Resolved
Resolved 1. That the performance update as set out at Appendix A to the report be noted. 2. That the amended risk register as set out at Appendix B (exempt) be approved.
Sutton Shareholdings Board noted this item on Monday 9 May 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved 1. That the performance update as set out at Appendix A to the report be noted. 2. That the amended risk register as set out at Appendix B (exempt) be approved.
1.1This report presents for noting the update contained in the Sutton Decentralised Energy Network performance report and presents for approval the risk register for Sutton Decentralised Energy Network Limited.
2.1That the Opportunity Sutton Limited Sub-Committee notes the performance update contained in the Sutton Decentralised Energy Network Performance report in Appendix A.
2.2Approves the amended Sutton Decentralised Energy Network risk register as attached in Appendix B (exempt).
3.1Following the Council’s decision in July 2014 to establish an Energy Services Company (ESCo), a detailed business model was prepared to demonstrate the commercial viability of the proposed company. The initial business plan was approved by the OSL Sub-Committee on 4 Agenda Item 6 Page 8
August 2015, along with the Shareholding Agreement, enabling Sutton Decentralised Energy Network Limited to be established.
3.2Since the approval of the business plan at OSL Sub-Committee progress has been made on both Phase 1 and Phase 2 of the network.
Performance Update
3.3The performance update is attached at Appendix A – Sutton Decentralised Energy Network Performance Report dated March and April 2016.
4. Risk Register: Revisions
4.1The changes to the SDEN Limited risk register are as agreed by the previous Opportunity Sutton Limited Sub Committee. Former risk 2 "Failure to follow the statutory guidance on the trading power issued by the DCLG" has been removed because Sutton Decentralised Energy Network Limited has now been formally set up. In addition there have been minor amendments to the mitigation of risk 21.
5. Impacts and Implications
Financial
5.1In July 2013, the London Borough of Sutton’s Strategy and Resources Committee (S&R) approved the Conceptual Business Case for the development of a district heating network in Sutton, with funding of £4.5m.
5.2A detailed Financial Model has been prepared for the Phase 1 Scheme and this demonstrates positive cash flow of £1.54m from delivery of the scheme.
5.3The interest rate being charged by the Council to the Company will be at a commercial rate to ensure compliance with state aid regulations. The Council will borrow the money and incur interest at the Public Works Loans Board rate which will be lower than the commercial rate charged to the Company. The interest margin charged by the Council is estimated to achieve additional income of around £1m over the life of the loan.
Legal
5.4The recommendations which are before the Sub-Committee do not give rise to any specific legal implications.
5.5With reference to Risk 2, as set out in the Risk Register, the external lawyers who are advising on relevant matters in relation to SDEN have advised that the “dominant influence” which the Council will retain over SDEN is sufficient to bring SDEN within the scope of the Utilities Contracts Regulations 2016 (“UCRs 2016). Consequently, in purchasing activities in respect Page 9 Agenda Item 6
of the district heat network, SDEN will for the most part need to comply with the UCRs 2016. These Regulations set out a procurement regulatory framework in compliance with EU law.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
SDENAppendix A | 294 KB | Download |
PDF |
SDENReport | 154 KB | DownloadRead as text |
Follow Sutton Shareholdings Board at Sutton and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 10 Mar 2026 | MinutesRESOLVED : that the minutes of the meeting held on 4 November 2025 be agreed as an accurate record. | Agreed | Open |
| 10 Mar 2026 | Sutton Decentralised Energy Network (SDEN) Business Plan and BudgetThat the Sutton Decentralised Energy Network 2026-29 Business Plan and budget be approved. That the Sutton Decentrali... | Approved | Open |
| 10 Mar 2026 | Cognus Business Plan and BudgetThat the progress made by Cognus Limited against its 2025/28 Business Plan be noted. That the update on Cognus Limite... | Noted | Open |
| 10 Mar 2026 | Sutton Living Limited (SLL) 2026/27 Budget & Ten Year Business PlanThat Sutton Living Limited's updated business plan for the period 2026 to 2036 as set out at Appendix A, be approved.... | Approved | Open |
| 4 Nov 2025 | MinutesRESOLVED : that the minutes of the meeting held on 25 March 2025 be agreed as an accurate record. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.