery of council priorities and generate savings. Among other areas, this work produced a business case to increase Electric Vehicle Charging Points (EVCPs) in the borough, with the aim of both supporting sustainable transport and making the best use of council assets to generate income that can be reinvested in local services.
3.2 An opportunity was identified to use council-owned land to deliver much needed high speed electric vehicle charging points across the borough to meet a projected increase in demand. While Sutton already has a number of EV chargers (mainly lamp column chargers, with some fast and rapid chargers), demand for EV charging is anticipated to grow by 2-3 times by 2030, and there is further potential to leverage existing council assets such as car parks.
3.3 As part of the business case, a site assessment was carried out to identify the locations where EV chargers could be installed. This assessment included officers responsible for Parks and Open Spaces, Parking, Highways & Transport, and Asset Management. The proposed sites were identified to align with areas where the future demand for EV chargers is expected to be highest. These include town centres, key retail areas, transport hubs, and residential areas with limited off-street parking. By prioritising these locations, the roll-out should maximise usage and provide convenient access for residents, commuters, and visitors.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.