CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
London Borough of Sutton
Environment and Neighbourhood Committee, Thursday 1 February 2018 at 7.30pm

Local Implementation Plan Allocation 2018/19

Noted Committee 3 papers

Environment and Neighbourhood Committee noted this item on Thursday 1 February 2018. Below is the council's own wording, with the papers it was decided on.

Item32

Resolved

RESOLVED that: The changes in the LIP Settlement, from those originally indicated in the Annual Spending Submission Guidance papers issued by TfL in June 2017, and the impact the revised settlement on the delivery of the programme previously consulted be noted. It be noted further reductions will be needed to bring the work programme in line with the settlement. It be agreed to incur capital expenditure of £890,400 for the capital schemes identified in the LIP for Corridors and Neighbourhoods, £100,000 for Local LIP funding and £765,000 for Beddington North Major Scheme so that the projects can proceed. A sum of £169,000 for various revenue initiatives which has been approved for 2018/19 and is included in the revenue estimates. The specific funding circumstances attached to the profiling of the Beddington Major Scheme, as set out in paragraphs 3.9 to 3.10 be noted. It be agreed to authorise the Assistant Director Environment, Housing and Regeneration (Safer and Stronger Communities) to take all necessary steps to implement the schemes, including commencing any necessary statutory consultations.
Word for word from the decision Sutton published for this meeting. Source: moderngov.sutton.gov.uk

Follow this further

Built from Sutton's papers

What the report saysPro

Report to Environment and Neighbourhood Committee

Summary

1.1This report outlines Transport for London’s (TfL’s) funding settlement to the Council for Local Implementation Plan (LIP) funding in 2018/19. A description of TfL’s transport related programmes is given and how schemes were selected to be put forward for funding.

1.2The details of the specific indicative allocations for individual schemes are listed in Appendix A and described in the report. The Committee are specifically requested to note that the allocation detailed is lower that that bid for, and the report suggests how this reduction in the LIP settlement might be managed.

1.3TfL have advised that their current Business Plan has been prepared against the background of very challenging economic circumstances; their revenue grant from central Government has reduced by £700m from 2018/19 onwards. As a consequence, TfL are not able to provide funding as indicated in the initial 2018/19 Annual Spending Submission Guidance.

1.4Furthermore, TfL have also advised that funding for the Principal Road Maintenance, between 2018/19 and 2019/20 has been paused, which presents a further shortfall in funding.

1.5The revised settlement is significant enough to require a review of the LIP programme that has been previously consulted on. Such a review is ongoing and is focused towards identifying and delivering fewer, larger, more impactful schemes. Agenda Item 7 Page 34

1.6The revised settlement will also impact on the capacity of the Highways and Transport function, which is part of the Environment Service shared with the Royal Borough of Kingston Council. A review of the resources requirement to support the delivery of a smaller capital programme is ongoing, with the likelihood that excess capacity will also need to be removed.

Recommendations

The Environment and Neighbourhood Committee is recommended to:

2.1Note the changes in the LIP Settlement, from those originally indicated in the Annual Spending Submission Guidance papers issued by TfL in June 2017, and the impact the revised settlement on the delivery of the programme previously consulted.

2.2Agree that in light of the revised and reduced settlement from TfL, the schemes and measures as given in Appendix A provide the basis for the LIP work programme for 2018/2019, noting that the scheme list will need to be amended from that previously supported by the six Local Committees in Summer 2017, and recommended changes are set out in paragraph 4.5.

2.3Note that further reductions will be needed to bring the work programme in line with the settlement.

2.4Agree to incur capital expenditure of £890,400 for the capital schemes identified in the LIP for Corridors and Neighbourhoods, £100,000 for Local LIP funding and £765,000 for Beddington North Major Scheme so that the projects can proceed. A sum of £169,000 for various revenue initiatives which has been approved for 2018/19 and is included in the revenue estimates.

2.5Note the specific funding circumstances attached to the profiling of the Beddington Major Scheme, as set out in paragraphs 3.9 to 3.10.

2.6Authorise the Assistant Director Environment, Housing and Regeneration (Safer and Stronger Communities) to take all necessary steps to implement the schemes, including commencing any necessary statutory consultations.

Background

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
(7) Local Implementation Plan Settlement 2018-19Report 177 KB DownloadRead as text
PDF
(7) Local Implementation Plan Settlement 2018-19: Appendix AAppendix 100 KB Download
PDF
(7) Local Implementation Plan Settlement 2018-19: Appendix BAppendix 99 KB Download

At this meeting

Whole meeting

Who was there

9 of 10 attended
JW
Councillor Jill WhiteheadChair, present
MA
Councillor Manuel AbellanVice-Chair, present
RM
Councillor Richard MarstonCommittee Member, present
SP
Councillor Steve PenneckCommittee Member, present
NP
Councillor Nighat PirachaCommittee Member, present
PW
Councillor Paul WingfieldCommittee Member, present
HZ
Councillor Hanna ZuchowskaCommittee Member, present
PM
Councillor Patrick McManusCommittee Member, present
TS
Councillor Tony ShieldsCommittee Member, present
RC
Councillor Richard CliftonSubstitute, expected

On this subject at Sutton

Search all
  1. Local Implementation Plan Allocation 2018/19This decision
  2. Local Implementation Plan Allocation 20/21Noted
  3. Local Implementation Plan Schemes 2020/21Agreed
  4. 2020/21 Local Implementation Plan SchemesAgreed
  5. Local Implementation Plan (LIP)Agreed
  6. Local Implementation Plan (LIP)Agreed

More from Sutton Environment and Neighbourhood Committee

All decisions
MeetingDecisionOutcome
1 Oct 2020 Minutes of the previous meetingthat the minutes of the meeting held on 11 March 2020 be agreed as an accurate record. Agreed Open
1 Oct 2020 Any urgent businessthat 1. the petitions received regarding street cleansing and refuse collection in Wandle Valley ward, specifically t... Refused Open
1 Oct 2020 Petitions Regarding the Safer, Active, Greener Streets Schemethat 1. The petitions received regarding the streetspace schemes be noted 2. The following be noted: · the rationale ... Noted Open
1 Oct 2020 Authority to Consult on the Draft Sustainable Transport Strategy Supplementary Planning DocumentRESOLVED : 1. that the Draft Sustainable Transport Strategy 2020-2025 (STS) for public consultation be agreed. Agreed Open
1 Oct 2020 Environment Strategy 2020 Refresh and Climate Emergency Response PlanRESOLVED : that 1. the updated Environment Strategy be agreed 2. the Climate Emergency Response Plan be agreed 3. It ... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies