Children, Family and Education Committee decided this item on Thursday 12 March 2015. Below is the council's own wording, with the papers it was decided on.
To incur expenditure up to £1m for primary bulge class provision expected to be needed for the forthcoming academic year in (2015/16). 2. That expenditure up to £1m for secondary bulge class provision was not now needed for the forthcoming academic year in (2015/16). 3. To incur expenditure on phase 2 of the secondary expansion projects up to the stated value of £13.75m. 4. To incur expenditure up to £450K for capital maintenance expenditure as set out in paragraph 6 of the report. 5. To authorise further £185K expenditure for Phase 1 Sherwood Park works for the school to expand on the former site of Stanley Park High School bringing the total project cost to £5.685m.
Word for word from the decision Sutton published for this meeting.Source: moderngov.sutton.gov.uk
Report to Children, Family and Education Committee
Summary
1.1This report provides an update on the delivery of school places in Sutton required due to demographic increase in the Borough. It seeks approval for capital expenditure for phase two of the secondary expansion projects, Capital Maintenance, increased funding for Sherwood Park, and funding for bulge classes in 2015. It also provides an update on the latest position (at the time of writing) with respect to the proposed new secondary school.
Recommendations
2.1To give authority to incur expenditure up to £1m for primary bulge class provision expected to be needed for the forthcoming academic year in (2015/16).
2.2To give authority to incur expenditure up to £1m for secondary bulge class provision which may be needed for the forthcoming academic year in (2015/16).
2.3To seek authority to incur expenditure on phase 2 of the secondary expansion projects up to the stated value of £13.75m.
2.4To give authority to incur expenditure up to £450K for capital maintenance expenditure as set out in paragraph 6.
2.5Authorisation for a further £185K expenditure for Phase 1 Sherwood Park works for the school to expand on the former site of Stanley Park High School bringing the total project cost to £5.685m. Agenda Item 5 Page 8
3. Primary Expansion Programme
3.1As stated in previous reports to the Children, Family and Education Committee, school expansions are required to meet the rising demand for school places in Sutton. Since 2008, 18 of the Borough’s primary schools have permanently expanded with a further eight schools admitting ‘bulge’ classes. Additional primary provision is likely to be required in 2015 and 2016 with officers currently working with schools to identify where additional classes can be commissioned for the forthcoming academic year (pending application data being available in February). In addition, the Council is developing proposals for a new primary school at Hackbridge in response to significant planned housing in that part of the Borough.
3.2All of the permanent expansions mentioned above have now been approved by the CFE Committee and further permanent expansions in the primary sector have not been commissioned at this stage. As the table below indicates, births have dropped a little since a peak in 2009, therefore further expansions should be treated with a degree of caution to avoid over commissioning. Nevertheless, the transition ratios from births to numbers on roll has been increasing suggesting that demand will remain high (likely owing to inward migration and pupil yield from housing).
3.3The table below provides the Council’s latest projection with respect to the need for reception places. Births are known up until 2017, thereafter they are assumed to plateau. Given that there needs to be some spare capacity in the system it is likely that additional ‘bulge class’ provision for September 2015 will be required and officers are seeking to plan on the basis that as many as three additional classes may be required – especially given recent volatility on transition rates. As with previous planning years, authorisation is sought for expenditure of up to £1m for bulge class provision in order to ensure that sufficient reception school places can be provided for the forthcoming academic year.
2014 Projected requirement for places – projected from 2015 onwards
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.