( i ) To note the progress made on public realm schemes, the Local Committee’s current financial position and the balance of £23,507 public realm funding remaining in 2014/15. (ii) That the remaining £505 of Transport for London funding be used on a scheme to improve parking in Calthorpe Gardens, or failing that such other parking scheme determined by the Executive Head of Commissioning in consultation with the Chair. ( iii ) That, subject to financial provision being made in revenue estimates 2015/16 for public realm funding, the sum of £7,250 be allocated for barrier baskets and floor planters in that year. (iv) That the scheme for solar-powered lights in trees in Manor Park, Sutton be not proceeded with and the provision of £2,000 be re-allocated to another scheme in the Park as yet to be determined. Councillor Kevin Burke declared a non-pecuniary interest in the scheme for road name signs in the Landseer Conservation Area.
Word for word from the decision Sutton published for this meeting.Source: moderngov.sutton.gov.uk
1.1This report provides an update on the progress of public realm projects since September 2014, new public realm schemes for the committee to consider and provides confirmation of the remaining budgets for 2014/15.
Recommendations
2.1To earmark a sum of £7,250 for planters and barrier baskets, as set out in Appendix A, to be funded from 2015/16 Public Realm Revenue Budget, subject to budgets being made available within the 2015/16 budget cycle that will be approved in March 2015.
Background
3.1This Committee has been allocated £41,263 of Public Realm capital funding to invest in area improvements, £16,505 for transport related schemes and £10,000 of revenue funding. Agenda Item 8 Page 14
4. Issues
Schemes for Consideration of Funding 4.1 Public realm schemes for consideration at this committee are detailed under Appendix A – Section 1
Current Public Realm Scheme Programme 4.2 Progress to date on current public realm schemes, funded by the committee, are detailed under Appendix A – Section 2.
Completed Public Realm Schemes 4.3 Public realm schemes which have been completed since the last meeting of the committee are detailed under Appendix A – Section 3. These include:
5.1Public realm schemes can be proposed by ward councillors or community representatives. Consultation is then undertaken to agree which schemes should be proposed. These are then voted on at each meeting of the Local Committee.
6. Impacts and Implications
Financial
6.1The Sutton Local Committee currently has a total available budget of £24,162 made up of £23,507 Public Realm Capital, £505 Transport for London funding and £150 direct revenue funding, if the proposals are agreed. This is detailed in Appendix A – Section 5
Legal
6.2There are no specific legal implications arising from this report.
Equalities
6.3The schemes described in this report have been subject to consultation with local residents, councillors, community representative and partner organisations. Meetings Page 15 Agenda Item 8
are held in accessible venues and everyone is encouraged to take part and put forward their ideas.
6.4When public realm improvements are made as a result of decisions taken by the Local Committee, particular account is taken of the requirements under the Disability Discrimination Act and Equality Act 2010 with regard to access requirements.
Localism
6.5Many of the schemes that are approved have a positive effect by promoting community activity and improving shared spaces that everyone can enjoy.
6.6The work of the Local Committee and the public realm budget are a key part of Sutton Council’s response to the localism agenda, and actively promotes the engagement of local residents in decision making.
7. Appendices and Background Documents
Appendix Letter Title A Area Improvements and Public Realm Programme
Background Documents There are no background documents relating to this report.
Audit Trail Version Date:
1.0Draft 03/11/2014 2.0 Draft 04/11/2014
Consultation with other officers Officer Comments Sought Comments checked by Finance Yes Tony Cooke Legal Yes/No Insert name of relevant officer Other Officers: Yes Consultation has been sought with the relevant officers as detailed in Appendix A Agenda Item 8 APPENDIX A 1. New Schemes for Consideration
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.