That the Opportunity Sutton Ltd Sub-Committee: 1. Approves the Sutton Decentralised Energy Network Limited business plan as attached in Appendix A to the report, noting the revisions made. 2. Approves the Sutton Decentralised Energy Network Limited risk register as attached in Appendix B to the report, noting the revision made. 3. Notes the project performance update, in paragraphs 3.3 – 3.5 of the report.
Word for word from the decision Sutton published for this meeting.Source: moderngov.sutton.gov.uk
1.1This report presents for approval the business plan annual review for Sutton Decentralised Energy Network Limited, noting amendments to the Phase 1 delivery timetable.
Recommendations
2.1That the Sub-Committee approve the Sutton Decentralised Energy Network business plan as attached in Appendix A, noting the revisions made.
2.2That the Sub-Committee approve the Sutton Decentralised Energy Network risk register as attached in Appendix B, noting the revision made.
2.3The Sub-Committee note the project performance update, in paragraphs 3.3 – 3.5. Agenda Item 5 Page 6
Background
3.1Following the Council’s decision in July 2014 to establish an Energy Services Company (ESCo), a detailed business model was prepared to demonstrate the commercial viability of the proposed company. The initial business plan was approved by the OSL Sub-Committee on 4 August 2015, along with the Shareholding Agreement enabling Sutton Decentralised Energy Network Limited to be established.
3.2Since the approval of the business plan at OSL Sub-Committee progress has been made on both Phase 1 and Phase 2 of the network.
Performance Update Phase 1 3.3 SDEN launched an OJEU procurement process to select a Design & Build and Operation & Maintenance Contractor for Phase 1 of the network. Pre-Qualification Questionnaires have been received from 12 bidders and evaluation has been completed.
3.4Network Rail have granted approval, in-principle, to SDEN’s proposal to cross the railway line at Hackbridge. SDEN have made minor amendments as per Network Rail’s request and will be submitting the final designs for approval shortly.
3.5A Heat Purchase Agreement has been agreed internally and issued to Viridor for comment. Once the document has been reviewed by Viridor detailed negotiations will commence before the contract is signed. The Master Supply Agreement, for Barratt, has been drafted and technical negotiations are on-going.
Phase 2 3.6 The Sutton Decentralised Energy Network and prospectus were formally launched at the Guildhall in November 2015. The launch was well attended by developers, partners and stakeholders.
4. Business Plan Review: Revisions
4.1The changes to the SDEN Limited business plan, as agreed by the previous Opportunity Sutton Limited Sub Committee, have been minor updates to the Phase 1 delivery plan and updates to the Phase 2 commercial plan. These changes have been made so the business plan aligns with the Phase 1 project plan, as agreed by the SDEN Project Board. In addition the SDEN Limited Risk Register has been removed from the main business plan document and is appendix B to this report. Details of these changes are set out in paragraph 4.2.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Cognus Business Plan and BudgetThat the progress made by Cognus Limited against its 2025/28 Business Plan be noted. That the update on Cognus Limite...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.