Resolved 1. That progress against priorities is noted 2. That the forecast outturn of a net overspend of £0.117m against an agreed revenue budget of £151.7m is noted 3. That the proposed amendments to the capital programme summarised at Appendix C be agreed
Word for word from the decision Sutton published for this meeting.Source: moderngov.sutton.gov.uk
1.1This report summarises the performance of the Council in the third period (October 2014- January 2015) against the Corporate Plan priorities and the 2014/15 commissioning intentions that support these. The report includes an overview of the organisation’s revenue and capital financial position, the highest rated risks from the Corporate Risk Register and a high level balanced score card summary of council-wide performance, including progress against our key Corporate Plan performance indicators. Where relevant, the report provides details of actions being taken to address risks of underperformance and significant budget variations up to month 10.
1.2The projected revenue outturn for the year is for an overspend of £0.117m (0. 1%) against a latest revenue budget estimate of £151.7m. The forecast for spend on the capital programme is £77.5m compared to a current capital programme budget for this year of £77.8m (an under spend of 0.4%).
Recommendations
2.1The Strategy and Resources Committee is recommended to:
1) Note progress against priorities 2) Note the forecast outturn of a net overspend of £0.117m against an agreed revenue budget of £151.7m 3) Agree the proposed amendments to the capital programme summarised at Appendix C
3. Background Agenda Item 4 Page 8
3.1The Council continues to face challenging financial circumstances arising from government funding reductions, the impact of demographic growth and government policies such as Welfare Reform and the Care Act.
3.2In response to these financial challenges, the Council has launched a borough wide consultation called Sutton's Future to provide residents and businesses with the opportunity to have their say on the future of the borough and proposed changes to the way the Council delivers its services. Recent consultations have focused on green garden waste, theatres and halls and the council tax reduction scheme.
3.3Despite this challenging financial situation, the Council's overall performance against key indicators is largely on track and good progress has been made so far this year towards delivering the Council’s priorities.
3.4This report summarises the performance of the Council in the third period (October 2014- January 2015) against the Corporate Plan priorities and the 2014/15 commissioning intentions that support these. The report includes an overview of the organisation’s revenue and capital financial position, the highest rated risks from the Corporate Risk Register and a high level balanced score card summary of council-wide performance, including progress against our key Corporate Plan performance indicators. Where relevant, the report provides details of actions being taken to address risks of underperformance and significant budget variations up to month 10
4. Issues
4.1Over the period to 2018-19, the Council has to find £38m of savings from its annual budget. The Council has delivered £32m of savings over the last four year period without significantly affecting levels of services, but this will be much more difficult to achieve over the next four years.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.