CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
London Borough of Sutton
Audit Committee, Thursday 11 December 2014 at 7.00pm

SMARTER SERVICES SUTTON PROGRAMME - OUTCOMES, LESSONS AND APPLICATION TO SMARTER COUNCIL PROGRAMME

Noted Finance 1 paper

Audit Committee noted this item on Thursday 11 December 2014. Below is the council's own wording, with the papers it was decided on.

Item23

Resolved

To note.
Word for word from the decision Sutton published for this meeting. Source: moderngov.sutton.gov.uk

Follow this further

Built from Sutton's papers

What the report saysPro

Report to Audit Committee

Summary

1.1This report outlines the outcomes and key lessons learned from the Smarter Services Sutton (SSS) programme and how the learning has been applied to subsequent programmes, in particular the Smarter Council programme. The report addresses the Committee’s resolution in minute 905/134 (iii) requesting a report on this subject during the 2014/15 municipal year.

1.2The SSS programme was successful, broadly achieving the overall savings target while maintaining resident satisfaction and delivering transformational change in at least some of the services reviewed as part of the programme. Success was aided by having a clear vision for the programme, effective leadership and governance arrangements, external challenge for all the reviews and making an effort to engage with stakeholders and staff. Areas for improvement include improving capacity and skills in programme and project management, continued focus on the reviews through to implementation, sustaining effective communication through the programme after the initial launch and identifying and exploiting synergies across the programme. These lessons and some of the key themes emerging from the individual reviews have informed the development and delivery of the Smarter Council Programme.

Recommendations

2.1This report is for information.

3. The Smarter Services Sutton Programme

3.1The SSS programme was intended to transform services, cut costs and maintain resident satisfaction. It was based on six principles:  Enabling smarter choices and behaviour change for customers (including internal customers for support services);  A measured approach to risk-taking, moving away from strong risk-aversion;  A focus on customers and their needs and priorities;  Working with partners to deliver and/or commission services; Agenda Item 6 Page 18

 An affordable management overhead, with flatter structures and a lower ratio of managers to staff; and  A clear expectation about the behaviours required of those in leadership roles across the Council.

3.2Starting in October 2009, the programme was delivered through a series of thirty reviews, mostly covering a specific service, although there were a small number of ‘cross-cutting’ reviews. Each review followed a common methodology and was given a savings target broadly equivalent to 25% of the service budget. Overall this meant that the programme aimed to achieve annual savings of £32.4m by 2014/15.

3.3The programme has broadly achieved its savings target, although some savings have been reprofiled to 2015/16 and 2016/17. The methodology helped to limit any negative effect on residents from the savings proposals and in some cases there were improvements in service. The ambition to deliver transformational change was sometimes, but not always, achieved.

3.4The programme had an original budget of £1.614m. This was made up of external spend on consultancy support and the cost of back filling staff seconded to the programme. The actual spend was £855k, an underspend of £759k. This was achieved partly because there was less need to use external support as there was rapid transfer of the necessary skills to council staff. Also services often decided not to take up the option of back filling seconded staff and some resource was provided from within the Improvement and Delivery team. The underspend has contributed towards the cost of the Smarter Council programme, although, as with SSS, maximum use has been made of internal resources.

4. Lessons from Smarter Services Sutton

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Smarter Services Sutton Programme: FinalReport 105 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

4 of 9 attended
DH
Councillor David HicksChair, present
AS
Councillor Alan SalterVice-Chair, present
RB
Councillor Richard BroadbentCommittee Member, present
AD
Councillor Adrian DaveyCommittee Member, absent
AM
Councillor Ali MirhashemCommittee Member, absent
RC
Councillor Richard CliftonSubstitute, present as substitute
GA
Gerald AlmerothOfficer, expected
PB
Phil ButlinOfficer, expected
DD
David DobbsOfficer, expected

On this subject at Sutton

Search all
  1. SMARTER SERVICES SUTTON PROGRAMME - OUTCOMES, LESSONS AND APPLICATION TO SMARTER COUNCIL PROGRAMMEThis decision
  2. Smarter services sutton - waste management reviewDecided
  3. Smarter Services Sutton Review - WasteNoted
  4. Smarter services sutton - waste management review updateNoted
  5. Smarter services sutton - review of waste managementNoted
  6. Smarter Services Report on Street CleansingNoted

More from Sutton Audit Committee

All decisions
MeetingDecisionOutcome
29 Mar 2018 Minutes of the last meetingthat the minutes of the meeting held on 11 January 2018 be agreed as a correct record. Agreed Open
29 Mar 2018 Treasury Management Quarterly reportRESOLVED that : The treasury management activity undertaken during the first nine months of the year was noted It be ... Noted Open
29 Mar 2018 Internal Audit Annual Plan 2018/19RESOLVED that : 1.The Internal Audit Plan, Charter and Strategy for 2018/19 was commented upon and it be approved. Approved Open
29 Mar 2018 SWLFP Anti Fraud and Investigations updateRESOLVED that : 1.The report was noted and commented upon . Noted Open
29 Mar 2018 Review risk registerRESOLVED that : The Corporate Risk Register was reviewed, considered and commented on. 2. No new risks were highlight... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies