Resolved
Resolved That the performance update contained in the Sutton Decentralised Energy Network Performance Report, as set out in Appendix A, be noted.
Sutton Shareholdings Board noted this item on Wednesday 14 June 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved That the performance update contained in the Sutton Decentralised Energy Network Performance Report, as set out in Appendix A, be noted.
1.1This report is presented for noting the update contained in the Sutton Decentralised Energy Network Performance Report.
The Sutton Shareholdings Board is recommended to:
2.1Note the performance update contained in the Sutton Decentralised Energy Network Performance Report in Appendix A.
3.1Following the Council’s decision in July 2014 to establish an Energy Services Company (ESCo), a detailed business model was prepared to demonstrate the commercial viability of the proposed company. The initial business plan was approved by the OSL Sub-Committee (now the Sutton Shareholdings Board) on 4 August 2015, along with the Shareholder Agreement, enabling Sutton Decentralised Energy Network Limited to be established. Agenda Item 6 Page 10
3.2Since the approval of the 2016 Business Plan at OSL Sub-Committee (now the Sutton Shareholdings Board) progress has been made on both Phase 1 and Phase 2 of the network.
4. Issues
No amends to Risk Register
4.1There have been no amendments to the Risk Register since the previous Sutton Shareholdings Board on 8 March 2017.
Performance Update
5.1The performance update is attached at Appendix A – Sutton Decentralised Energy Network Performance Report dated February 2017 to May 2017.
6. Impacts and Implications
Financial
6.1In July 2013, the London Borough of Sutton’s Strategy and Resources Committee (S&R) approved the Conceptual Business Case for the development of a district heating network in Sutton, with funding of £4.5m.
6.2A detailed Financial Model for the Phase 1 Scheme was presented to the Housing, Economy and Business committee in March 2015. This demonstrated a positive cash flow of £1.54m from delivery of the scheme.
6.3The Financial Model has been revised to take account of the latest information on likely costs and revenues. As a result of the revisions the model shows an improved net positive cash flow on core assumptions of £1.64m. A review of the revised model by KPMG is in progress.
Legal
6.4This report seeks to update the Shareholdings Board and the recommendations which are before the Board do not give rise to any specific legal implications. Page 11 Agenda Item 6
7. Appendices and Background Documents
Appendix letter Title
A Sutton Decentralised Energy Network Limited Performance Report
Background documents
None
Audit Trail
Version Final 31 May 2017
Consultation with other officers
Finance Yes Phil Butlin
Legal Yes Padma Srinivasan
Equality Impact Assessment No N/A required? This page is intentionally left blank
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
SDEN Performance update: Appendix AAppendix | 88 KB | Download |
PDF |
SDEN Performance update: ReportReport | 113 KB | DownloadRead as text |
Follow Sutton Shareholdings Board at Sutton and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 10 Mar 2026 | MinutesRESOLVED : that the minutes of the meeting held on 4 November 2025 be agreed as an accurate record. | Agreed | Open |
| 10 Mar 2026 | Sutton Decentralised Energy Network (SDEN) Business Plan and BudgetThat the Sutton Decentralised Energy Network 2026-29 Business Plan and budget be approved. That the Sutton Decentrali... | Approved | Open |
| 10 Mar 2026 | Cognus Business Plan and BudgetThat the progress made by Cognus Limited against its 2025/28 Business Plan be noted. That the update on Cognus Limite... | Noted | Open |
| 10 Mar 2026 | Sutton Living Limited (SLL) 2026/27 Budget & Ten Year Business PlanThat Sutton Living Limited's updated business plan for the period 2026 to 2036 as set out at Appendix A, be approved.... | Approved | Open |
| 4 Nov 2025 | MinutesRESOLVED : that the minutes of the meeting held on 25 March 2025 be agreed as an accurate record. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.