RESOLVED : that 1. The performance updated contained in the Sutton Decentralised Energy Network performance report in Appendix A be noted. 2. The amendments to the Sutton Decentralised Energy Network Risk Register in Appendix B be noted. 3. It be agreed that Opportunity Sutton Limited approve as parent company that SDEN carries out capital works up to £200k, to enable a future connection to the development north of Hackbridge Station.
Word for word from the decision Sutton published for this meeting.Source: moderngov.sutton.gov.uk
1.1This report is presented for noting the update contained in the Sutton Decentralised Energy Network Performance Report and Risk Register as well as the approval of an extension to the Felnex pipe network to enable a future connection to the development north of Hackbridge Station.
Recommendations
The Sutton Shareholdings Board is recommended to:
2.1Note the performance update contained in the Sutton Decentralised Energy Network Performance Report in Appendix A.
2.2Note the amendments to the Sutton Decentralised Energy Network Risk Register in Appendix B. Agenda Item 7 Page 14
2.3Agree that Opportunity Sutton Limited approve as parent company that SDEN carries out capital works up to £200k, to enable a future connection to the development north of Hackbridge Station.
Background
3.1Following the Council’s decision in July 2014 to establish an Energy Services Company (ESCo), a detailed business model was prepared to demonstrate the commercial viability of the proposed company. The initial business plan was approved by the OSL Sub-Committee (now the Sutton Shareholdings Board) on 4 August 2015, along with the Shareholder Agreement, enabling Sutton Decentralised Energy Network Limited to be established.
3.2Since the approval of the 2016 Business Plan at OSL Sub-Committee (now the Sutton Shareholdings Board) progress has been made on both Phase 1 and Phase 2 of the network. Agreements have been signed with the heat supplier and homes are being built at the Felnex development.
3.3During the negotiation of the Connection and Supply Agreement (C&SA) with Barratts discussions took place regarding the need for SDEN to extend the on site main “spine pipework”, being laid by Barratt’s as a part of their obligations, to enable a future connection to customers along London Road. This is particularly key to SDEN’s future development plans as there is significant likelihood that a development on the North of Hackbridge Station will be brought forward in the near future and further details are provided in Appendix A.
4. Issues
Risk Register
4.1The Risk Register, attached in Appendix B, has been amended since the previous Sutton Shareholdings Board on 14 June 2017 and is appended in change mark form to show the changes made.
Options considered
Performance Update
5.1The performance update is attached at Appendix A – Sutton Decentralised Energy Network Performance Report dated March 2017 to July 2017.
6. Impacts and Implications
Financial
6.1In July 2013, the London Borough of Sutton’s Strategy and Resources Committee (S&R) approved the Conceptual Business Case for the development of a district heating network in Sutton, with funding of £4.5m. Page 15 Agenda Item 7
6.2A detailed Financial Model for the Phase 1 Scheme was presented to the Housing, Economy and Business committee in March 2015. This demonstrated a positive cash flow of £1.54m from delivery of the scheme.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Cognus Business Plan and BudgetThat the progress made by Cognus Limited against its 2025/28 Business Plan be noted. That the update on Cognus Limite...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.