Environment and Neighbourhood Committee approved this item on Thursday 15 January 2015. Below is the council's own wording, with the papers it was decided on.
That the schemes and measures detailed in the report which have received Local Implementation Plan funding become part of the Highways, Transport and Smarter Travel delivery programme for 2015/16. 2. That £1,366,000 financial provision be released for the capital schemes identified in the settlement for 2015/16 (£187,000 for various revenue initiatives have been approved for 2015/16 and will be included in the revenue estimates). 3. That £100,000 of the Local Transport Funding element of the settlement be allocated to the Local Committees on a per capita basis. 4. That the Executive Head of Commissioning be authorised to take all necessary steps to implement the schemes, including commencing any necessary statutory consultations.
Word for word from the decision Sutton published for this meeting.Source: moderngov.sutton.gov.uk
Report to: Environment and Neighbourhood Date: 15 January 2015 Committee
Report title: Local Implementation Plan Funding 2015/2016
Report from: Strategic Director - Environment and Neighbourhoods
Ward/Areas affected: Borough Wide
Chair of Committee: Councillor Jill Whitehead
Author(s)/Contact Paul Blunt, Transport Planning and Programme Manager Number(s): Tel. 020 8770 6445
Corporate Plan Priorities: A Green Council - Sutton's Transport Implementation Plan 2011-2014
Open/Exempt: Open
Signed: Date: 30 December 2014
1. Summary. This report outlines Transport for London’s (TfL’s) allocation to the Council of Local Implementation Plan (LIP) funding for 2015/16. A description of TfL’s transport related programmes is given and how schemes were selected to be put forward for funding. The details of the specific indicative allocations for individual schemes are listed in Appendix A and described in the report.
2. Recommendations.
a) Agree that the schemes and measures detailed in this report that having received LIP funding become part of the Highways, Transport and Smarter Travel delivery programme for 2015/16.
b) Release financial provision of £1,366k for the capital schemes identified in the settlement for 2015/16 (£187,000 for various revenue initiatives has been approved for 2015/16 and will be included in the revenue estimates).
c) Agree to allocate the £100k Local Transport Funding element of the settlement to Local Committees on a per capita basis.
d) Authorise the Executive Head of Commissioning to take all necessary steps to implement the schemes, including commencing any necessary statutory consultations. Agenda Item 8 Page 62
3. Background.
3.1The LIP is Sutton’s Transport Plan for the borough and was updated in 2013 to cover detailed transport proposals for the three financial years 2014/15 to 2016/17. It also sets out a longer term transport plan up to 2031. The LIP is Sutton’s contribution to the Mayor’s overall Transport Plan for London.
4. Funding Submission Consultation and Assessment Process.
4.1All Ward Councillors were invited to put forward schemes for inclusion in the 2015/16 spending submission. The list of proposals was produced, by ‘rolling forward’ the current LIP programme taking account of ongoing work and completed schemes. New proposals were selected following site visits and a degree of initial investigation to ensure the proposals were practicable, that they meet Mayor’s Transport Strategy (MTS) goals and the Borough’s transport objectives (Appendix B), design standards, represent value for money, and would be likely to be acceptable to the public. Ward Councillors were contacted for comments on new proposals and the list of proposals was reported to the Local Committees.
5. 2015/16 LIP Submission.
5.1The Environment and Neighbourhood Committee approved the LIP submission on 4th September 2014 (min.6/2014).
5.2The Council submitted its LIP funding submission for 2015/16 to TfL in October 2014.
6. 2015/16 LIP Allocations.
6.2TfL announced the LIP funding allocations for London Boroughs on 12th December 2014. There are three main LIP programmes as listed in the following paragraphs.
6.3Programme 1 - Maintenance. TfL funds principal road renewal, bridge strengthening, highway structures and assessment. There is no preset allocation for maintenance and schemes in this category are assessed by TfL on merit. An allocation of £170,000 has been made for Principal Road maintenance, slightly less than our £200,000 bid. TfL have yet to decide on whether to fund a number of bridge strengthening projects totalling £360,400. The London Bridges Engineering Group (LoBEG) is currently reviewing the pan-London bridge assessment and strengthening programme and any funding through this programme will be advised in February 2015.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.