Release of Capital Funding for Highways Maintenance Programme 2015/16 and update on procurement of highways and lighting contracts

Decided Committee 4 papers

Environment and Neighbourhood Committee decided this item on Thursday 18 June 2015. Below is the council's own wording, with the papers it was decided on.

Item7

Resolved

To incur capital expenditure for the 2015/16 Planned Carriageway and Footway Maintenance Programmes as outlined in the 2012-2016 Capital Programme.
Word for word from the decision Sutton published for this meeting. Source: moderngov.sutton.gov.uk

Follow this further

Built from Sutton's papers

What the report saysPro

Report to Environment and Neighbourhood Committee

Page 65 Agenda Item 7

Report to: Environment and Neighbourhood Date: 18 June 2015 Committee Report title: Release of Capital Funding for Highways Maintenance Programme 2015/16 and update on procurement of highways and lighting contracts Report from: Mary Morrissey, Strategic Director – Environment, Housing and Regeneration Ward/Areas affected: Borough Wide Chair of Committee: Councillor Jill Whitehead Author(s)/Contact Davina Millership, Interim Head of Highways and Transport Number(s): Tel. 020 8770 6657 Corporate Plan Priorities: A Fair Council – Building safe, strong and healthy communities, A Green Council and A Smarter Council. Open/Exempt: Open Signed: Date: 22 May 2015

1. Summary 1.1 The Planned Carriageway and Footway Maintenance Works Programme is drawn up to address the more important maintenance requirements of roads in the Borough through a prioritisation process and this report seeks approval to incur capital expenditure for the roll out of the programme in 2015/16.

1.2The report also updates on progress regarding the re-procurement of the highways and street lighting contracts and the basis of the agreed extension of these existing contracts, as agreed at the January Environment and Neighbourhoods Committee.

2. Recommendations The Environment and Neighbourhood Committee is recommended to:

2.1Agree to incur capital expenditure for the 2015/16 Planned Carriageway and Footway Maintenance Programmes as outlined in 2012-2016 Capital Programme.

3. Background 3.1 A planned highway maintenance programme is drawn up each year for carriageways and footways.

3.2All carriageways are prioritised using an agreed weighting assessment, which takes account of:  the overall condition  amount of revenue spend per road  whether they are bus routes/cycle routes  if there are any other schemes programmed to take place  usage/location  Feedback on condition from Councillors/members of the public.

3.3Within this criterion, carriageways are given slightly higher weightings if they are requested by members, part of a cycle route, in poor condition or close to a high amenity area. Agenda Item 7 Page 66

3.4Maintenance works on footways are prioritised using an equal weighting assessment based on:  overall condition,  whether it is on a bus route  Proximity to high amenity areas.

3.5The maintenance programme is sent to all Public Utilities for consultation as required under the New Roads and Street Works Act (NRSWA) 1991. This allows the Utilities to give notice of their future planned works and provides an opportunity to co-ordinate works so that they are given an opportunity to do their works first prior to any work being carried out.

4. Issues Considerations when prioritising the Planned Highways Maintenance Works Programme 4.1 Condition surveys are the key method of assessing whether a carriageway or footway needs maintenance. For carriageways, scanning equipment is used to identify structural defects and visual inspections. Visual inspections by both external surveyors and highway staff are used to assess the condition of footways.

4.2Frequently concerns are raised regarding the condition of footways with officers because of their poor visual appearance. A concrete slab footway or carriageway may appear excessively cracked or a black top footway may appear extensively patched, although as long as they can be maintained free from trip hazards they are safe to use. Given the financial constraints on planned maintenance works, appearance alone will not justify replacement of surfacing materials.

4.3The issue about how long a carriageway or footway was last resurfaced is also not itself a relevant consideration: the key factors are condition and safety. The life of individual roads and footways are dependent upon many factors including the original construction depth and type of materials used, level of usage, level of statutory undertakers/utilities disturbance, tree roots and age of construction.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
07: Appendix A: Planned Highways MaintenanceAppendix 60 KB Download
PDF
07: Appendix B: Planned Highways Maintenance: FootwaysAppendix 84 KB Download
PDF
07: Appendix C: Reactive Maintenance Contract: Performance FrameworkAppendix 60 KB Download
PDF
07: Highways report: signedReport 98 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 13 attended
JW
Councillor Jill WhiteheadChair, present
NP
Councillor Nighat PirachaVice-Chair, present
MA
Councillor Manuel AbellanCommittee Member, present
AD
Councillor Adrian DaveyCommittee Member, present
RM
Councillor Richard MarstonCommittee Member, present
PM
Councillor Patrick McManusCommittee Member, present
SP
Councillor Steve PenneckCommittee Member, present
TS
Councillor Tony ShieldsCommittee Member, absent
PW
Councillor Paul WingfieldCommittee Member, present
HZ
Councillor Hanna ZuchowskaCommittee Member, present
MM
Mary MorrisseyOfficer, expected
EP
Eleanor PurserOfficer, expected

All 13 on the meeting page

On this subject at Sutton

Search all
  1. Release of Capital Funding for Highways Maintenance Programme 2015/16 and update on procurement of highways and lighting contractsThis decision
  2. Release of Capital Funding for Planned Highways Maintenance in 2013/14Decided

More from Sutton Environment and Neighbourhood Committee

All decisions
MeetingDecisionOutcome
1 Oct 2020 Minutes of the previous meetingthat the minutes of the meeting held on 11 March 2020 be agreed as an accurate record. Agreed Open
1 Oct 2020 Any urgent businessthat 1. the petitions received regarding street cleansing and refuse collection in Wandle Valley ward, specifically t... Refused Open
1 Oct 2020 Petitions Regarding the Safer, Active, Greener Streets Schemethat 1. The petitions received regarding the streetspace schemes be noted 2. The following be noted: · the rationale ... Noted Open
1 Oct 2020 Authority to Consult on the Draft Sustainable Transport Strategy Supplementary Planning DocumentRESOLVED : 1. that the Draft Sustainable Transport Strategy 2020-2025 (STS) for public consultation be agreed. Agreed Open
1 Oct 2020 Environment Strategy 2020 Refresh and Climate Emergency Response PlanRESOLVED : that 1. the updated Environment Strategy be agreed 2. the Climate Emergency Response Plan be agreed 3. It ... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies