Resolved
To incur capital expenditure for the 2015/16 Planned Carriageway and Footway Maintenance Programmes as outlined in the 2012-2016 Capital Programme.
Environment and Neighbourhood Committee decided this item on Thursday 18 June 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
To incur capital expenditure for the 2015/16 Planned Carriageway and Footway Maintenance Programmes as outlined in the 2012-2016 Capital Programme.
Page 65 Agenda Item 7
Report to: Environment and Neighbourhood Date: 18 June 2015 Committee Report title: Release of Capital Funding for Highways Maintenance Programme 2015/16 and update on procurement of highways and lighting contracts Report from: Mary Morrissey, Strategic Director – Environment, Housing and Regeneration Ward/Areas affected: Borough Wide Chair of Committee: Councillor Jill Whitehead Author(s)/Contact Davina Millership, Interim Head of Highways and Transport Number(s): Tel. 020 8770 6657 Corporate Plan Priorities: A Fair Council – Building safe, strong and healthy communities, A Green Council and A Smarter Council. Open/Exempt: Open Signed: Date: 22 May 2015
1. Summary 1.1 The Planned Carriageway and Footway Maintenance Works Programme is drawn up to address the more important maintenance requirements of roads in the Borough through a prioritisation process and this report seeks approval to incur capital expenditure for the roll out of the programme in 2015/16.
1.2The report also updates on progress regarding the re-procurement of the highways and street lighting contracts and the basis of the agreed extension of these existing contracts, as agreed at the January Environment and Neighbourhoods Committee.
2. Recommendations The Environment and Neighbourhood Committee is recommended to:
2.1Agree to incur capital expenditure for the 2015/16 Planned Carriageway and Footway Maintenance Programmes as outlined in 2012-2016 Capital Programme.
3. Background 3.1 A planned highway maintenance programme is drawn up each year for carriageways and footways.
3.2All carriageways are prioritised using an agreed weighting assessment, which takes account of: the overall condition amount of revenue spend per road whether they are bus routes/cycle routes if there are any other schemes programmed to take place usage/location Feedback on condition from Councillors/members of the public.
3.3Within this criterion, carriageways are given slightly higher weightings if they are requested by members, part of a cycle route, in poor condition or close to a high amenity area. Agenda Item 7 Page 66
3.4Maintenance works on footways are prioritised using an equal weighting assessment based on: overall condition, whether it is on a bus route Proximity to high amenity areas.
3.5The maintenance programme is sent to all Public Utilities for consultation as required under the New Roads and Street Works Act (NRSWA) 1991. This allows the Utilities to give notice of their future planned works and provides an opportunity to co-ordinate works so that they are given an opportunity to do their works first prior to any work being carried out.
4. Issues Considerations when prioritising the Planned Highways Maintenance Works Programme 4.1 Condition surveys are the key method of assessing whether a carriageway or footway needs maintenance. For carriageways, scanning equipment is used to identify structural defects and visual inspections. Visual inspections by both external surveyors and highway staff are used to assess the condition of footways.
4.2Frequently concerns are raised regarding the condition of footways with officers because of their poor visual appearance. A concrete slab footway or carriageway may appear excessively cracked or a black top footway may appear extensively patched, although as long as they can be maintained free from trip hazards they are safe to use. Given the financial constraints on planned maintenance works, appearance alone will not justify replacement of surfacing materials.
4.3The issue about how long a carriageway or footway was last resurfaced is also not itself a relevant consideration: the key factors are condition and safety. The life of individual roads and footways are dependent upon many factors including the original construction depth and type of materials used, level of usage, level of statutory undertakers/utilities disturbance, tree roots and age of construction.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
07: Appendix A: Planned Highways MaintenanceAppendix | 60 KB | Download |
PDF |
07: Appendix B: Planned Highways Maintenance: FootwaysAppendix | 84 KB | Download |
PDF |
07: Appendix C: Reactive Maintenance Contract: Performance FrameworkAppendix | 60 KB | Download |
PDF |
07: Highways report: signedReport | 98 KB | DownloadRead as text |
Follow Environment and Neighbourhood Committee at Sutton and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 1 Oct 2020 | Minutes of the previous meetingthat the minutes of the meeting held on 11 March 2020 be agreed as an accurate record. | Agreed | Open |
| 1 Oct 2020 | Any urgent businessthat 1. the petitions received regarding street cleansing and refuse collection in Wandle Valley ward, specifically t... | Refused | Open |
| 1 Oct 2020 | Petitions Regarding the Safer, Active, Greener Streets Schemethat 1. The petitions received regarding the streetspace schemes be noted 2. The following be noted: · the rationale ... | Noted | Open |
| 1 Oct 2020 | Authority to Consult on the Draft Sustainable Transport Strategy Supplementary Planning DocumentRESOLVED : 1. that the Draft Sustainable Transport Strategy 2020-2025 (STS) for public consultation be agreed. | Agreed | Open |
| 1 Oct 2020 | Environment Strategy 2020 Refresh and Climate Emergency Response PlanRESOLVED : that 1. the updated Environment Strategy be agreed 2. the Climate Emergency Response Plan be agreed 3. It ... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.