Resolved 1. That the performance update contained in the Sutton Decentralised Energy Network Performance Report as set out at Appendix A to the report be noted. 2. That the un-amended Sutton Decentralised Energy Network Risk Register as set out at Appendix B (exempt) to the report be noted.
Word for word from the decision Sutton published for this meeting.Source: moderngov.sutton.gov.uk
1.1This report presents for noting the update contained in the Sutton Decentralised Energy Network Performance Report and presents for noting the Risk Register for Sutton Decentralised Energy Network Limited.
Recommendations
The Sutton Shareholdings Board is recommended to:
2.1Note the performance update contained in the Sutton Decentralised Energy Network Performance Report in Appendix A.
2.2Note the un-amended Sutton Decentralised Energy Network Risk Register as attached in Appendix B (exempt) from the previous committee. Agenda Item 5 Page 4
Background
3.1Following the Council’s decision in July 2014 to establish an Energy Services Company (ESCo), a detailed business model was prepared to demonstrate the commercial viability of the proposed company. The initial business plan was approved by the OSL Sub-Committee (now the Sutton Shareholdings Board) on 4 August 2015, along with the Shareholder Agreement, enabling Sutton Decentralised Energy Network Limited to be established.
3.2Since the approval of the business plan at OSL Sub-Committee (now the Sutton Shareholdings Board) progress has been made on both Phase 1 and Phase 2 of the network.
4. Performance Update
4.1The performance update is attached at Appendix A – Sutton Decentralised Energy Network Performance Report dated May and June 2016.
5. Risk Register: Revisions
5.1There have been no amendments to the Risk Register since the previous Opportunity Sutton Limited Sub-Committee (now the Sutton Shareholdings Board) on 9 May 2016.
6. Impacts and Implications
Financial
6.1In July 2013, the London Borough of Sutton’s Strategy and Resources Committee (S&R) approved the Conceptual Business Case for the development of a district heating network in Sutton, with funding of £4.5m.
6.2A detailed Financial Model has been prepared for the Phase 1 Scheme and this demonstrates positive cash flow of £1.54m from delivery of the scheme.
Legal
6.3The recommendations which are before the Shareholdings Board do not give rise to any specific legal implications.
7. Appendices and Background Documents
Appendix letter Title
A Sutton Decentralised Energy Network Limited Performance Report
B Sutton Decentralised Energy Network Limited Risk Register, exempt by virtue of paragraph 3 of Schedule 12A of the Local Government Act 1972.) Page 5 Agenda Item 5
Background documents
n/a
Audit Trail
Version Final Date: 07/06/2016
Consultation with other officers
Finance Yes Lyndsey Gamble
Legal Yes Sheila Saunders
Integrated Impact Assessment No N/A required? This page is intentionally left blank
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Cognus Business Plan and BudgetThat the progress made by Cognus Limited against its 2025/28 Business Plan be noted. That the update on Cognus Limite...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.