That expenditure for Brookfield Primary School Phase 2 project up to a maximum of £600k was approved. 2. The update provided on Hackbridge Primary School expansion project was noted. 3. That expenditure up to £685k from Early Years ‘Trajectory Funding’ to build a new Nursery facility at Green Wrythe Primary School to support the demand for the 2 year free old entitlement places in the Borough subject to a tender exercise was approved. 4. That expenditure up to £755k for essential maintenance works that do not already have prior approval (as detailed in section 5 of the report and the project reports for Cheam Fields and Robin Hood Junior schools) was approved. 5. Updates on September 2015 Primary and Secondary planning rounds and on Phase 1, 2 and 3 of the Secondary Expansion Programme was noted.
Word for word from the decision Sutton published for this meeting.Source: moderngov.sutton.gov.uk
Report to Children, Family and Education Committee
Summary
1.1This report provides an update on the delivery of school/nursery places in Sutton required due to demographic increase in the Borough as well as a summary of the proposed capital maintenance programme. It is made up of the following items:
Brookfield Primary School Phase 2 – Key Stage 2 Update on Hackbridge Primary School Project Proposal to create new Nursery provision at Green Wrythe to support 2 year old provision. Capital Maintenance Programme 2015-16 September 2015 primary and secondary planning round Update on Phase 1 and 2 of the Secondary Expansion Programme Update on Phase 3 of the Secondary Expansion Programme (Free School)
Recommendations
2.1To approve expenditure for Brookfield Primary School Phase 2 project up to a maximum of £600k.
2.2To note update provided on Hackbridge Primary School expansion project.
2.3To approve expenditure up to £685k from Early Years ‘Trajectory Funding’ to build a new Nursery facility at Green Wrythe Primary School to support the demand for the 2 year free old entitlement places in the Borough subject to a tender exercise. Agenda Item 5 Page 8
2.4To approve expenditure up to £755k for essential maintenance works that do not already have prior approval (see section 5 below and note project reports for Cheam Fields and Robin Hood Junior.
2.5To note further updates on (i) September 2015 Primary and Secondary planning rounds, (ii) Update on Phase 1, 2 and 3 of the Secondary Expansion Programme.
3. Brookfield Phase 2
3.1Brookfield Primary School was formerly a 2FE primary school but a number of years ago, reduced its Published Admission Number (PAN) due to insufficient demand in the local area. As demand has increased in recent years, Brookfield permanently expanded in 2012 back to a 2FE primary school admitting 420 pupils in total. Alterations made to the internal accommodation at the school, coupled with limited accommodation provided by the original design, meant that the school would not have had sufficient and suitable accommodation to revert straight back to 2FE therefore some phased works were required.
3.2The first phase of the project which completed in September 2012 provided a new reception classroom and library / ICT space. Existing music, drama and resource spaces were then filled with classrooms as the school grew (having admitted additional classes since 2009) such that they are full to 2FE this year. Phase 2 works relate to the extension of the school hall, the provision of a small store and group room space in line with Building Bulletin 103 guidance. This project would be expected to deliver for the £600k sum already identified in the current basic need capital programme (see Appendix A for the Capital Spend Approval Report).
3.3Committee are requested to approve a budget £600k to complete phase 2 of this primary expansion.
4. Update on Hackbridge Primary School Expansion Project
4.1This project relates to the proposal to expand Hackbridge Primary School by 2 forms of entry (420 pupils) on to a split site on land near to Bedzed. The latest position is that designs for the school are progressing and the Transport Assessment has been completed. Given the nature of the site a significant number of surveys have been required prior to a planning application including an archaeological study/dig in May which required general works to form a temporary bridge across the culvert adjacent to London Road.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.