Resolved
Resolved That the amendment of the accounting period dates to 1 April to 31 March for Opportunity Sutton Limited (OSL), Sutton Living Limited (SLL), Sutton Decentralised Energy Network (SDEN) and Encompass, be noted and ratified.
Sutton Shareholdings Board noted this item on Tuesday 8 November 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved That the amendment of the accounting period dates to 1 April to 31 March for Opportunity Sutton Limited (OSL), Sutton Living Limited (SLL), Sutton Decentralised Energy Network (SDEN) and Encompass, be noted and ratified.
1.1This report is to note and ratify the amendment of the accounting period dates for Opportunity Sutton Limited (OSL), including the two subsidiary companies Sutton Living Limited (SLL) & Sutton Decentralised Energy Network (SDEN), and Encompass).
The Sutton Shareholdings Board is recommended to:
2.1Note and ratify the amendment of the accounting period dates to 1 April to 31 March for Opportunity Sutton Limited (OSL), Sutton Living Limited (SLL), Sutton Decentralised Energy Network (SDEN) and Encompass.
3.1The financial year end of each company was set in accordance with the date the company was registered at Companies House. This means that the financial year end was different for each company.
3.2The accounting periods can be amended by submitting a form to Companies House to either shorten or lengthen the accounting periods to change the financial year end date Agenda Item 5 Page 4
to 31 March. This has been completed by the Company Auditors, Turpin Barker Armstrong. 3.3 As this is a reserved matter, the Board is asked to ratify this amendment.
4. Impacts and Implications
Financial
4.1There are no direct financial implications.
Legal
4.2Under Schedule 1, Part A of the Shareholders Agreement for OSL, SLL and SDEN and Schedule 1 of the Shareholders Agreement for Encompass, amending the financial yearÂend date of the Company is a reserved matter for the Shareholder. The Shareholder is therefore required to provide their approval to change the financial year end date.
5. Appendices and Background Documents
Appendix Letter Title None
Background Documents None
Audit Trail Version Final Date: 27 September 2016
Consultation with other officers Officer Comments Sought Comments checked by Finance Yes Phil Butlin Legal Yes Laiping Man Integrated Impact Assessment No N/A required?
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Amendment to Accounting Period: ReportReport | 102 KB | DownloadRead as text |
Follow Sutton Shareholdings Board at Sutton and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 10 Mar 2026 | MinutesRESOLVED : that the minutes of the meeting held on 4 November 2025 be agreed as an accurate record. | Agreed | Open |
| 10 Mar 2026 | Sutton Decentralised Energy Network (SDEN) Business Plan and BudgetThat the Sutton Decentralised Energy Network 2026-29 Business Plan and budget be approved. That the Sutton Decentrali... | Approved | Open |
| 10 Mar 2026 | Cognus Business Plan and BudgetThat the progress made by Cognus Limited against its 2025/28 Business Plan be noted. That the update on Cognus Limite... | Noted | Open |
| 10 Mar 2026 | Sutton Living Limited (SLL) 2026/27 Budget & Ten Year Business PlanThat Sutton Living Limited's updated business plan for the period 2026 to 2036 as set out at Appendix A, be approved.... | Approved | Open |
| 4 Nov 2025 | MinutesRESOLVED : that the minutes of the meeting held on 25 March 2025 be agreed as an accurate record. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.