That the tenders submitted be opened by the Surveyor and Treasurer. (d) Employee Matters To note:- ( i ) That Margi Singh, Administration Manager, received a merit for her first assignment in law as part of the first module of the Institute of Cemetery and Crematorium Management (ICCM) Certificate in Management. (ii) That Karen Levi and Jo Benjafield , Administration Assistants, have begun studies towards an NVQ in Business Administration. (iii) That Adam Petry , Crematorium Technician, will attend the ICCM course in customer care. (iv) That all Crematorium staff will complete the enhanced Certificate of Cremation as part of the ICCM’s guidelines regarding the cremation of babies. (e) Recycling of Metals Following Cremation To note, further to Minute 8(e) of the meeting on 10 June 2014, that a cheque for £3,333 has been sent ... view the full minutes text for item 19.
Word for word from the decision Sutton published for this meeting.Source: moderngov.sutton.gov.uk
NORTH EAST SURREY CREMATORIUM BOARD Report by the Surveyor to the Board – 9 December 2014
BUSINESS LEVEL ACTIVITY
1. Appendix 1 to this report provides information in respect of cremation numbers for the past five years and for the first seven months of this financial year. Appendix 2 shows the same information in a graph. The current forecast of total cremations for the year is 1,750, slightly above the 5-year average and erring on the side of caution in case of a mild winter.
2. The first five months of this year saw a 3% fall in activity over that achieved in the same period last year, largely due to the need to limit the number of cremations undertaken each day. Demand for business remains high, however it is still necessary to limit the number of cremations to 8 per day due to problems associated with the cremators and abatement equipment.
3. The Treasurer’s initial estimate for the expected number of cremations for 2014/15 has been set at 1,750 (as above) and at a conservative 1,500 for 2015/16.
This item is for information.
PERFORMANCE MONITORING
4. Performance monitoring records in respect of the day-to-day management and operation of the Crematorium by Wandsworth Council’s Bereavement Services team for September, October and November were included as Appendices 3, 4 and 5 in the meeting information sent to Members. A summary of the information included in the five sections of the monitoring forms, for the period September to November, is set out in the following paragraphs.
5. Financial matters. All financial matters have been correctly reported and there are no issues needing to be drawn to Members’ attention.
6. Quality control issues. Both cremator machines are maintained by specialist German company IFZW. The machines are currently operational but not abated. Ongoing issues with the abatement equipment, and the absence of reassurance from IFZW that the cremators can be fully utilised, means that no more than 8 cremations a day are being undertaken. As a consequence some business has had to be turned away, this position is continuing in 2014/15. While preparations are made to replace the crematory equipment in order to achieve 100% abatement, a trading arrangement with Eastbourne crematorium continues with the intention of purchasing all of their spare abated cremations for 2014. There remains an expected shortfall in the number of abated cremations required to meet both the crematorium’s quota and the burden sharing agreement with Putney Vale. An update on arrangements is given in the Action Plan at Appendix 6.
7. Replacement of cremators. The anticipated programme for the scheme has only changed slightly, as a result of tenderers asking for an extension of time to submit their proposals.
Task Completion Date Issue of tender documentation 8 October 2014 Closing date for queries regarding the 5 November 2014 tender documentation Closing date for return of tender 10 December 2014 – 12 noon documentation Evaluation of tender documentation 4 February 2015 Preferred Supplier decided and notified 23 February 2015 Contract award (NESC Board meeting) 10 March 2015 Order Placed 17 March 2015 Contract commences Estimated w/c 4 May 2015 Contract completion (26 weeks term) Estimated w/c 2 Nov 2015
The above programme will include initial financial and technical appraisal in December 2014 and, subject to this exercise, visits to three sites (of officers’ choice) per qualifying tenderer. These visits are expected to take place in January 2015 and together with references from current operators, would inform the tender evaluation exercise. Stophers will be used to assist in the evaluation of sites.
Three tenders are expected, from IFZW, ATI and Facultative Technologies and all three companies have visited the crematorium to see the site and ask questions.
This item is for information.
8. Employee matters.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.