Planned Highway Maintenance and Street Lighting Programmes 2020/2021
DecidedCommittee3 papers
Environment and Neighbourhood Committee decided this item on Wednesday 11 March 2020. Below is the council's own wording, with the papers it was decided on.
that capital expenditure be incurred in 2020/21 for the proposed highway maintenance programme for footways and carriageways and street lighting column replacement programme, as detailed in paragraph 6.1 (subject to funding confirmation, and noting as the officer tabled at the meeting, that the Carriageways funding is £725k (rather than £718k as per the report)), so that the schedule of works identified under Appendices A and B can be undertaken. the Assistant Director, Highways, Transport, and Regulatory Services, in consultation with the Chair of the Environment and Neighbourhood Committee, be delegated authority to make in-year changes to the prioritised planned highway maintenance programme to facilitate effective delivery and to respond in-year to emerging priorities or unforeseen events, e.g. severe weather conditions.
Word for word from the decision Sutton published for this meeting.Source: moderngov.sutton.gov.uk
1.1As part of the Council’s ‘Ambitious for Sutton’ plan, the Council is committed to maintaining and improving the physical environment for all its residents. The Council’s highway network is the most visible, used and valuable physical asset for which the Council is responsible. To meet the Council’s corporate objective of being a great place to live, work and raise a family, considerable investment in the heavily used highway assets is required to maintain them in a serviceable condition. Highway maintenance needs for footways, carriageways and street lighting have been reviewed, and the proposed programme for 2020/21 is set out in Appendices A and B and prioritised on a Borough-wide basis.
Recommendations
2.1To incur capital expenditure in 2020/21 for the proposed highway maintenance programme for footways and carriageways and street lighting column replacement programme, as detailed in paragraph 6.1 (subject to funding confirmation), so that the schedule of works identified under Appendices A and B can be undertaken. Agenda Item 7 Page 36
2.2To delegate authority to the Assistant Director, Highways, Transport, and Regulatory Services, in consultation with the Chair of the Environment and Neighbourhood Committee, to make in-year changes to the prioritised planned highway maintenance programme to facilitate effective delivery and to respond in-year to emerging priorities or unforeseen events, e.g. severe weather conditions.
Background
3.1The Council’s public highway network is the most valuable asset the Council owns and has a major significance to borough residents, communities and businesses. A well-maintained network is critical to the way that the borough is perceived and provides one of the bedrocks underpinning the ‘Ambitious for Sutton’ agenda. As described in the Capital Strategy, key rolling programmes for the Council include highway asset maintenance, pavement improvements and resurfacing, and street lighting works. It is also a requirement of the “Well managed highway infrastructure” Code of Practice to develop planned maintenance programmes.
3.2A provisional planned highway maintenance programme is prepared each year from Council highways inspectors’ safety condition reports and road condition surveys. This is coupled with the level of capital funding available and allows for a list of borough public highway locations most in need of planned maintenance to be put into a works programme.
3.3All carriageway and footway locations on the provisional planned maintenance list are prioritised using a weighted score condition assessment, which takes account of the overall condition and usage of each location and incorporates feedback received from councillors and members of the public throughout the year, including petitions (e.g. the petition to resurface Woodmansterne Road has received 191 signatures). Under this process, strategic roads, bus routes and cycleways receive a higher priority, as do footways in shopping areas and those close to hospitals, schools and care homes. Street lighting columns are identified for replacement based on their age and condition. The prioritised lists are set out in the Appendices.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.