Environment and Neighbourhood Committee noted this item on Thursday 1 February 2018. Below is the council's own wording, with the papers it was decided on.
RESOLVED that: Progress made on the Beddington Park project and the potential timeline revision due to the silt drying process be noted. It be agreed to delegate authority to the Strategic Director Environment, Housing and Regeneration to agree any further adjustments to the Beddington Park Heritage Lottery Fund project designs. The revised timeline for the Whitehall project be noted, and that the museum will reopen in summer 2018 with project activities continuing until 2020. It be noted the Glass Plate Negatives phase two project will be completed in September 2018.
Word for word from the decision Sutton published for this meeting.Source: moderngov.sutton.gov.uk
1.1In January 2013, Environment and Neighbourhood Committee agreed that eight bids should be considered for submission to the Heritage Lottery Fund (HLF). After further investigation, four were deemed viable and submitted to the HLF. On 30 March 2017 Environment and Neighbourhood Committee received a report and approved works to the projects.
1.2This report sets out the issues, changes and progress of the following projects:
1.3Beddington Park HLF - The final stage 2 application for Beddington Park was successfully submitted to HLF in February 2016 with the approval of Environment and Neighbourhood Committee.
1.4Whitehall HLF – The final stage 2 application for Whitehall was successfully submitted to HLF in Agenda Item 6 Page 26
March 2015 with the approval of full council.
1.5Glass Plate Negatives - project completed (with a grant of £96,300) and follow up project funding awarded of £95,000.
Recommendations
The Environment and Neighbourhood Committee is recommended to:
Beddington Park
2.1To note the progress made on the project and the potential timeline revision due to the silt drying process.
2.2Delegate authority to the Strategic Director Environment, Housing and Regeneration to agree any further adjustments to the Beddington Heritage Lottery Fund project designs.
Whitehall
2.3To note the revised timeline for the Whitehall project. The museum will reopen in summer 2018 with project activities continuing until 2020.
Glass Plate Negatives
2.4To note that the phase two project will be completed in September 2018.
Background
Beddington Park
3.1The Beddington Park HLF Stage two bid was submitted in February 2016 and was successful in gaining lottery funding of £3,260,400 towards a total project cost (development and delivery) of £3,835,440.
3.2As a pilot for ‘Citizen Led Commissioning’, officers continue to engage with stakeholders to gain an understanding and ownership of the project outcomes. A stakeholder steering group has been in place since the development stage.
3.3The project is based on five key themes established in the original commissioning and consultation; 1) Access safety and Infrastructure, 2) Activities and Events, 3) Wildlife, 4) History, 5) Lakes and Waterways. These have remained at the core of the project and have been developed to meet stakeholder needs and match the requirements of HLF.
Whitehall
3.4The Whitehall HLF project was submitted in March 2015 and was successful in gaining £1,522,300. A contribution required of the Council was £210,000.
3.5The costs of delivering the capital elements of the project were in excess of initial estimates and the project team worked closely with HLF and an application for a grant top-up of £367,000 was Page 27 Agenda Item 6
successful in December 2016, with additional funding from the Council of £138,400 being provided. Capital works will be completed in the spring of 2018 with the museum reopening in the summer 2018.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.