Resolved
that the Environment & Neighbourhood Committee: 2.1 Approved the capital expenditure for the 2016/17 financial year ‘Planned Highway and Pavement Maintenance Programme’ as outlined in the attached 2012-16 Capital Programme.
Environment and Neighbourhood Committee approved this item on Thursday 15 September 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
that the Environment & Neighbourhood Committee: 2.1 Approved the capital expenditure for the 2016/17 financial year ‘Planned Highway and Pavement Maintenance Programme’ as outlined in the attached 2012-16 Capital Programme.
1.1The Council has a statutory duty under S41 of the Highways Act 1980 to maintain the highway in a safe condition for all users. The Planned Highway Maintenance Works Programme is drawn up to address the more important maintenance requirements of roads in the Borough and the prioritisation process is designed to deliver our duty of care under section 41 of the 1980 Highways Act and provide Best Value in the use of public funds.
The Environment and Neighbourhoods Committee is recommended to:
2.1Approve the capital expenditure for the 2016/17 financial year ‘Planned Highway and Pavement Maintenance Programme’ as outlined in the attached 201216 Capital Programme.
3.1A provisional planned highway maintenance programme is drawn up each year from: highways Inspectors’ reports, road condition survey(s), perceived need and the amount of capital available; this is pulled together into a coherant list by the Planned Maintenance Engineer.
3.2All roads on the provisional planned maintenance list are then prioritised using an agreed weighting assessment, which takes account of the overall condition, usage, location and Agenda Item 6 Page 50
feedback on condition from Councillors and members of the public. Within this criterion, principal roads, bus routes and cycleways receive a higher priority, as do footways in shopping areas and those close to hospitals, schools and care homes.
3.3Due to capital funding levels there is rarely enough money to meet the needs of the borough hence the need to prioritise based upon need. This leads to a backlog of roads requiring attention.
3.4The provisional list of roads is sent to all public utilities for consultation as required under the New Roads and Street Works Act (NRSWA) 1991, this allows the utilities to give notice of their future planned works and provides an opportunity for schemes to be programmed to minimise the level of delay to the wider community.
3.5Residents and transport providers are informed of pending works through an advance letter drop in the weeks leading up to planned maintenance taking place. The term contractor also affixes notices to lamp columns in the days preceding the works and bus operators advise passengers of any diversions required.
4. Issues
4.1Local authorities are now required by HM Treasury to value their transport assets in line with CIPFA’s Transport Infrastructure Code and report this annually; the Depreciated Replacement Cost (DRC) of Sutton’s highway assets was reported as £725 million in 2012/2013.
5.1A variety of planned maintenance methods are used to carry out the works dictated by existing condition and underlying construction materials ranging from full reconstruction (most expensive option) to surface overlays (cheapest option). The option chosen is designed to give the greatest longevity to the road at the least expense.
6. Impacts and Implications
Financial
6.1The capital estimates for planned maintenance in 2016/2017 are:
Highways Pavements Total £’000 £’000 £’000
700 500 1,200
6.2Agreement is needed by the Environment and Neighbourhood Committee to incur capital expenditure for the Planned Highway and Pavement Maintenance Programme so that the Page 51 Agenda Item 6
schedule of works identified under Appendices A and B can be undertaken during 2016/17 financial year.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
(6) Planned Maintenance Report 2016-2017: Appendix AAppendix | 290 KB | Download |
PDF |
(6) Planned Maintenance Report 2016-2017: Appendix BAppendix | 217 KB | Download |
PDF |
(6) Planned Maintenance Report 2016-2017: ReportReport | 105 KB | DownloadRead as text |
Follow Environment and Neighbourhood Committee at Sutton and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 1 Oct 2020 | Minutes of the previous meetingthat the minutes of the meeting held on 11 March 2020 be agreed as an accurate record. | Agreed | Open |
| 1 Oct 2020 | Any urgent businessthat 1. the petitions received regarding street cleansing and refuse collection in Wandle Valley ward, specifically t... | Refused | Open |
| 1 Oct 2020 | Petitions Regarding the Safer, Active, Greener Streets Schemethat 1. The petitions received regarding the streetspace schemes be noted 2. The following be noted: · the rationale ... | Noted | Open |
| 1 Oct 2020 | Authority to Consult on the Draft Sustainable Transport Strategy Supplementary Planning DocumentRESOLVED : 1. that the Draft Sustainable Transport Strategy 2020-2025 (STS) for public consultation be agreed. | Agreed | Open |
| 1 Oct 2020 | Environment Strategy 2020 Refresh and Climate Emergency Response PlanRESOLVED : that 1. the updated Environment Strategy be agreed 2. the Climate Emergency Response Plan be agreed 3. It ... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.