Resolved
RESOLVED : 1. That the Inter Authority Agreement relating to the environmental services procurement be agreed. 2. That the governance arrangements for de-selection of bidders, as set in paragraph 4.6 of the report, be agreed.
Environment and Neighbourhood Committee agreed this item on Thursday 17 September 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED : 1. That the Inter Authority Agreement relating to the environmental services procurement be agreed. 2. That the governance arrangements for de-selection of bidders, as set in paragraph 4.6 of the report, be agreed.
1.1The four boroughs of the South London Waste Partnership are bound by Inter Authority Agreements with regards Phase A and B in relation to the procurement and contracts relating to waste disposal (IAA).
1.2This report seeks approval to agree a new IAA relating to the current environmental services project for the procurement of Waste Collection (including Commercial Waste), Street Cleaning, Fleet Management and Parks, including grounds maintenance and their associated services.
That the Environment and Neighbourhoods Committee:
2.1Agree the Inter Authority Agreement relating to the environmental services procurement.
2.2Agree the governance arrangements for de-selection of bidders at 4.6.
3.1Sutton, along with RB Kingston, LB Merton and LB Croydon have been part of the South London Waste Partnership since 2004. In establishing the Partnership it was a legal requirement to fully constitute a Joint Waste Committee (JWC), underpinned by an IAA. As stated above, previous IAAs have only related to the procurement and contract of waste disposal activities.
3.2In November 2014, it was agreed at the Environment and Neighbourhood Committee to commence a joint procurement for waste collection, street cleaning, winter maintenance (gritting), commercial waste and vehicle maintenance (LOT1) and grounds maintenance including parks, arboriculture and grass verges (LOT2). It was also agreed that delegated authority be given to the Chair of Management Group in consultation with the Management Group, Strategic Steering Group, the Partnership legal lead and members of the Joint Waste Committee to deselect bidders and agree the specification at each stage up to and including the invitation to submit final tender.
4. Issues
4.1The existing IAAs relate to the agreement between the partner boroughs for their waste disposal contracts, this includes the procurement arrangements and management of contracts.
4.2This IAA relates solely to the procurement of Lots 1 and 2 by the boroughs and sets out amongst other things the principles for sharing costs of the procurement. The procurement of Lots 1 and 2 is not covered by previous IAAs, as this procurement is not being carried out by the SLWP itself, but by the Boroughs who are jointly procuring these services and utilising the relationships and experience that has come from the SWLP. This current IAA formally evidences by way of a Deed the principles agreed via a signed letter by the Chief Executive dated 26 January 2015.
4.3Officers have taken the principles set out in this letter and the arrangements in current IAAs and created a revised document. This document relates to the procurement phase only of the project with a contract management section to be added prior to contract commencement in April 2017.
4.4The main principles remain consistent with those in existing agreements. The points below summarise the main elements of the agreement;
1. London Borough of Croydon will act as the procuring authority. 2. Each of the boroughs will agree to indemnify others in the event of their withdrawal from the procurement. 3. Partners will equally share the cost of procurement (25% each). 4. All partners will commit the required resources to the project. 5. Any depots made available by partners will be for the duration of the contract. 6. The revised governance arrangements.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
05: IAA reportReport | 120 KB | DownloadRead as text |
Follow Environment and Neighbourhood Committee at Sutton and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 1 Oct 2020 | Minutes of the previous meetingthat the minutes of the meeting held on 11 March 2020 be agreed as an accurate record. | Agreed | Open |
| 1 Oct 2020 | Any urgent businessthat 1. the petitions received regarding street cleansing and refuse collection in Wandle Valley ward, specifically t... | Refused | Open |
| 1 Oct 2020 | Petitions Regarding the Safer, Active, Greener Streets Schemethat 1. The petitions received regarding the streetspace schemes be noted 2. The following be noted: ยท the rationale ... | Noted | Open |
| 1 Oct 2020 | Authority to Consult on the Draft Sustainable Transport Strategy Supplementary Planning DocumentRESOLVED : 1. that the Draft Sustainable Transport Strategy 2020-2025 (STS) for public consultation be agreed. | Agreed | Open |
| 1 Oct 2020 | Environment Strategy 2020 Refresh and Climate Emergency Response PlanRESOLVED : that 1. the updated Environment Strategy be agreed 2. the Climate Emergency Response Plan be agreed 3. It ... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.