CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
London Borough of Sutton
Environment and Neighbourhood Committee, Thursday 15 January 2015 at 7.30pm

Pay & Display Machine Replacement Programme

Decided Committee 1 paper

Environment and Neighbourhood Committee decided this item on Thursday 15 January 2015. Below is the council's own wording, with the papers it was decided on.

Item28

Resolved

That officers proceed with the procurement of new Pay & Display machines through the use of the Braintree Council Framework (PROC11-0155). 2. That the Strategic Director for Environment & Neighbourhoods have delegated authority to award the contract, in consultation with the Chair of Environment & Neighbourhoods Committee and authority to incur capital expenditure of £625,000 so that work may proceed.
Word for word from the decision Sutton published for this meeting. Source: moderngov.sutton.gov.uk

Follow this further

Built from Sutton's papers

What the report saysPro

Report to Environment and Neighbourhood Committee

Summary

1.1As part of a programme of rationalisation and modernising the Parking Service, linking with other activities such as the re-commissioning of the Parking Enforcement contract and refresh and improvement of CCTV infrastructure, the Pay and Display machine network is to be refreshed.

1.2Capital funding is approved for replacement of the existing Pay and Display machines which operate pay and display parking in Sutton Town Centre and surface car parks across the Borough. Improvements to multi-storey pay on foot machines will also be considered subject to available resources.

1.3There are in existence a number of frameworks which are able to be used as a procurement route for the new Pay & Display machines. Three have been investigated:

 ESPO (Eastern Shires Purchasing Organisation) - Framework 509 (Pay and Display Solutions and Parking Management Information Systems  Braintree District Council – Framework PROC11-0155 (Car Parking Equipment)  Crown Commercial Services – RM869 (Traffic Management Technology) Agenda Item 7 Page 56

1.4Each provides a route for procurement for replacement machines and associated maintenance through mini competition with ESPO offering a direct award route also which cuts down the procurement timeline to award the contract.

1.5The replacement programme will be used as an opportunity to rationalise and reposition the Pay and Display machine network and introduce added functionality (where required) including, but not limited to:

 credit/debit card facility to reduce cash transactions  multiple printers to reduce machine down time  solar power to reduce running costs and reliance on street lighting columns  remote access via CCTV private wireless network/4G network to increase access to management information, service status and reduce costs of tariff changes

1.6Following investigation it is recommended that the Braintree Council Framework (PROC11- 0155) be utilised for this procurement due to the specification being fit for purpose with all options to achieve objectives, outlined above, able to be procured under Lot 2 (Pay & Display Solutions).

1.7Due to the value of the contract a Committee decision is required to approve the process and delegate authority for award of contract

Recommendations

2.1That the Environment & Neighbourhoods Committee agrees to Officers proceeding with the procurement of new Pay and Display machines through use of the Braintree Council Framework (PROC11-0155).

2.2That the Environment & Neighbourhoods Committee agrees to delegate authority to award the contract to the Strategic Director – Environment & Neighbourhoods in consultation with the Chair of the Environment & Neighbourhoods Committee and authority to incur capital expenditure of £625k is given so that work can proceed.

Background

3.1There are 150 machines in the current network, the majority of which were installed in 1994. Two of these machines, located in Wallington Library Car Park, were installed in 2011 through the Wallington Integrated Transport package of regeneration works.

3.2The operational life of a P&D machine is typically 8 to 10 years. With the landscape and provision of on street parking having changed considerably since 1994, a number of machines are located incorrectly due to removal and/or relocation of P&D parking bays.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
07: Pay and Display Equipment Replacement Programme reportReport 130 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 13 attended
JW
Councillor Jill WhiteheadChair, present
NP
Councillor Nighat PirachaVice-Chair, present
KB
Councillor Kevin BurkeCommittee Member, present
CH
Councillor Colin HallCommittee Member, apologies
PM
Councillor Patrick McManusCommittee Member, apologies
SP
Councillor Steve PenneckCommittee Member, present
HP
Councillor Hamish PollockCommittee Member, present
TS
Councillor Tony ShieldsCommittee Member, present
PW
Councillor Paul WingfieldCommittee Member, present
HZ
Councillor Hanna ZuchowskaCommittee Member, present
MA
Councillor Manuel AbellanSubstitute, present as substitute
TC
Councillor Tim CrowleySubstitute, present as substitute

All 13 on the meeting page

More from Sutton Environment and Neighbourhood Committee

All decisions
MeetingDecisionOutcome
1 Oct 2020 Minutes of the previous meetingthat the minutes of the meeting held on 11 March 2020 be agreed as an accurate record. Agreed Open
1 Oct 2020 Any urgent businessthat 1. the petitions received regarding street cleansing and refuse collection in Wandle Valley ward, specifically t... Refused Open
1 Oct 2020 Petitions Regarding the Safer, Active, Greener Streets Schemethat 1. The petitions received regarding the streetspace schemes be noted 2. The following be noted: · the rationale ... Noted Open
1 Oct 2020 Authority to Consult on the Draft Sustainable Transport Strategy Supplementary Planning DocumentRESOLVED : 1. that the Draft Sustainable Transport Strategy 2020-2025 (STS) for public consultation be agreed. Agreed Open
1 Oct 2020 Environment Strategy 2020 Refresh and Climate Emergency Response PlanRESOLVED : that 1. the updated Environment Strategy be agreed 2. the Climate Emergency Response Plan be agreed 3. It ... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies